Shripati Lakhu Mane v. the Member Secretary, Maharashtra Water Supply and Sewerage Board & Ors.
V. RAMASUBRAMANIAN, J.
1. The plaintiff in a suit for recovery of money has come up with
the above appeal challenging the judgment and decree of the High Court
of Judicature at Bombay in a regular appeal under Section 96 of the
Code of Civil Procedure, 1908, by which the decree granted by the Trial
Court for recovery of Rs.24,97,077/- together with interest at 10% per
annum was modified into a decree for recovery of Rs.7,19,412/- together
with interest.
2. We have heard Mr.Vinay Navare, learned senior counsel for
the appellant, and Mr. Sunil Murarka, learned counsel for the respondents.
3. The appellant is a registered contractor with the Gove rnment
of Maharashtra. In a tender for the execution of the work of Regional
Rural Piped Water Supply Scheme for Dabhol-Bhopan and other villages
in Ratnagiri District, the appellant became the successful tender er. He
was issued with a work order on 03.07.1986, for the execution of the
work at the cost of Rs.80,45,034/-, which was 47% above the estimated
cost. The time for the completion of the work was stipulated as 30 months.
But it appears that Respondent No.3 herein issued a letter dated
28.07.1986 informing the appellant that the work order was kept i n
abeyance. After a few representations, Respondent No.3 inf ormed the
appellant vide letter dated 17.12.1986 to start the work.
4. Though the appellant started executing the work from
29.12.1986, he was informed about the non-availability of C-1 pipes and
cement pipes of the diameter stipulated in the contr act. Later, the
respondents wanted a change in the terms of the wor k order by
substituting pipes of different diameter. Therefore, the appellant started
demanding modified rate.
5. When the above dispute was brewing, Respondent No .3
instructed the appellant, vide letter dated 02.03.1987 to stop the pipeline
work and start the work of construction of another work at a dif ferent
SHRIPATI LAKHU MANE v. THE MEMBER SECRETARY, MAHARA SHTRA
WATER SUPPLY AND SEWERAGE BOARD
place namely Panchanadi. By another letter dated 04.03.1 987, the
Respondent No.2 informed the appellant about a modification whi ch
involved the construction of one head-work at Karjai and another at
Panchanadi. A work order dated 01.07.1987 was also issued in respect
of these head-works.
6. Compounding the agony of the appellant, the bills raised by him
were not honoured in time due to shortage of funds. Therefore, the
appellant did not proceed with the work. As a result, Respondent No.2
issued a threat to withdraw the work order and also to levy a fine of
Rs.10/- per day from 01.03.1988. Ever since then, the parties wer e at
loggerheads, which ultimately led to the appellant filing a suit for recovery
of a sum of Rs.51,35,289/-
7. The aforesaid claim of Rs.51,35,289/- comprised of several
heads of claim such as (i) value of the work done; (ii) release of the
security deposit; (iii) compensation; and (iv) damages etc.
8. Before the Trial Court, the appellant examined himself as PW-
1 and marked several documents as exhibits. On the side of the
respondents, 5 witnesses were examined as DWs 1 to 5 and the
respondents also marked several documents.
9. Eventually, the Trial Court, by a judgment and decree dated
02.02.1998 decreed the suit partially, directing the respondents to pay to
the appellant, a sum of Rs. 24,97,077/- together with interest at 10% per
annum from the date of the suit till realization.
10. Aggrieved by the decree so granted, the respondents file d a
regular civil appeal under Section 96 of the Code of Civil Procedur e,
1908 on the file of the High Court of Judicature at Bombay. The appellant
did not file any appeal though the suit was decreed partially.
11. By a judgment and decree dated 24.04.2009, impugned in this
appeal, the High Court allowed the appeal partially and reduce d the
decree amount to Rs.7,19,412/-. Therefore, the plaintiff has come up
with the above appeal.
12. Before we proceed to consider the grounds of attack and the
rival contentions, it will be useful to see the different heads of claims
made by the appellant before the Trial Court, the heads of claims and
the extent to which these heads of claims were allowed by the Trial
Court, and the heads of claims allowed by the High Court in the impugned
843
judgment. For easy appreciation, they are presented in a tabular column
as follows:-
13. As could be seen from the above table, what was allowed by
the Trial Court under three heads of claims namely, (i) the release of
security deposit to the tune of Rs.2,21,000; (ii) over-heads for the period
from January 1989 to 30.09.1990 to the tune of Rs. 5,63,115/-; and (iii)
loss of profits to the tune of Rs.9,73,250/-, were disallowed by the High
Court. Therefore, the appeal before us is actually confined only to these
3 heads of claims.
14. The main and perhaps the only reason why the High Court
rejected the claims under the aforesaid 3 heads, was that the appel lant
had abandoned the work under the main contract and that therefo re
neither the question of release of security deposit nor the q uestion of
payment of overheads nor the question of allowing a claim for loss of
profit, did arise. Therefore, the only issue that arises for consideration in
this appeal before us is as to whether there was abandonment o f work
by the appellant.
15. In order to see whether there was abandonment on the p art
of the appellant, it is necessary to have a look at the timeline of events,
as reflected by the documentary evidence on record. The timeline wa s
as follows:-
1 Though the amount totals to Rs. 24,77,027/-, the d ecree of the trial court was for Rs.
24,97,077/-
SHRIPATI LAKHU MANE v. THE MEMBER SECRETARY, MAHARA SHTRA
WATER SUPPLY AND SEWERAGE BOARD [V. RAMASUBRAMANIAN ]
(i) The work order was issued to the appellant on 03.07.1986 and
an agreement was registered. The agreement stipulated a period of 30
months for the completion of the work;
(ii) By a letter dated 28.07.1986, the respondents informed the
appellant that the execution of the work order shall be kept in abeyance.
Though no reason was indicated in the letter, the respondents took a
stand later that it was due to “administrative exigencies”;
(iii) After nearly 5 months, a letter dated 17.12.1986 was issued
directing the appellant to commence work;
(iv) While the case of the appellant was that his oblig ation to
commence the execution of the contract came into effect on 03.07.1986,
the case of the respondents in the written statement was that the date of
commencement of the work should be taken only as 17.12.1986, which
was the date on which the order for keeping the work-order in abeyance
was lifted;
(v) Within a few days, the appellant notified the respondents, about
the non-availability of C-1 pipes and cement pipes of the diameter
originally agreed. When the respondents wanted to replace the pipes
with pipes of different dimension, the appellant demanded a fresh rate to
be finalized, through a letter dated 20.02.1987. This fact is admitted in
paragraph 8 of the written statement;
(vi) Even before the issue raised in the letter dated 20.0 2.1987
could be resolved, the respondents issued another letter dated 02.03.1987
instructing the appellant to stop the pipeline work and start the work at
Panchanadi. Though the respondents claimed in paragraph 9 of their
written statement that the letter dated 02.03.1987 merely cal led upon
the appellant to concentrate on the construction of head-work, it i s
nevertheless admitted that the said letter contained the words, “please
be stopped”, in so far as the pipeline work is concerned;
(vii) According to the respondents, they issued a telegram dated
02.04.1987 calling upon the appellant to start the work of laying the
pipelines;
(viii) By a letter dated 04.03.1987, the plaintiff was informed that
the Scheme was undergoing modifications. While the appellant claimed
that the modification involved one head-work at Panchanadi and another
head-work at Karjai, the respondents claimed in paragraph 10 of the
845
written statement, that the head- work at Karjai, was already included in
the original tender itself. However, the respondents admitted that there
was at least one modification, imposed by their letter dated 04.03.1987;
(ix) The fact that the appellant sent a representat ion dated
04.11.1987 raising 2 issues namely [1] the issue of non-payment of bills
due to paucity of funds and [2] the issue of delay in sanction of the
modified rate already proposed on 20.02.1987 for the work of laying
pipes of different dimension, is admitted by the respondents in paragraph
11 of the written statement, though they disputed the correctness of the
contents of the said letter. Interestingly, the averments of the appellant
in paragraph 11 of the plaint about the reply dated 02.12.1987 in response
to the appellant’s representation dated 04.11.1987, was not at all d ealt
with by the respondents in paragraph 11 of their written statement;
(x) It was at this juncture, that Respondent No.3 issued a letter
dated 22.02.1988, imposing a fine of Rs.10/- per day w.e.f. the date of
the said letter. By this letter the appellant was also called upon to start
the work by 01.03.1988;
(xi) Despite the appellant’s objections, another let ter dated
22.03.1988 was issued, reiterating the proposal for imposing a fine and
calling upon the appellant to start work;
(xii) In fact, in the letter dated 22.03.1988, the respondents admitted
for the first time that the subject work was split into two parts and that
the proposed revised rates were as provided therein;
(xiii) Subsequently, there were several communications in April,
June, July and August, 1988 all of which pointed to a disagreement on
the revised rates on account of the modifications and the non-payment
of bills;
(xiv) While according to the appellant the execution of the work
under the contract was to commence on 03.07.1986 with a liability to
complete it by 03.01.1989, the contention of the respondents was that
the execution of the work was to commence only in December, 1986
and that therefore the liability to complete the work expired only in June,
1989;
(xv) However, admittedly, the respondents increased the fine
amount from Rs.10/- per day to Rs.25/- per day vide their letter dated
19.04.1989. By another letter dated 06.10.1989, the respondents informed
SHRIPATI LAKHU MANE v. THE MEMBER SECRETARY, MAHARA SHTRA
WATER SUPPLY AND SEWERAGE BOARD [V. RAMASUBRAMANIAN ]
the appellant that though the time for completion of the project expired
on 17.06.1989 and though the appellant did not ask for any extension, he
was being granted extension up to 31.12.1989.
16. The entire sequence of events narrated in the prec eding
paragraph would show that the appellant was not guilty of anything
including abandonment. Admittedly, Clause 3(a) of the contract enabled
the respondents to rescind the contract, forfeit the security deposit and
entrust the work to another contractor at the risk and c osts of the
appellant. This clause was never invoked by the respondents. Therefore,
we are surprised, especially in the light of the communicat ions from
February, 1988 up to October, 1989 as to how the High Court could have
found the appellant guilty of abandonment.
17. In fact, Section 67 of the Indian Contract Act, 1872 makes it
clear that if any promisee neglects or refuses to afford th e promisor
reasonable facilities for the performance of his promise, the promisor is
excused by such neglect or refusal. Section 67 together with the illustration
contained there under reads as follows:-
“67. Effect of neglect of promisee to afford promis or
reasonable facilities for performance. —If any promisee
neglects or refuses to afford the promisor reasonable facilities for
the performance of his promise, the promisor is excused by such
neglect or refusal as to any non-performance caused thereb y.”
Illustration
A contracts with B to repair B’s house.
B neglects or refuses to point out to A the places in whi ch his
house requires repair.
A is excused for the non-performance of the contract, if it is caused
by such neglect or refusal.”
18. In the case on hand, the respondents issued the work order on
03.07.1986 but directed the work order to be kept in abeyance by a
subsequent letter dated 28.07.1986. After this stalemate was lifted by a
letter dated 17.12.1986, two things happened namely, (i) a change in the
diameter of the pipes supplied by the respondents for carryi ng out the
contract; and (ii) request for the performance of additional work without
finalization of the modified rates. Therefore, the respondents cannot even
accuse the appellant of non-performance of the contract.
847
19. It is fundamental to the Law of Contract that whenever a
material alteration takes place in the terms of the origi nal contract, on
account of any act of omission or commission on the part of one of the
parties to the contract, it is open to the other party not to perform the
original contract. This will not amount to abandonment. Mor eover,
abandonment is normally understood, in the context of a right and not in
the context of a liability or obligation. A party to a contract may abandon
his rights under the contract leading to a plea of waiver by t he other
party, but there is no question of abandoning an obligation. In this case,
the appellant refused to perform his obligations under the wor k-order,
for reasons stated by him. This refusal to perform the obl igations, can
perhaps be termed as breach of contract and not abandonment.
20. It is interesting to note that the respondents did not choose, (i)
to allege breach of contract against the appellant; and (ii) consequently
to invoke the right to rescind the contract under cla use 3(a). The
respondents, if they were justified in doing so, could have taken recourse
to the remedy available under Section 75 of the Contract Act and sought
compensation for the damage sustained through the non-fulfillment of
the contract. On the contrary they attributed abandonment to the appellant
(without understanding the true purport of the word ‘abandonment’)
and refused to honour the claims made by the appellant.
21. The finding of the High Court that there was abandonment of
contract, was on the basis that after the second bill was cleared in May,
1987, the work under the main contract did not progress. This finding
goes completely contrary to yet another finding that the pe riod of the
contract was up to June, 1989 and that the respondents themselves granted
extension of time to complete the contract up to 31.12.1989, des pite
there being no request from the appellant. We fail to underst and as to
how a person who abandoned the contract in May, 1987 could be granted
extension of time up to December, 1989 on the very understanding of
the respondents that the contract was up to June, 1989. In fact, the High
Court recorded a finding in paragraph 9 of the impugned judgment that
according to DWs 3, 4 and 5, the power to rescind under clause 3(a) of
the tender was invoked and the security deposit forfeited. This was not
how the respondents pitched their claim even in the written statement.
In any case such a finding cannot co-exist with the specific stand of the
respondents that the period of contract was extended up to Dec ember,
1989.
SHRIPATI LAKHU MANE v. THE MEMBER SECRETARY, MAHARA SHTRA
WATER SUPPLY AND SEWERAGE BOARD [V. RAMASUBRAMANIAN ]
22. The refusal of a contractor to continue to execute the wo rk,
unless the reciprocal promises are performed by the other party, cannot
be termed as abandonment of contract. A refusal by one party to a
contract, may entitle the other party either to sue for breach or to rescind
the contract and sue on a quantum meruit for the work already done.
Paragraph 694 of Volume 9, Fourth Edition of Halsbury’s Laws of
England, may be usefully extracted to highlight the remedies available
to a party to the contract, if the other party absolutely refuses to perform
his part of the contract.
“694. Work done under a contract terminated for breach.
Where one party has absolutely refused to perform, or has rendered
himself incapable of performing, his part of the contract, he puts
in the power of the other party either to sue for a breach of it, or
to rescind the contract and sue on a quantum meruit for the work
actually done. Thus, where a publisher engaged an author to write
a work but abandoned the project, the author was entitle d to
recover reasonable remuneration without tendering the completed
work; and where a defendant wrongfully revoked the plaintiff’s
authority to sell his land after the latter had found a purchaser, the
plaintiff recovered reasonable remuneration for his work and labour
up to that date.
This type of quantum meruit claim is analogous to claims
for the repayment of money on total failure of consideration. In
both cases, the contract must be at an end before the claim can
be brought; but once the contract is at an end there is a logical
difficulty in saying that the claim is contractual.”
The respondents did not choose the option of rescinding the contract
and suing for damages in terms of clause 3 (a) and (b). It wa s the
respondents who made it difficult for the appellant to execute the contract
as per the terms originally agreed.
23. In the light of the above, we are of the view that the Hi gh
Court was clearly in error in overturning the judgment of the Trial Court
with regard to the aforesaid 3 heads of claims, on a wrong understanding
that there was abandonment of contract on the part of the appellant.
Hence this appeal is allowed. The impugned judgment and decree of the
High Court are set aside and the judgment and decree of the Trial Court
are restored. It appears that during the pendency of the first appeal
849
before the High Court, the respondents deposited a sum of Rs.42,98,168/
- towards the amount decreed by the Trial Court. As seen from paragraph
16 of the impugned judgment of the High Court, the amount deposited
by the respondents before the High Court was withdrawn by the appellant
on 13.01.1999 by furnishing a bank guarantee. Therefore, while modifying
the decree, the High Court directed the appellant to return the bal ance
amount, failing which the Trial Court was empowered to encash the
bank guarantee for the remainder amount. In view of this, while ordering
the issue of notice in the special leave petition and granting interim stay,
this Court directed the appellant to keep the bank guarantee alive. Now
that we are allowing the appeal setting aside the judgment of the Hi gh
Court and restoring the judgment of the Trial Court, the bank guarantee
shall stand discharged.
24. The appeal is allowed. There will be no order as to costs.