Delhi Development Authority v. Sunil Khatri & Ors.
HEMANT GUPTA, J.
1. The challenge in the present appeal is to an order d ated
22.12.2014 passed by the High Court of Delhi whereby an application
filed in the pending writ petition was allowed, holding that the acquisition
proceedings stand lapsed in view of Section 24(2) of the Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 20131.
2. The land of the respondents 2 measuring 14 Bigha 8 Biswa
comprising in Khasra No. 1883 (4-16), 1884 (4-16) and 1885 (4-16) at
village Chattarpur was notified under Section 4 of the Land Acquisition
Act, 18943, as required for the planned development of Delhi vide
notification dated 25.11.1980. The notification was in respect of lands
situated at Village Chattarpur, Satbari Maidangarhi, Sayoorpur and Rajpur
Khurd. The declarations under Section 6 of the Act were published on
27.5.1985, 6.6.1985, 7.6.1985 and 26.2.1986, and the award was announced
on 05.06.1987.
3. The process of acquisition initiated vide notifications dated
5.11.1980 and 25.11.1980 was challenged in a number of writ petitions
before the High Court and an interim order of stay of dispossession was
1 For short, the ‘2013 Act’
2 For short, the ‘land owners’
3 For short, the ‘Act’
73
granted. In the first bunch of writ petitions, the challeng e was to the
notification under Section 4 of the Act inter alia on the ground that the
notification was not for a public purpose. Such challenge was remained
unsuccessful on 15.11.1983 by a judgment reported as Munni Lal v. Lt.
Governor of Delhi 4.
4. Various writ petitions were thereafter filed to chal lenge the
notification under Section 6 of the Act on the ground that such notification
has been published after the time limit provided by Central Act No. 68 of
1984. The Full Bench of the High Court in a judgment dated 27.5.1987
reported as Balak Ram Gupta v. Union of India5held that the stay
of dispossession in one or the other writ petition is required to be taken
into consideration for determining the period of three years in publication
of the notification. The High Court held as under:
“39. We have, for the reasons stated above, come to the conclusion
that the period during which stay orders were in force should be
excluded in computing the validity of the declaration under S. 6.
So far as the notification dated 25- 11-80 is concerned, we find
that the latest of the S. 6 declarations was on 26-2-86. The stay
order (in C.M.P. 668/81) was in operation from 18-3 -81 to
15-11-83 i.e. for a period of 2 years, 7 months and 27 days. They
are therefore in time having been issued within three years plus 2
years 3 months, i.e., 5 years 3 months of the S. 4 notification. So
far as the notification dated 5-11-1980 is concerned, we find that
the latest of the S. 6 declaration was issued on 7-6- 1985, i.e., 4
years 7 months after the S. 4 notification. They stay order ( in
CMP 4226/81) was operative from 30-9-1981 to 15-11-1983, i.e.,
for 2 years and 11/2 months. If this period is exclude d the
declaration is within time. We answer the principal issue debated
before us accordingly.”
5. After deciding the question of law, the matter was ordered to
be placed before the appropriate Division Bench. The writ petitions were
decided by the Division Bench on 14.10.1988, when the operative order
was passed stating ‘reasons to follow’. The High Court upon recording
the reasons in a judgment reported as Shri B.R. Gupta v. Union of
India & Ors. 6on 18.11.1988, set aside the notification issued under
4 1983 SCC OnLine Del 321
5 For short, the ‘Balak Ram-I’, 1987 SCC OnLine Del 227 : AIR 1987 Del 239
6 For short, the ‘Balak Ram-II’, 1988 SCC OnLine Del 367 : (1989) 37 DLT 150 (DB)
DELHI DEVELOPMENT AUTHORITY v. SUNIL KHATRI &
ORS. [HEMANT GUPTA, J.]
Section 6 of the Act as the writ petitioner was neither given an opportunity
of personal hearing, nor was he actually heard in the objections filed by
the land owners under Section 5A of the Act and since there was no
record maintained for consideration of large number of objections filed
by the writ petitioners/land owners, it was held that the writ petitioner
whose land is being taken by the Government without his consent has a
right to know the reasons as to why his claim for exemption was being
declined. It was held as under:
“16. We may note that there are number of other contentions
raised by the petitioner in the writ petition apart from the ones
that are mentioned and considered above. We need not go into all
of them and given any finding, since we have already come to the
conclusion that reports under Section 5A and orders under Section
6 cannot be sustained in law on the basis of the contentions already
noted by us.”
6. In C.W.P. No. 2657/85 (Abhey Ram v. Union of India), an
order of status quo was passed by the High Court on 29.10.1985. The
writ petition was dismissed later on 2.9.1987 in view of the judgment in
Balak Ram-I. The land owners filed an appeal before this Court whereby
the order of status quo as to dispossession was passed on 25.3.1988. In
the final order, reported as Abhey Ram & Ors. v. Union of India &
Ors.7, the judgment in Balak Ram-I was maintained. This Court referred
to Balak Ram-II wherein it was found that the writ petitions were
allowed on 14.10.1998 by an operative order that ‘reasons to foll ow’.
This Court noticed that unfortunately, in Delhi Development Authority
v. Sudan Singh & Ors. 8, the operative part of the judgment was not
been brought to the notice of this Court. Therefore, the ratio therein has
no application to the facts in this case. A three judge Bench of this Court
held as under:
“12. It is true that a Bench of this Court has considered the effect
of such a quashing in Delhi Development Authority v. Sudan
Singh [(1997) 5 SCC 430 : (1991) 45 DLT 602] . But, unfortunately,
in that case the operative part of the judgment referred to earlier
has not been brought to the notice of this Court. Therefore, the
ratio therein has no application to the facts in this case............’’
7 (1997) 5 SCC 421
8 (1997) 5 SCC 430
75
7. The judgment in Sudan Singh was directed against an order of
the Delhi High Court in a judgment reported as Balbir Singh v. Union
of India & Ors.9. The High Court restrained the respondents on 6.1.1989
in Civil Writ Petition No. 51 of 1989 from dispossessing the petitioner
from the land in dispute or demolition of the building. The writ petition
was allowed on 21.4.1989 and the notification under Section 6 was
quashed as a whole. There was also a direction to handover physic al
possession of the land to the land owners on their depositing the
compensation amount disbursed to them along with interest.
8. In Brig. Gurdip Singh Uban v. Union of India 10, the Delhi
High Court was examining the acquisition of land in Village Chattarpur
vide notification dated 25.11.1980 under Section 4 of the Act. The High
Court quashed the notification under Section 6 of the Act. It was held as
under:
“27. The petitioners have urged before us that the judgement in
Balak Ram Gupta’s case has received the seal of approval of the
Supreme Court in 45 (1991) DLT (11) 602 (SC) (Delhi
Development Authority v. Sudan Singh) in para 4, wherein th e
Supreme Court has also said that the notifications with re spect
not to 11 villages, but 12 villages have been quashed.
28. In the light of the specific seal of approval by the Sup reme
Court in the aforesaid judgment, it is difficult to see how the Full
Bench judgement of the High Court in Balak Ram Gupta’s case
and Division Bench judgement in Balak Ram Gupta’s case is
not applicable to the instant case, particularly in view of the fact
that “notification”, are specifically treated as “l aw”, as
contemplated by Article 13(3)(a) of the Constitution of India. It
has been so held in (1985) 1 SCC 641. ( Indian Express
Newspapers (Bombay) Private Ltd. v. Union of India ). The
notifications being law, law having been quashed, and made
nugatory it enures for the benefit of all persons who are likely to
be affected by such law/notification.”
9. Furthermore, this Court in Delhi Administration v. Gurdip
Singh Uban & Ors.11allowed the appeal and set aside the judgment of the
High Court and it was held as under:
9 1989 SCC OnLine Del 211 : (1989) 39 DLT 233 (DB)
10 1996 SCC OnLine Del 879
11 For short, the ‘Gurdip Singh Uban-I’ (1999) 7 SCC 44
DELHI DEVELOPMENT AUTHORITY v. SUNIL KHATRI &
ORS. [HEMANT GUPTA, J.]
“7. We may state that it is true that in Sudan Singh’s case a two
Judge Bench of this Court confirmed another judgment of the Delhi
High Court wherein the High Court had allowed the writ petition
on the basis that the judgment of the Division Bench dated
18.11.1988 had quashed the Section 6 declaration wholly. It is
also true that in Sudan Singh’s case too no objections were filed
by the owners under section 5A. But, we are governed by the
judgment of the three Judge Bench in Abhey Ram’s case where
the said Bench not only referred to the effect of the Divisi on
Bench judgment of the High Court dated 18.11.1988 but also
referred to the judgment of the two Judge Bench of this Court in
Sudan Singh’s case. The three Judge Bench in Abhey Ram is
binding on us in preference to the judgment of two Judges i n
Sudan Singh”.
10. The land owners filed review petition against the order passed
in Gurdip Singh Uban-I inter-alia on the ground that on account of
conflict between Abhey Ram and Sudan Singh, matter should be placed
before larger Bench. Such review was dismissed on 24-11- 1999 in the
judgment reported as Delhi Administration v. Gurdip Singh Uban &
Ors.16. This Court held as under:
“45. It will be noticed that when Abhey Ram [(1997) 5 SCC 421]
was decided in the High Court, the Full Bench decision alone was
there and not the subsequent Division Bench judgment in Balak
Ram Gupta case. But by the time Abhey Ram case [(1997) 5
SCC 421] came up before the three learned Judges in this Court
on 20-8-1999, the latter order of the Division Bench dated 18-11-
1988 in Balak Ram Gupta [B.R. Gupta v. Union of India, (1989)
38 DLT 243 (DB) (order dated 18-11-1988)] was also available
and naturally the appellant raised a plea based on the latter order
of the Division Bench judgment dated 18-11-1988 which said that
the entire Section 5-A inquiry and the entire land acquisition
proceedings stood quashed. The appellant in Abhey Ram [(1997)
5 SCC 421], in our view, was certainly entitled to do so. His
contention was however repelled in Abhey Ram [(1997) 5 SCC
421] holding that notwithstanding the broad language used in the
latter reasoned order dated 18- 11-1988, its area of operat ion
was to be confined to what was stated by the same Divisio n
16 For short, the ‘Gurdip Singh Uban-II’, (2000) 7 SCC 296
77
Bench earlier on 14-10-1988 when a brief operative order w as
passed in the 73 cases allowing the writ petitions. We have already
held that the writ absolute dated 14-10-1988 in each case was
based on non-consideration of objections and not on the basis of
there being no public purpose and that the decision in each case
must, therefore, be confined to the land covered therein. The three-
Judge Bench in Abhey Ram [(1997) 5 SCC 421] held that the
reasoned order dated 18-11-1988 of the Division Bench could not
travel beyond the earlier operative order dated 14-10-1988 an d
could not have covered land other than the land involved in the
said batch of writ petitions. In our view, the question o f the
correctness or interpretation of the orders dated 14-10-1988 and
18-11- 1988 in Balak Ram Gupta was put in issue directly in
Abhey Ram [(1997) 5 SCC 421] in this Court and the said decision
in Abhey Ram [(1997) 5 SCC 421] can neither be characterised
as uncalled for nor as being obiter nor as a decision per incuriam.
Sudan Singh [(1997) 5 SCC 430] had not gone into this question
at all and would not help the applicant.”
11. In another bunch of writ petitions in Chatro Devi v. Union of
India12, the Hon’ble Judges of the Division Bench differed on the question
as to whether the objections filed under Section 5-A of the Act are required
to be decided only by the person who has provided the opportunity of
hearing. The matter was referred to a 3 rd Judge who held that where
objections have been filed and heard by one Collector and the report had
been submitted by another Collector, the proceedings stand vitiated for
being in violation of the principles of natural justice. Some of the land
owners in this matter were owners of land in Village Chattarpur wherein
there was interim order of stay of dispossession. Though the Hon’ble
Judges differed on the ground of hearing of objections filed by the land
owners, but in respect of all other issues, the Court held as under:
“33. The Division Bench judgment in the case of Balak Ram
Gupta (supra) no longer can be stated to be a good law in view
of the judgment of the Supreme Court in Abhey Ram’s case,
Gurdip Singh’s case as well as a recent Division Bench judgment
of this Court in the case of Sunil Nagpal v. Union of India, CW
838/86 decided on 17.12.2004 wherein similar writ petitions were
dismissed. The judgment of Sudan Singh (supra) was not
12 2005 SCC Online Delhi 279
DELHI DEVELOPMENT AUTHORITY v. SUNIL KHATRI &
ORS. [HEMANT GUPTA, J.]
approved by a Larger Bench of Supreme Court in Abhey Ram’s
case (supra). Thus, none of these two judgments can tilt either
the equity or the law in favour of the petitioners.
xxx xxx xxx
39. It is evident from the above discussion that larger number of,
writ petitions have been dismissed by the Courts and particularly
after pronouncement of the judgment of the Supreme Court in the
cases of Gurdip Singh and Abhey Ram (supra) even recently in
the Sunil Nagpal’s case (supra) number of writ petitions were
dismissed by another Division Bench of this Court. Wherever the
petitioners have been granted relief by different Division Bench
of this Court, it has been primarily by following the judgment of
the Division Bench in Balak Ram Gupta’s case (supra) and prior
to the pronouncement of the judgment of the Supreme Court in
the above referred cases. Even if one was to accept the contentions
raised on behalf of the petitioners, in my opinion, the petitioners
are not entitled to any relief in the facts and circumstances of the
present case.”
12. This Court in a judgment reported as Union of India v. Shiv
Raj13 dismissed the appeals arising out of Chatro Devi inter-alia on the
ground that the majority view of the High Court that objecti ons are
required to be decided by the same Collector who heard the objections is
correct. The said judgment however, relating to interpretation of Section
24(2) of the 2013 Act, was held to be not laying down good law in the
Constitution Bench judgment of this Court reported as Indore
Development Authority v. Manoharlal and Others. 14
13. In another set of appeals, this Court in a judgment reported as
Om Prakash v. Union of India and Others 15dismissed the appeals
of the land owners who had not filed objections under Secti on 5-A of
the Act. This Court relied upon Abhey Ram and Gurdip Singh
Uban-I held as under:
“54. It is emphasised by him that in the light of judgment of this
Court in Delhi Admn. v. Gurdip Singh Uban [(2000) 7 SCC
296] known as Gurdip Singh Uban-II [(2000) 7 SCC 296], all
13 (2014) 6 SCC 564
14 (2020) 8 SCC 129
15 (2010) 4 SCC 17
79
points having already been considered, no fresh look is required
by this Court. More so, when each and every point a rgued,
hammered and contended by the appellants has already been
decided against them. It was also submitted by him that i n the
name of unfair treatment, matters which stood closed either by
several judgments of this Court or of the Delhi High Court and
also keeping in mind that the land acquisition proceedings were
initiated in the year 1980, nothing more is required to be done and
the appeals deserve to be dismissed.
xxx xxx xxx
91. In the light of the foregoing discussion, more so, keeping in
mind the ratio of which stood concluded by a judgment of Bench
of three learned Judges of this Court in Abhey Ram [(1997) 5
SCC 421], we are of the opinion that it is not a fit case where we
are called upon to come to a different conclusion that subsequent
declaration issued under Section 6 was beyond the period of
limitation. Fact situation does not warrant us to do so.”
14. In Manohar Lal Atree v. Union of India & Ors. 16, the
challenge was to the acquisition of land situated in Village Satbari. On
27.7.1990, the Division Bench passed an interim ord er that any
development activity undertaken on the land in question will be at the risk
and cost of the respondents. However, the writ petition was allowed on
6.12.1990 relying upon Balbir Singh that the notification under Section
6 of the Act stands quashed. There was also a direction for restoration
of possession and on payment by the land owners of the compensation
disbursed.
15. The respondents-land owners in Smt. Sheila Khatri & Ors.
v. Union of India & Ors.17, in the writ petition filed in the year 1999,
alleged that the notification under Section 6 of the Act stands quashed
and therefore, the award in respect of land of the land owne rs was
illegal. The land owners challenged the Section 6 notification and that no
further proceedings could be taken under Section 11-A of the Act on the
basis of the existing Section 4 notification. The land owners made reference
to Writ Petition No. 2478 of 1985 ( Moohul Transport Company Pvt.
Ltd. v. Union of India) wherein it was held that the entire land covered
16 Civil Writ Petition No. 2364 of 1990 decided on 6.12.1990
17 Civil Writ Petition No. 1786 of 1998
DELHI DEVELOPMENT AUTHORITY v. SUNIL KHATRI &
ORS. [HEMANT GUPTA, J.]
by that notification stands de-acquired. The land owners also m ade
reference to Balbir Singh wherein a direction was issued to handover
the vacant possession of land to all those persons who have received
compensation and the land owners were directed to return/re fund the
compensation received by them along with interest. The land owners
have averred to the following effect:
“16. That it is submitted that all the above mentioned judgements
passed by this Court in CWP No. 1639 of 1985 dated 18.11.1989
(Balak Ram II) dated 16.5.1989 in CWP No. 51 of 1989 (Balbir
Singh) and judgement dated 6th December, 1990 in Civil Writ
Petition No. 2364 of 1990 (Manohar Lal Atree) applies squarely
to the case of the petitioners in the present writ petition. In view
of the above mentioned legal position, the land in question owned
and possessed by the petitioners are free from acqu isition
proceedings and the petitioners are the lawful owners in actua l
physical possession of the said land.”
(Names Mentioned for easy identification of the cases)
16. The land owners contended that the objections dated 2.12.1980
were found in the old records left by late Shri K.C. Khatri, t herefore,
they have reason to believe that objections were filed by the deceased
K.C. Khatri. We may state that there is no categorical assertion of filing
of such objections, therefore, the reason to believe that objections were
filed is not conclusive. Still further, even if such objections were filed,
neither Shri K.C. Khatri nor his legal heirs have disputed the acquisition
proceedings on the ground of non-consideration of such objections before
announcing of the award bearing No. 15/87-88 on 5.6.1987. The land
owners have also referred to an order passed by the Division Bench of
the High Court on 17.12.1996 in the case of Brig. Gurdeep Singh Uban
holding that once the acquisition proceedings were quashed in a writ
petition, the entire proceedings fall through.
17. According to the appellant, there was a stay of dispossession
operating in one or the other writ petition, even after decision of Balak
Ram-II on 14.10.1988/ 18.11.1988. Thereafter, the Delhi High Court in
Balbir Singh, Gurdeep Singh Uban and in various other judgments
had taken a view that the entire acquisition proceedings shall stand
quashed. However, the issue was clarified by this Court in Abhey Ram
on 22.4.1997 and Gurdip Singh Uban-I and II on 20.8.1999 and
81
18.8.2000 respectively. Therefore, there was an era of uncertainty about
the status of acquisition proceedings in view of either sta y operating
against the appellant or on account of setting aside of the notification under
Section 6 of the Act. It was only the issue of the validity of notification
under Section 6 of the Act which attained finality when Gurdip Singh
Uban-II was decided. Thus, the period of five years had not expired
before the commencement of the 2013 Act with effect from 1.1.2014.
18. Mr. Bansal, learned counsel for the land owners vehemently
argued that there is specific provision for exclusion of ti me if stay is
operating in another writ petition in terms of Explanation 2 in Section 6
of the Act and the Explanation in Section 11-A of the Act, but there is no
corresponding exclusion clause in Section 24(2) of the 2013 Act.
Therefore, it was contended that the period of stay can ver y well be
excluded for publication of a notification under Section 6 or for announcing
the award but not after the award, on the strength of the interim orders
passed in the writ petition of other land owners. Therefore, after the
expiry of five years before the status-quo order was passed in favour of
the land owners, the proceedings had lapsed in terms of Section 24(2) of
2013 Act. It was contended that stay granted in the writ petitions filed
by other land owners cannot be used by the State for excluding su ch
period in the case of the land owners herein.
19. Learned counsel for the land owners further argued that the
award was announced on 5.6.1987 and the interim order in favour of the
land owners was passed on 9.7.1999. Thus, for a period of 12 years
from the date of making of the award, there was no stay by the Court or
by giving effect to any statutory provision of the Act granting such stay
under Section 24(2) of the 2013 Act. It was contended that the State has
been taking possession on different dates, therefore, it cannot be inferred
that the stay in one or the other case was deterrent for the appellant to
take possession of the land which was subject matter of acquisition. The
land owners have made elaborate reference on the undisputed principle
that the judgment is an authority for what it actually deci des and not
what follows from it, i.e., what is meant by obiter dictum and ratio
decidendi. It was also argued that the Casus Omissus cannot be supplied
by including further words in the statute.
20. We have heard learned the Counsel for the parties and fi nd
that the appeal deserves to be allowed. The aforementioned judgments
have been thoroughly examined by this Court in Om Prakash. The
DELHI DEVELOPMENT AUTHORITY v. SUNIL KHATRI &
ORS. [HEMANT GUPTA, J.]
judgments in Balbir Singh and Gurdeep Singh Uban were again
recently examined by this Court in Delhi Development Authority v.
Godfrey Phillips (I) Ltd. & Ors.18decided on 6.5.2022, wherein it was
held as under:
“36. In Balak Ram-II, the acquisition proceedings were quashed
since the objections filed by the land owners were not h eard or
decided in accordance with law. Thus, Balak Ram-II is a
judgment in personam and not in rem, as the grievance of the writ
petitioners was specific to them. The judgment of the High Court
in Balbir Singh is based upon the fact that in Balak Ram-II, the
entire notification under Section 6 of the Act stands quashed. Such
aspect has not found favor in Abhey Ram and Gurdip Singh
Uban-I and II. Otherwise also, non-hearing of objections filed
would be limited to those land owners who have filed objections.
The predecessor-in-interest of the purchaser has not filed a ny
objections under Section 5A of the Act, therefore, the judgment in
Balak Ram-II cannot come to the aid of land owners who have
never preferred any objections.
37. Therefore, the judgment in Balbir Singh does not confer any
right on the other land owners who have not disputed the acquisition
proceedings on the ground of lack of effective hear ing of
objections under Section 5-A of the Act. Since the original land
owner never filed any objections under Section 5-A of the Act,
the purchaser cannot seek the relief which was not available even
to the original land owner.
38. The purchaser has purchased the property knowing fully well
that the vendor has not disputed the acquisition proceedings. But
on the basis of an order passed in Balbir Singh, it was conveyed
and accepted by the purchaser, that the acquisition stands quashed
and original land owner was in possession of the land. Since Sudan
Singh, affirming the order in Balbir Singh has not been approved
by this Court in the three judgments referred hereinabove (Abhey
Ram, Gurdip Singh Uban-I and Gurdip Singh Uban-II), no
right would accrue to the original land owner or the purchaser.
The High Court in the impugned order has not noticed any of the
three judgments of this Court in Abhey Ram, Gurdip Singh Uban-
18 Civil Appeal No. 3073 of 2022
83
I and Gurdip Singh Uban-II nullifying the effect of Balbir Singh
and instead ordered the purchaser to deposit twice of the amount
paid to the original land owner. The condition of payment of
compensation in Balbir Singh by the land owners does not survive
in view of the fact that such judgment has not been approved by
this Court.”
21. In the writ petition filed by the land owners, there w as an
interim order of stay granted on 9.7.1999, even before Gurdip Singh
Uban-I was decided on 20.8.1999. The notifications under Section 6 of
the Act which were quashed became effective only after t he order of
this Court in Gurdip Singh Uban-I and II. The land owner strangely
made no mention of the judgment delivered on 22.4.1997 in Abhey Ram.
The order of stay of dispossession in the writ petition filed by the land
owner continued when the 2013 Act came into force. The land whic h
was the subject matter of challenge in Gurdip Singh Uban19was also
at Village Chattarpur, even before the Award was announced. There
was an interim order of stay of dispossession on 28.4.1986 in respect of
land situated in the village Chattarpur which continued till such time the
notification under Section 6 of the Act was quashed relying upon Balbir
Singh decided on 15.05.1989 and Sudan Singh. This order was set
aside by this Court on 20.8.1999 in Gurdip Singh Uban I. The land
owner had got stay in their writ petition on 9.7.1999. Thus, there was no
stay free period of 5 years before coming into force of the 2013 Act.
22. It is to be noted that since the entire notification was quashed
by the High Court in Gurdip Singh and Balbir Singh, therefore, the
State could not take possession on the basis of quashed notification. But
before the judgments of this Court were pronounced in the year 1999 or
2000, the land owner had obtained stay of dispossession. Therefore, it is
not a stay of dispossession pending notification under Section 6 or award
under Section 11-A but the acquisition of the entire land which came to
be settled by this Court. Thus, the State could not take possession on the
basis of a notification under Section 6 leading to the award on 05.06.1987.
The argument that there was no stay from the date of the award till the
stay was granted in favour of the land owner is hence partly correct as
there was no stay but the acquisition itself stood quashed. The refore,
when the 2013 Act came into force on 01.01.2014, the five years ha d
not lapsed which was stay free or free from setting aside of the acquisition.
19 WP (C) No. 920 of 1986 decided on 17.12.1996
DELHI DEVELOPMENT AUTHORITY v. SUNIL KHATRI &
ORS. [HEMANT GUPTA, J.]
23. Learned counsel for the land owners has referred to a counter
affidavit dated 9.7.2018 filed by the State in Mrs. Verinder Kaur v.
Government of NCT of Delhi 20 to the effect that the amount of
compensation in respect of village Chattarpur was withd rawn for the
purpose of award in village Kakrola. However, the said wri t petition
was dismissed by the Division Bench of the High Court inter alia on
the ground that the petitioner did not challenge the acquisition proceedings
for more than 3 decades. It was held as under:
“The fact of the matter is that as far as the Petitioner is concerned
she never came forward to challenge the land acquis ition
proceedings at any stage. While certain others came to the Court
and got interim orders in their favour, the Petitioner did not challenge
the proceedings at any stage. The inability of the Respondents to
take possession is explained by the fact that an interim order was
passed in one set of petitions which continued for a long time.
Interfering with the land acquisition proceedings at this stage when
the Petitioner has not shown any interest in challenging them for
more than three decades would encourage an abuse of the process
of law. Entertaining the petition would be contrary to the decision
by a three Judge Bench of the Supreme Court in Indore
Development Authority v. Shailendra (2018) 3 SCC 412 .”
24. In another judgment of this Court reported as Delhi
Development Authority v. Rajan Sood21, the land owner had the benefit
of stay in his favour when the 2013 Act came into force. Ther e was a
direction issued in the writ petition filed by the land owner on 9.11.2011 to
consider the application under Section 48 of the Act. It was held that
Section 48 of the Act would be applicable as the possession of land is not
taken over by the acquiring authority and thus the land owners would be
deemed to be in possession of the same. It was held as under:
“7.1 … It is the case on behalf of the original writ peti tioners
that a purported letter dated 23.09.1986 allegedly taking symbolic
possession was never disclosed by appellants in the proceedings
conducted before the High Court on two separate occasions and
the same has been filed for the first time in the present proceedings.
The aforesaid is not correct. Even in the impugned order itself in
20 WP (C) No. 589 of 2018 decided on 13.8.2019
21 Civil Appeal No. 1927 of 2022 Decided on 29.3.2022
85
paragraph 2, the High Court has noted the submissions on behalf
of the appellants to the effect that the possession was taken over
on 23.09.1986. Therefore, it cannot be said such a plea is taken
for the first time before this Court. It is the case on behalf of the
original writ petitioners, relying upon the earlier order passed by
the High Court dated 09.11.2011 in writ petition No. 7714/2011
that, the original writ petitioners continue to be in possession and
the actual possession has never been taken over. However, it is
required to be noted that even in the order dated 09.11.2011, there
was no specific finding given by the High Court that the original
writ petitioners are in possession of the land in question. On the
contrary, it is observed that the authority to consider the application
under section 48 of the Act, 1894 on merits on the assumption of
the possession being with the original writ petitioners. Therefore,
while passing the order dated 09.11.2011 also, the High Court
assumed the original writ petitioners are in possession hence as
such no specific finding was given to the effect that the original
writ petitioners are in possession.
xx xx xx
7.3 Be that as it may. Assuming for the sake of argument that the
original writ petitioners are found to be in possession a nd the
compensation was not tendered, in that case also as can be seen
from the order passed by the High Court on 09.11.2011 in writ
petition No. 7714/2011, the authority was restrained from taking
any coercive action in respect of the land in question. Therefore,
in view of the subsequent decision of this Court in the c ase of
Indore Development Authority (supra - paragraph 366.8), the
period, during which the interim order is/was operative, has to be
excluded in the computation of five years’ period. In the present
case even, it is the contention on behalf of the original writ petitioners
that the order of no coercive action was directed to be continued
till the application under section 48 of the Act, 1894 was decided.”
25. In another judgment in Delhi Development Authority v. Bhim
Sain Goel & Ors.22, notifications dated 21.3.2003 and 18.3.2004 under
Sections 4 and 6 of the Act respectively were the subject m atter of
consideration. The award was passed by the Land Acquisition Collector
on 22.8.2005. In a writ petition filed challenging the Section 6 notification,
22 Civil Appeal No. 3151 of 2022 passed by this Court on 25.4.2022
DELHI DEVELOPMENT AUTHORITY v. SUNIL KHATRI &
ORS. [HEMANT GUPTA, J.]
the High Court directed to maintain status quo with regard to nature, title
and possession of the land in question. The writ petition was dismissed
but in appeal before this Court, there was an interim order of stay. During
the pendency of the appeal, the 2013 Act came to be enacted. The land
owners filed a writ petition to declare the proceedings as lapsed. Such
writ petition was allowed on 2.2.2016 which was then challenged before
this Court. This Court held as under:
“12. On the application of the aforesaid principles to the facts of
this case, there cannot be any doubt that the respondents cannot
take shelter under Section 24(2) of the 2013 Act. This is for the
simple reason that it is by their conduct in approaching the Courts
and obtaining interim orders that the appellant was prevented from
taking possession of the lands. We are clear in our minds that this
is indeed one such case where the respondents have launched
litigation, obtained orders and it has clearly prevented the appellant
from taking possession and therefore, the impugned judgment of
the High Court would have to be set aside.
xx xx xx
22. The principle which has appealed to the Constitution Bench of
this Court is squarely applicable to the facts of this ca se. The
public authority which had set the law in motion under the earlier
regime cannot be put to a loss when at the end of the day or on
the day of reckoning it is found that they must succeed in l aw.
Here we have found that the appellant is fully justified in contending
that but for the orders passed by the High Court and this Court,
the possession would have been taken, and the land would have
vested under the law. We must proceed on the basis that but for
the interim orders passed which cannot survive the final disposal
of the cases, the land would have stood vested with the Government
under the earlier regime…
xx xx xx
24. It is clear as daylight that it would be completely antithetical
to public interest were the Government be compelled to shell out
public funds under the 2013 Act to acquire land which already
belongs to it. We cannot be oblivious to the said sublime principle
as well.”
87
26. Pertinent to note, though the High Court in Balak Ram-II had
not quashed the notification under Section 6 of the Act, but in some of the
subsequent judgments such as in Balbir Singh, the High Court held that
the notification stands quashed and the land stood reverted back to the
land owners. Therefore, an option was given to the land owners to refund
the compensation. Such judgment of Balbir Singh was affirmed by this
Court in Delhi Development Authority v. Sudan Singh23. Delhi High
Court in Gurdip Singh Uban etc. relied upon Sudan Singh to hold that
the notification under Section 6 of the Act stands quashed. However,
Sudan Singh was specifically found to be laying down not good law in
Abhey Ram, Gurdip Singh Uban-I and Gurdip Singh Uban-II. There
was a stay in the writ petition filed by the land owners themselves which
continued to operate till the 2013 Act came into force. Therefore, it was
the order of the High Court itself which prevented the appellant to take
possession. However, such position got clarified only after the judgment
in Gurdip Singh Uban-I, later clarified in Gurdip Singh Uban-II, but
in the meantime, there was an interim order granted in favour of the land
owners.
27. This Court in Indore Development Authority v. Manoharlal
and Others24held that the twin conditions of failure to take possession
or payment of compensation alone can lead to the lapse of notification
under Section 24(2) of the 2013 Act. This Court has held as under:
“306. When the authorities are disabled from performing duties
due to impossibility, would be a good excuse for them to save
them from rigour of provisions of Section 24(2). A litigant may be
right or wrong. He cannot be permitted to take advantage of a
situation created by him of interim order. The doctrine “commodum
ex injuria sua nemo habere debet” that is convenience cann ot
accrue to a party from his own wrong. Provisions of Section 24
do not discriminate litigants or non-litigants and treat them
differently with respect to the same acquisition, ot herwise,
anomalous results may occur and provisions may becom e
discriminatory in itself.
307. In Union of India v. Shiv Raj [Union of India v. Shiv Raj,
(2014) 6 SCC 564 : (2014) 3 SCC (Civ) 607] , this Court did not
23 (1997) 5 SCC 430
24 (2020) 8 SCC 129
DELHI DEVELOPMENT AUTHORITY v. SUNIL KHATRI &
ORS. [HEMANT GUPTA, J.]
consider the question of exclusion of the time. In Karnail Kaur v.
State of Punjab [Karnail Kaur v. State of Punjab, (2015) 3 SCC
206 : (2015) 2 SCC (Civ) 259] and in Sree Balaji Nagar Residential
Assn. [Sree Balaji Nagar Residential Assn. v. State of T.N., (2015)
3 SCC 353 : (2015) 2 SCC (Civ) 298], various aspects including
the interpretation of provisions of Section 24 were not taken into
consideration. Thus, the said rulings cannot be said to be laying
down good law.
xx xx xx
314. The maxim “lex non cogit ad impossibilia” means that the
law does not expect the performance of the impossible. Though
payment is possible but the logic of payment is relevant. There are
cases in which compensation was tendered, but refused and then
deposited in the treasury. There was litigation in court, which was
pending (or in some cases, decided); earlier refere nces for
enhancement of compensation were sought and compensation was
enhanced. There was no challenge to acquisition proceedings or
taking possession, etc. In pending matters in this Court or in the
High Court even in proceedings relating to compensation, Section
24(2) was invoked to state that proceedings have lapsed due to
non-deposit of compensation in the court or to deposit in the
treasury or otherwise due to interim order of the court needf ul
could not be done, as such proceedings should lapse.
xx xx xx
316. Another Roman Law maxim “nemo tenetur ad impossibilia”,
means no one is bound to do an impossibility. Though such acts of
taking possession and disbursement of compensation are n ot
impossible, yet they are not capable of law performance, during
subsistence of a court’s order; the order has to be complied with
and cannot be violated. Thus, on equitable principles also, such a
period has to be excluded........................“
28. Therefore, the period of 5 years had not lapsed on 1.1.2014
which could lead to lapsing of the acquisition proceedings. The appellant
was prevented by the interim orders in a number of writ petitions filed to
take possession. Therefore, prior to the commencement of 2013 A ct,
there was no stay free period of 5 years which could lead to a declaration
that the proceedings stand lapsed. Still further, the notifications under
89
Section 6 of the Act quashed on 15.5.1989 and 17.12.1996 were set
aside in Gurdip Singh Uban-I and II but before that, there was an
order of stay of dispossession granted in favour of the land ow ner on
27.9.1999. Therefore, on account of setting aside of notification under
Section 6 of the Act, the State could not take possession in view of the
orders passed by the High Court.
29. In view of the above, the appeal is allowed. The order passed
by the High Court is set aside and the writ petition filed by the land
owners is dismissed.
Nidhi Jain Appeal allowed.
(Assisted by : Tamana, LCRA)
DELHI DEVELOPMENT AUTHORITY v. SUNIL KHATRI &