M. P. Power Management Company Limited, Jabalpur v. M/S. Sky Power Southeast Solar India Private Limited & Others
K. M. JOSEPH, J.
1. Leave granted.
2. The appellant impugns the Judgment of the High Court dated
27.02.2020 in Writ Petition No. 420 of 2019. It further challenges t he
Order dated 28.12.2020 in Review Petition No. 682 of 2020. By the said
Judgment in the Writ Petition, the High Court allowed the Writ Petition
filed by the first respondent and quashed the Order dated 07 .07.2018,
which was passed by the appellant, terminating the Power Purchase
Agreement (hereinafter referred to as ‘the PPA’, for short), which was
entered into by the appellant and the first respondent. The review filed
by the appellant was dismissed. Hence the appeals.
THE FACTS
3. The appellant, which is “a wholly owned company of t he
Government of Madhya Pradesh” (as described by the appellant in the
Special Leave Petition), is responsible for the bulk purchase of electricity
in the State of Madhya Pradesh for onward sale/supply to the distribution
utilities (DISCOMS). The appellant issued a request for proposal (RFP)
dated 06.05.2015 for long-term procurement of 300 MW of solar energy
through tariff-based competitive bidding. The bid of M/s Sky Power
Southeast Asia Holding Limited was accepted. It was de clared the
successful bidder for three units of 50 MW each at different tariff rates.
The bidder subsequently incorporated the first respondent, viz ., M/s Sky
Power Southeast Solar India Private Limited as a spe cial purpose
company. This was for developing one project of 50 MW. The rate,
which is applicable in respect of the first respondent, was Rs.5.109 per
unit. In respect of the other two bids, the bidder incorporate d other
companies, viz., M/s Sky Power Solar India Private Limited and M/s
Sky Power Southeast Asia One Private Limited. The rates applicable in
respect of said companies for the other two projects consist ing of 50
MW each was Rs.5.298 per unit and Rs.5.051 per unit, respectiv ely.
The PPA was entered into on 18.09.2015. The agreement, inter alia ,
provided for pre-commissioning activities. They are described as
satisfaction of conditions subsequent by the seller. The first respondent
is the seller under the PPA.
4. The Agreement contemplated completion of the conditions
subsequent, within a period of 210 days. In other words, the Agreement,
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD.
admittedly, provided that the first respondent was to achieve fulfilment
of conditions subsequent by 15.04.2016. The Agreeme nt further
contemplates an extension of the period of fulfilment of the condition
subsequent on payment of penalty for a further period of nine months.
Thus, calculating 210 days and an additional nine months from 18.09.2015,
which is the date of the PPA, the period would come to an e nd on
15.01.2017. A communication was addressed dated 12.01.2017 by the
first respondent. The first respondent purported to refer to Article 2.1 of
the PPA, which, inter alia , reads as follows:
“Article 2.1 Seller agrees and undertaken to duly perform and
complete all of the following activities seller’s own cost and risk
within 210 days from the effective Date unless such completion
is affected by any force Majeure event, or if any of the Effective
is specifically waived in writing by MPPMCL:
a) The Seller shall obtain all Consents, Clearance and Perm its
required for supply of Power to MPPMCL as per the terms of
this Agreement;”
5. The first respondent purported to present certain documents
and contend that there was compliance of its obligations under the PPA.
This led to communication dated 22.02.2017 addressed by the appellant
to the first respondent. It referred to the status of the documents, which
the appellant noted. Furthermore, appellant sought certain documents. It
is, inter alia , pointed out by the appellant that the first respondent had
no documents in regard to 34.12 hectare of land and an unregiste red
lease deed for only 12 months was submitted, which co uld not be
considered as fulfilment of the condition subsequent. Thereafter, it was
stated that the PPA is liable to be terminated in terms of Article 2.5.1 of
the PPA. Explanation/justification if any was called for f rom the first
respondent. Acting on the request of the first respondent, the appellant
granted time for response of the first respondent till 10.03.2 017. The
response, which was given on 10.03.2017, reads as follows:
“Firstly, we are thrilled to update you that the project is under
advanced construction and all equipment order for the projec t
have been placed and construction happening on site we exp ect
that the project will be top quality using the best equipment in the
market and constructed by a top-tier EPC, for the benefit of both
Sky Power and the state of MP .
11
1. Satisfaction of Condition subsequent regarding Constructi on
Financing
MPPMCL Comment: “Loan sanction letter of Mis L&T Finance
vide letter No. S07201A03/16-17 DATED 29.08.2016 Copy of
facility agreement and affecting compliance documents as stated
in above letters are required to be submitted”
SKY POWER comment: reference is made to paragraph 2.1.1.(b)
of the PPA, reproduced below:
Sd/-
D.G .M. (Commerical-3)
R.0. MPMCL, Bhopal”
6. Thereafter, the first respondent sent communicatio n dated
14.03.2017. It reads as follows:
“SKY POWER GLOBAL
March 14, 2017
To,
The Managing Director
MP Power Management Company Limited
Bittan Market,
Bhopal-462016
Attention :Chief General Manager Commercial, MPPMC, Jabalpur.
Ref: Submission of Documents to MP Power Management
Company limited (“MPPMCL”) for fulfilment of Condition s
subsequent by SkyPower southeast solar India private Limite d
(“Sky Power”)
Reference: 1. Sky Poer Letter dated 10 March 2017,
2. Sky Power Letter SKP2/MP/SOLAR MPPMCL/2015-16/06
dated 12 Jan 2017
3. Agreement (PPA) dated September 18, 2015 between
MPPMCL and Skypower
Dear Sir,
Further to our office letter dated 10 March 2017 & skyP2/MP/
SOLAR/MPPMCL/2015-16/06 dated 12 Jan 2017 we hereby
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. L TD. [K. M. JOSEPH, J.]
submit that we have completed the entire acquisition for land 29,
85 Acres including balance 87.S Acres of land parcels.
The relevant land registration documents have been enclosed for
your perusal
We hereby submit that we have duly completed land registration
for 249,85 Acer for the project
Thanking you in anticipation.
MIS SKYPOWER SOUTHEAST SOLAR INDIA PRIVATE
LIMITED
Sd/- Shivani Jhariya
(Authorized Signatory)
Sd/-
D.G.M. (Commerical-3)
R.O. MPMCL, Bhopal”
7. After a gap of nearly five months, the next date, which is invoked
by the appellant, is 09.08.2017. It is the case of the appellant that as the
first respondent had failed to comply with the conditions subsequent, by
misrepresentation and manipulation, it purported to obtain approval from
the Chief Electrical Inspector General (CEIG) under Regulation 32 of
the Central Electricity Authority (Measures relating to safety and
electricity supply) Regulation, 2010 read with Section 162 of the Act.
According to the appellant, the Report of the CEIG came to the
knowledge of the appellant on 20.08.2017. Prior to the said date, the
appellant purported to terminate the PPA in terms of Article 2.5.1(d) of
the PPA, considering it to be mandatory by communica tion dated
11.08.2017. In short, according to the appellant, as the maximum period,
within which, the conditions subsequent, had to be fulfilled, had run out
on 15.01.2017, under the PPA, the appellant had no other option but to
terminate the Agreement. This led to the first Writ Petition filed by the
first respondent. The said Writ Petition, viz ., Writ Petition No. 12880 of
2017, came to be allowed by the High Court by Judgme nt dated
20.06.2018. The relevant portion of the Judgment reads as follows:
“2. The contract has been terminated on account of 54 days delay
in achieving the first milestone i.e., procurement of land, financial
closure and necessary permissions from the competent authority
13
within 210 days from the date of execution of agreement for
completing the first part of the project. The only reason to terminate
the agreement is that the petitioner has failed to achieve first
milestone within 210 days though the condition of - procurement
of land was modified after 210 days on 20.04.2016. The delay in
achieving the first milestone is visited with penalty in ter ms of
Clause 2.5. of the agreement.
3. Similar communication terminating the contract was set aside
by this Court in Writ Petition No.12432/2017 (Renew Clean Energy
Private Limited vs M.P. Power Management Company Limited
and another) vide order dated 18.08.2017. In the said petition, the
petitioner has admittedly commissioned the power project within
the time prescribed except that there was delay of 16 day s in
achieving the first milestone. The said order has been affirmed on
05.04.2018 by the Hon’ble Supreme Court in Civil Appeal No.3600/
2018 (M.P. Power Management Company Limited vs Renew
Clean Energy Private Limited and another).
4. The parties are not ad idem about the stage of commissioning
of the power project in the present petition.
5. Mr. Kaurav sought to justify the termination of the Power
Purchase Agreement (PPA) asserting that the petitioner has not
commissioned the power project within the time fixed in the
agreement, but the lack of commissioning of power project is not
the reason for terminating of the contract. Since, such is not the
reason mentioned in the order terminating the agreement, therefore,
the respondents cannot supplement the reasons for termination of
the contract by virtue of additional assertions in the return and/or
in the arguments raised in view of the Supreme Court decision in
Mohinder Singh Gill v. Chief Election Commissioner (1978) 1 SCC
405.
6. In view of the fact that the similar reason of termination of the
agreement has not been found to be justified in the matter of
Renew Clean Energy Private Limited (supra), therefore, the
impugned communication dated 11.08.2017 is hereby set aside.
However, liberty is granted to the respondents to pass fresh orders
in terms of Power Purchase Agreement dated 18th Septembe r,
2015 in accordance with law.”
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
8. On 07.07.2018, the appellant issued the fresh termination notice.
This came to be challenged by the first respondent by Writ Petition No.
420 of 2019. After exchange of pleadings, by the first impugned judgment
dated 27.02.2020, the High Court set aside the termina tion order.
Thereafter the appellant in September, 2020 filed review petition which
came to be dismissed by the second impugned order. On 15.04.2021 this
court issued notice and stayed the impugned orders.
9. We have heard Mr. K.M. Natraj, learned Additional Solicitor
General on behalf of the appellant and Dr. A.M. Singhvi, learned Senior
Counsel along with Mr. Naman Nagrath, learned Senior Counsel on
behalf of the first respondent. We also heard Shri V. Giri, learned Senior
Counsel appearing for the fifth respondent (Madhya Pradesh State Load
Despatch Centre).
10. Shri K.M. Natraj, learned Additional Solicitor General submits
that the impugned judgments are clearly unsustainable. He would firstly
point out that the writ petition filed by the first res pondent is not
maintainable. The PPA in question is not a statutory contract and therefore
interference with the order terminating the contract was not justifiable.
In this regard he drew support from the judgment of this Court in Kerala
State Electricity Board and Another v. Kurien E. Kalathil and Others 1.
He would next contend that the PPA contemplated provisions to resolve
disputes. He further contended that first respondent should have resorted,
if at all, to a civil suit to claim redress. He pointed out that a writ petition
is a public law remedy. The contract in question not being statutory in
nature, there was no public law element so as to justify the approach
under Article 226. He would next contend that there is no basis for the
High Court to have interfered at all. This is a case where b roadly the
contract contemplated fulfilment of conditions at two stages. The first
stage related to various conditions that had to be fulfille d by the first
respondent which are described as conditions subsequent in the P PA.
They are also aptly described as the pre-commissioning stage. The PPA
clearly contemplated fulfilment of these conditions on an indisputable
basis on or before 15.01.2017. In arriving at this date, the maximum
period of 9 months contemplated under the PPA as the period which can
be extended on payment of penalty is also included. However, the first
respondent did not fulfil the conditions subsequent except with a further
delay of 56 days. The PPA clearly provides that if the ti me limit is
1 (2000) 6 SCC 293
15
exceeded which in this case was 15.01.2017, the appellant shall terminate
the contract. This is not a question of power or a discretion. T his is a
right which inhered with the appellant, a party to a contra ct. In this
regard he would emphasise that while the State may be burdened with
the obligation to act in a fair manner, it does not take away the rights
available to the State as a party to a contract to exercise the right with it
under the contract. In other words, the appellant as State wi thin the
meaning of Article 12 should not be denied the very right which could be
duly exercised by a private party if it stood in the shoes of the appellant
in similar circumstances. This is all that has been done by the appellant.
Coming to the second stage, namely, commissioning of the project by
the first respondent, our attention was drawn to Article 2.6 of the PPA.
He contended that agreement contemplated commissioning of p lant
within 12 months from the date of the financial closure subject to Force
Majeure. He would point out that there were no circumst ances for
invoking Force Majeure. The period of 12 months from the date of
financial closure determined the maximum period within which the
commissioning had to take place. He would submit that first respondent
was in breach of even commissioning. Therefore, on that score also,
there is no justification for the High Court to have interfered in the matter.
He would further submit that there is another vital circumstance which
should have dissuaded the High Court from granting relief. The case
threw up disputed questions of facts. On the one hand, it was t he case
of the first respondent, that the first respondent had proceede d to do
everything within the time which is a period of two years from
18.09.2015, the date of the PPA, and it was only if commissioning was
not done within the said period that what is described in the agreement
as Seller’s default occurs. Here is a case where the first respondent had
not actually on the ground carried out necessary installation. In this regard,
he would contend that while the CEIG has given its approval, the approval
was granted without the first respondent having complied its obligations
under the contract. In this regard essentially two aspects are projected.
It is firstly pointed out that while the first writ peti tion was pending
consideration, the appellant carried out an inspection on 19.04.2018. A
report ensued on 21.04.2018. It was revealed that the approval which is
granted by the CEIG may not advance the case of the first res pondent
as certain lacunae emerged. It was found by the inspecting team of the
appellant that in the blocks 9 and 10 (the project of 50MW consisted of
10 blocks of 5 MW each), 61 inverters were missing. It was further
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
revealed that in regard to 258 invertors, there was duplication of numbers.
In other words, without there being the professed numbers of invertors
as required under the contract, the approval of the CEIG was procured.
In fact, this aspect, which when it was discovered by the appe llant,
formed the foundation for the review petition but was not fa vourably
considered by the High Court. A writ petition in the facts of t his case
would not lie. He would submit that while a writ petit ion may be
maintainable when the State is awarding its largesse in the form of award
of contract, once it enters into a contract there would arise no occasion
for the court to do judicial review and strike it down. Action taken by the
state as contracting party when it is within the four walls of the contract
is immune in public law proceedings. That an action may lie for breach
of contract where the aggrieved party can seek damages sh ould have
weighed with the court. He would further contend that there is yet another
dimension which has been overlooked by the High Cou rt. The
overwhelming public interest in the facts of this case did not favour the
writ court interfering in the matter. In this regard he would expatiate by
pointing out that the interference by the High Court will pr oduce the
following results:
The PPA casts an obligation on the appellant to purchase power
at the rate of Rs.5.109 per unit for a period of 25 years. Power is available
in the market at a far cheaper rate. The inevitable result of implementing
the order of the High court would be that the appellant would h ave to
purchase power at a much higher rate and what is more disturbing and
should have troubled the High Court to decline jurisdiction is the aspect
that the increased rate would have to be passed on to the end consumer.
Put it differently, when the appellant being entitled to terminate the contract
and would be in a position to purchase power at a cheaper rat e and
charge the consumers at the lower rate, by the court granting relief to
the first respondent, the appellant is compelled to purchase power at the
higher rate and that too for a long period of 25 years, and what is more,
compelled to pass on the burden to the hapless consumer. Thus, public
interest in fact in the case lay in the court declining to grant relief to the
first respondent. He would further point out that the impugned judgment
does not deal with any of the aspects, be it the factual dimensions or the
legal requirements. The judgment is bereft of discussion of the contentions
raised by the appellant. He would therefore contend that the impugned
judgments should be set aside and appeals allowed.
17
11. Per contra , Dr. A.M. Singhvi, learned Senior Counsel for the
first respondent would point out that there is absolutely no basis for
maintaining the appeal in the facts. He would point out that this is a case
where the first respondent turned out to be the lowest bidder in respect
of the project in question and what is more an incredible number of 182
bidders participated. It is trouncing its competitors that the holding
company of the first respondent turned out to be the lowest bidder (here
we must notice that during the course of the arguments the appellant did
propose that first respondent could come up with pro posal which
apparently should involve rates lower than the contract rate so that the
public interest concern is adequately addressed whe reas the first
respondent pointed out since it has planned for the project on the basis
which made it the lowest bidder, it would not be feasible for it to reduce
the rate any further). Dr. Singhvi pointed out that there is no basis for
discriminating the case of the first respondent and M/s. Renew Energy.
It is pointed out that the High Court in the first round of litigation had
interfered with the termination order following the judgment in Renew
Energy. In the case of Renew Energy, it could achieve fulfilment of the
conditions subsequent with a delay of 16 days which was condone d
finally. In the case of the first respondent, the delay happened to be 56
days. Otherwise, their cases are similar. Renew Energy was allowed to
commission whereas the first respondent was at the recei ving end of
discrimination without any basis. He would point out that the first
respondent under the contract had 24 months from 18. 09.2015 to
commission the project. Well before the expiry of 24 months, the project
was ready. The respondent was prevented from commissioning. A party
cannot take advantage of its own wrong. He would point out that t he
law has not stood still after this Court adopted a hands off approach in
the decision in Radhakrishna Agrawal and others v. State of Bihar
and others 2. Imbibing the grand mandate in Article 14 that it behoves
the State to steer clear of unfairness in all its acts, this Court has weaved
a taboo against arbitrary action by the state even after it entered into a
contract. He would point out in this regard the judgment of this Court in
ABL International Ltd. v. Export Credit Guarantee Corpn. of India
Ltd.3 and the decisions following the same approving of the writ court
granting relief in contractual matters also. He would point out that, present
arbitrariness, be it after a contract is entered into, the State has no place
2 (1977) 3 SCC 457
3 (2004) 3 SCC 553
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
to hide when action is challenged and its action must pass the scrutiny of
the constitutional court. It must demonstrate that the action wa s fair.
The action of the State falls far short of the exacting standard of fairness
that the Constitution demands in the case at hand for the f ollowing
reasons:
12. Outbidding an unusually large body of competitors, a bid based
on competitive tariff, the first respondent which is a globa l player in
Renewable Energy (solar power) bids at a rate which was very much
acceptable to the appellant and investment was made by the first
respondent in the region of nearly Rs. 350 crores. There was an initial
hiccup. One of the conditions subsequent was that the first respondent
had to acquire land for the project by way of sale deeds. T here were
insuperable obstacles which upon the first respondent pointing them out
to the appellant, the appellant realized the genuine difficulty and amended
the Article. This, in fact, would necessarily mean that the period of 210
days would commence not from the date of the agreement but thereafter
on the basis of the amended Article. The first respondent en gaged the
services of a company for the purposes of purchase and installation of
the parts of the project. It had procured, inter alia the invertors which
were to be installed, from abroad. There are irrefutable documents in
the form of invoices, bills of lading, lorry receipts which fortify the first
respondent in its stand that it had installed all the invertors. The project
was ready to take off well within 24 months. The first respondent would
suffer grave avoidable financial loss, besides fall in esteem as a global
player, if the termination dated 07.07.2018 is allowed to stand. U nder
the contract, the first respondent was obliged to sell power at an agreed
rate for a period of 25 years. The fact that in view of the play of market
forces, there has been a fall in the price of solar power and it would be
open to the appellant to procure solar power at a cheaper rate should not
allow the appellant to resile from its contractual obligations. In fact, it is
pointed out that the appellant is purchasing power even now at even
higher rates. Being State under Article 12, the appellant should not be
permitted to seek shelter under the theory of alternate remedi es. This
Court is reminded of the chronology of events commencing from the
date of the PPA in the year 2015. The first respondent has suc ceeded
before the High court on two occasions. In this regard he would point
out that in the impugned termination order dated 07.07.2018, the appellant
has purported to revive the closed chapter relating to non-fulfilment of
conditions subsequent. The contention runs that by the judgment in the
19
first writ petition the impugned order therein which was based on the
first respondent not fulfilling the conditions subsequent was quashe d.
This was done being inspired by the judgment of the High court in the
case of Renew Energy which has received the seal of approval by this
Court as well. As far as the only other aspect about commissioning not
being in time Dr. Singhvi addressed two submissions. Firstly, he would
point out that admittedly, the appellant has not issued the pre-termination
notice contemplated in Article 9.1 of the PPA. This suffices to sustain
the judgment. Secondly, equally importantly the appellant has act ed
arbitrarily in not realizing that the first respondent had 24 months to
commission the project and before the expiry of the same, the respondent
was fully ready to fulfil its obligation. The learned senior counsel would
also submit that contention of there being disputed questions of fact is
premised on red herrings . In this regard he would point out that on
09.07.2017, a notice was issued by the first respondent to the appellant
calling upon the appellant to inspect and it would be ready to commission
the project and that it was ready to supply power. However, no inspection
was carried by the appellant till 19.04.2018. The competent body namely
the CEIG had carried out inspection which spread over a few days. The
Body was fully satisfied with the first respondent being compliant. All
that happened was after the inspection, in September, 2017 si nce the
first respondent was visited with the first order of termi nation dated
11.08.2017 which was challenged in the High Court, there was a shortage
of personnel around the project site. This facilitated thefts of the parts
which were installed. FIRs promptly registered in September 2017 should
rule out the possibility of the case of theft being an afterthought. This is
as the inspection was carried by the appellant much later on 19.04.2018.
It is further pointed out that as far as the duplication is concerned in the
number of certain invertors, it has been established as inconsequential
by the first respondent. The inspection and the report of the CEIG cannot
be lightly brushed aside on such a case. Still furthermore, it is pointed out
that having regard to the massive cost of the project which stood at
nearly Rs. 350 crores, what is involved is a miniscule percentage. In this
regard learned counsel would emphasise the contravention of Artic le
9.1 under which the appellant was obliged to serve a notice in case of
the alleged seller’s default for not commissioning the project in 24 months
from the date of PPA. If such a notice had been given, the first respondent
would have had an opportunity if at all even proceeding on the basis of
appellant’s contention being tenable to procure invertors which are
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
portable and available in the market and redress the problem. When the
project has progressed in the manner, it had to deny the first respondent
the fruits of its labour, acting under a solemn contract awa rded to it
would be clearly unfair. The mere fact that there had been a fall in the
market price of solar power should not persuade this Court to find that
there is no overwhelming public interest. In this regard he also sought to
draw support from recent Judgment of this Court in Vice Chairman &
Managing Director, City and Industrial Development Corporated
of Maharashtra Ltd. and Another v. Shishir Realty P. Ltd. and others .
He would further point out that solar power being renewable energy and
green energy must be encouraged and it was on this basis that the first
respondent participated in the global tender and was selected, upon it
being the lowest bidder amongst a large number of bidders. Dr. Singhvi
would point out that for various reasons the contract in quest ion is a
statutory contract. He would submit that any rate irrespective of being
statutory contract or not, it is but a fact in deciding whe ther the writ
applicant should be relegated to an alternate remedy. The jurisdiction of
the High Court under Article 226 in the overpowering presence of Article
14 would embrace the power to strike at arbitrary action by the State,
even in the working out of rights in a non-statutory contract.
13. Shri V. Giri, learned senior counsel for respondent No.5 would
support the appellant in its stand that the first respondent w as in clear
breach of the contract. It is the case of fifth respondent that there are
various steps to be undertaken and completed under regulations extant
before which commissioning can be permitted. It is the case of the fifth
respondent that the first respondent could not therefore be said to have
acted in compliance with the regulations and therefore cannot be heard
to say that it had commissioned the project.
14. Shri K.M. Natraj, Additional Solicitor General would submit
that the judgment of the High court in the first-round litigation left it open
to the appellant to take fresh proceedings under the contract. It is for the
said reason that the said judgment was not challenged by the appellant.
He would also point out at any rate even proceeding on the basis that the
High Court is bound by the earlier judgment at any rate, as far as this
Court is concerned, it would be free to consider the issue as to whether
on account of there being an admitted delay of 53 days by the first
respondent beyond the maximum time contemplated under the contract
for fulfilling conditions subsequent, whether the appellant was justified
21
being duty bound in the matter of terminating the contract? He further
pointed out that there was a distinction in the case of the first respondent
and the case of Renew Energy. In the case of Renew Energy, this Court
while refusing to interfere with the judgment of the Hi gh Court had
made it clear that it is not pronouncing on the question as to the delay in
fulfilling the conditions subsequent and its impact. Secondly, it is pointed
out that in the case of Renew Energy, the said company had gone ahead
and commissioned the project and the only aspect was the delay of 16
days whereas in the case of the first respondent the contract was liable
to be terminated both for the reasons that the conditions subsequent was
not fulfilled within the maximum time and also for the reason that the
first respondent had not commissioned the project within the time provided
under the contract.
15. After hearing the learned counsel for the parties, we find that
the following points arise for our consideration.
(1) Whether the PPA in question, is a statutory contract?
(2) What is the scope of judicial review of action by the S tate
in a matter arising from a contract and what is the effect of
the contract not being statutory? What is arbitrariness?
(3) What is the concept of public law in judicial revi ew in a
contractual matter?
(4) Whether there is an arbitration clause in regard to the subject
matter?
(5) Whether the order dated 07.07.2018 terminating the contract
based on first respondent not fulfilling the conditi ons
subsequent is sustainable having regard to the judgment
rendered by the High Court in the earlier round of litigation
on 20.06.2018? And will the said judgment bar the appellant
from terminating the contract on the ground of non-fulfilment
of conditions subsequent?
(6) Whether the writ petition must be dismissed as the case
involves disputed questions of facts?
(7) Whether the case of the first respondent is on par with
Renew Energy?
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
(8) What is the effect of non-compliance of Article 9.1 of the
PPA, namely, the effect of appellant not issuing notice
contemplated therein before issuing the impugned
termination dated 07.07.2018?
(9) What is overwhelming public interest in the context of
judicial review in a contractual matter? Is the conc ept
applicable only to cases which involve challenge to award
of largesse by the State or is it applicable across the Board
irrespective of the stage when the matter arises in relation
to a contract?
(10) Whether this Court should interfere with the judgment of
the High Court in the totality of facts?
16. Before we proceed to consider the question whether what is
involved is a statutory contract or not, we may make the f ollowing
prefatory remarks:
Under Article 298 of the Constitution, the Executive Power
of the Union and each State, inter alia, extends to making of
contracts for any purpose. Article 299 provides for manner in
which contracts made in the exercise of the executive pow er of
the Union or the State is to be made.
17. In this case, we are dealing not with a case where a contract
has been made by the State in exercise of its executive power within the
meaning of Article 298. The PPA is a contract which has been entered
into by the appellant, which is a fully owned Government Company. It is
one thing to hold that the appellant, as a fully owned Governm ent
Company, would be State for the purpose of Article 12 of the Constitution
of India and, quite another, to find that a contract is one which is made in
the executive power of the State within the meaning of Ar ticle 162 of
the Constitution. What is contemplated, is the power of the Union or the
State read in conjunction with Article 73 and Article 162 of the Constitution
of India, respectively. In other words, for the purpose of Article 298, the
broader concept of State, as defined in Article 12 of t he Constitution,
which, no doubt, would include the appellant, is inapposite and inapplicable.
The appellant, being a Company, would not be entitled to exercise the
executive power contemplated in Article 162 of the Constitution, which
is the power with the Union or the State Governments. In this regard we
23
may notice that the present avtar of Article 298 is born by substituting in
1956 the original version and the present version reads as follows: -
“298. Power to carry on trade, etc. The executive power of
the Union and of each State shall extend to the carrying on of
any trade or business and to the acquisition, holding and disposal
of property and the making of contracts for any purpose:
Provided that —
(a) the said executive power of the Union shall, in so far a s
such trade or business or such purpose is not one with respect
to which Parliament may make laws, be subject in each State
to legislation by the State; and
(b) the said executive power of each State shall, in so f ar as
such trade or business or such purpose is not one with respect
to which the State Legislature may make laws, be subject to
legislation by Parliament.”
It is pertinent to notice the Objects and Reasons.
“Clause 19.-In this clause it is proposed to revise and amplify
the scope of article 298, mainly to make it clear that Uni on
Government, as well as the State Governments, are competent
to carry on any commercial or industrial undertaking, whether
or not it is related to a matter within the legislative competence
of the Union, or, as the case may be, of the State. Similarly, the
holding, acquisition and disposal of property and the making of
contracts by the Union or a State could be for any purpose
without constitutional impropriety. At the same time, the revised
article provides that this extended executive power of the Union
and of the States will be subject, in the former case, to legislation
by the State, and in the latter case, to legislation by Parliament.”
WHETHER THE PPA IS A STATUTORY CONTRACT?
18. Moving on to the concept of the Statutory Contract, the learned
Additional Solicitor General, no doubt, sought to draw consider able
support from the Judgment of this Court reported in Kerala SEB and
another v. Kurien E. Kalathil and others 4. That was a case, which
involved, a Writ Petition filed by a contractor, who was aw arded the
4 (2000) 6 SCC 293
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
work of construction of a dam, staking a claim, for enhanced minimum
wages, which the contractor claimed, he had paid to his workers. There
was no dispute that the workmen were entitled to the enhanced wage s
under a Notification. The appellant-Board, however, contended that the
respondent-contractor had failed to prove the payment of the enhanced
wages to the workmen. The High Court allowed the Writ Petition a nd
this Court, while setting aside the Judgment, proceeded to mak e the
following statement:
“10. We find that there is a merit in the first con tention of
Mr Raval. Learned counsel has rightly questioned th e
maintainability of the writ petition. The interpret ation and
implementation of a clause in a contract cannot be the subje ct-
matter of a writ petition. Whether the contract envisages a ctual
payment or not is a question of construction of contract. If a term
of a contract is violated, ordinarily the remedy is not the writ petition
under Article 226. We are also unable to agree with the
observations of the High Court that the contractor was se eking
enforcement of a statutory contract. A contract would not become
statutory simply because it is for construction of a public utili ty
and it has been awarded by a statutory body. We are also unable
to agree with the observation of the High Court that since the
obligations imposed by the contract on the contracting parties come
within the purview of the Contract Act, that would not make the
contract statutory. Clearly, the High Court fell into an error in
coming to the conclusion that the contract in question was statutory
in nature.
11. A statute may expressly or impliedly confer power on a
statutory body to enter into contracts in order to enable it to
discharge its functions. Dispute arising out of the terms of such
contracts or alleged breaches have to be settled by the ordina ry
principles of law of contract. The fact that one of the par ties to
the agreement is a statutory or public body will not by itself affect
the principles to be applied. The disputes about the meaning of a
covenant in a contract or its enforceability have to be determined
according to the usual principles of the Contract Act. Every act
of a statutory body need not necessarily involve an exercis e of
statutory power. Statutory bodies, like private parties, have power
to contract or deal with property. Such activities may not ra ise
25
any issue of public law. In the present case, it has not been shown
how the contract is statutory. The contract between the parties is
in the realm of private law. It is not a statutory cont ract. The
disputes relating to interpretation of the terms and conditions of
such a contract could not have been agitated in a petition unde r
Article 226 of the Constitution of India. That is a matter fo r
adjudication by a civil court or in arbitration if provided for in the
contract. Whether any amount is due and if so, how much and
refusal of the appellant to pay it is justified or not, are not the
matters which could have been agitated and decided in a wri t
petition. The contractor should have relegated to other remedies.”
19. As to what is a statutory contract, fell for consideration before
this Court in the case reported in India Thermal Power Ltd. v. State of
M.P. and others 5. Incidentally, it dealt with generation, distribution and
supply of electricity and, what is more, emanated from the St ate of
Madhya Pradesh. While negotiations were going on bet ween the
respondent-State, Electricity Board and independent power producers,
on the basis of State inviting offers from potential private investors, for
establishing power projects, the Central Government amended the earlier
Tariff Notification. The Electricity Board decided to prioritize the projects,
which offered the least tariff. The appellant-independent power producer
challenged the said decision in a Writ Petition. It must be noti ced that
MoU and Power Purchase Agreement had been entered into by t he
appellant therein. The Division Bench of the High Court took the view
that the PPAs therein were statutory contracts, ent ered into under
Sections 43 and 43(A) of the Electricity Supply Act, 1948. This Court,
while dealing with this aspect and rejecting the contention that the
Electricity Board could not unilaterally alter the conditions of the contract
and invite bids, held as follows:
“11. It was contended by Mr Cooper, learned Senior
Counsel appearing for appellant GBL and also by som e
counsel appearing for other appellants that the appellant/
IPPs had entered into PPAs under Sections 43 and 43-A of
the Electricity Supply Act and as such they are stat utory
contracts and, therefore, MPEB had no power or authority
to alter their terms and conditions. ………………
5 (2000) 3 SCC 379
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
……… Merely because a contract is entered into in exercise
of an enabling power conferred by a statute that by itself
cannot render the contract a statutory contract. If enter ing
into a contract containing the prescribed terms and
conditions is a must under the statute then that co ntract
becomes a statutory contract. If a contract incorpo rates
certain terms and conditions in it which are statutory then
the said contract to that extent is statutory. A contract m ay
contain certain other terms and conditions which may not
be of a statutory character and which have been
incorporated therein as a result of mutual agreemen t
between the parties. Therefore, the PPAs can be regard ed
as statutory only to the extent that they contain provision s
regarding determination of tariff and other statuto ry
requirements of Section 43-A(2). Opening and maintaining
of an escrow account or an escrow agreement are not the
statutory requirements and, therefore, merely becau se
PPAs contemplate maintaining escrow accounts that
obligation cannot be regarded as statutory. ”
(Emphasis supplied)
20. The decision in India Thermal Power Ltd . (supra), dealing
with the concept of statutory contract, came to be considered in the light
of Section 6A of U.P. Industrial Area Development Act of 1976. The
said provision reads as follows:
“6A. Power to authorize a person to provide infrastructure
or amenities and collect tax or fee. - Notwithstand ing
anything to the contrary contained in any other provisions
of this Act and subject to such terms and conditions as may
be specified in the regulations, the Authority may, by
agreement, authorize any person to provide or maintain or
continue to provide or maintain any infrastructure or
amenities under this Act and to collect taxes or fees, a s the
case may be, levied therefor.”
21. This Court interpreting a contract entered into under Section
6A in Jaypee Kensington Boulevard Apartments Welfare Association
and others v. NBCC (India) Ltd. and others 6, took the view that the
6 (2022) 1 SCC 401
27
agreement in question did not acquire the status of a statutory contract
merely for having been executed in terms of the power under S ection
6A.
22. The contention of the respondent is that the PPA is a statutory
contract since it incorporates essential features such as tariff determined
through bidding (paragraph-4.7-CUF, paragraph-4.4-chan ge in law,
paragraph-4.5-payment security, paragraph-4.6-and bidding process,
paragraphs-5.4 and 5.5-prescribed under the guidelines for tariff based
competitive process for grid connected power project based on renewable
energy resources issued by the MNRE under Section 63 of the A ct).
23. The respondent relies on India Thermal Power Ltd. (supra)
to contend that if the contract incorporates certain sta tutory terms and
conditions, it is statutory.
24. Section 63 of the Electricity Act, 2003, reads as follows:
“63 (Determination of tariff by bidding process) Notwithstanding
anything contained in Section 62, the appropriate Commission shall
adopt the tariff, if such tariff has been determine d through
transparent process of bidding in accordance with the guidelines
issued by the Central Government.”
25. In the PPA in question, under the definition clause (Article 1),
bidding guidelines have been defined as follows:
“Bidding Guidelines” shall mean the “Guidelines for Tariff Based
Competitive Bidding Process for Grid Connected Power Projects
Based on Renewable Energy Sources” issued by Government of
lndia, Ministry of New and Renewable Energy on December, 2012
under Section - 63 of the Electricity Act and as amended f rom
time to time;”
26. We are of the view that it may not be appropriate to describe
the PPA as a Statutory Contract. Section 63 of the Electricity Act, 2003
must be understood in the background of immediately preceding provision,
viz ., Section 62, In a paradigm shift from the earlier regime, the task of
determining the tariff has been conferred on the appropriate Commission.
Section 62 indicates the procedure. Section 63, on the other hand, compels
the Commission to adopt the tariff determined through a tr ansparent
process of bidding. However, the transparent process of biddi ng must
be in accordance with the guidelines issued by the Central Government.
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
Thus, it is for the purpose of applying the tariff determined under Section
63 for the purpose of adopting the tariff under Section 62, that the
guidelines issued by the Central Government become relevant. It is true
that there is reference to the guidelines made under Sect ion 63 in the
PPA. However, it is for the purpose of conducting the bidding that the
guideline would become relevant. That the tariff has been arrived at in
accordance with the transparent process of bidding, which is in t une
with the guidelines under Section 63, may not be sufficient to make the
PPA a Statutory Contract. What is contemplated in India Thermal Power
Limited (supra), is that a contract containing prescrib ed terms and
conditions being mandatory under the Statute, results in th e contract
becoming a Statutory Contract. If this test is applied, we fail to see how
the reference to the bidding guidelines, under which the bids were made
and finally the PPA is entered into, can be treated as tantamounting to
saying that the PPA contains prescribed statutory terms and conditions
as an indispensable part of a Statute. We are not shown also as to how
the PPA can be described as containing terms and conditions, which are
statutory in nature. The expression ‘terms and conditions’, w hich are
statutory in nature, must be understood as those statutory term s and
conditions, which provide for rights and obligations of the contracting
parties. Such reference is conspicuous by its absence in the PPA. It is
common case that the appellant is incorporated under the Comp anies
Act. It is not a statutory body or a corporation. Therefore, we would
come to the conclusion that we cannot describe the co ntract as a
Statutory Contract. We must also notice that the PPA is not made either
in purported compliance with the statutory dictate, either in the form of
parent enactment or a subordinate legislation. The terms and conditions
of the PPA are not transplanted into the PPA from any Statutory provision.
The appellant being company under the Companies Act, would be free
as any other contracting party, subject, no doubt, to its positi on as an
instrumentality of the State under Article 12 of the Constitution of India
and the law otherwise. Moreover, the terms, which are relev ant to the
lis before us, viz, the Articles relating to the fulfilment of the condition
subsequent and the provisions relating to commissioning, sellers’ default
and power of termination, are not demonstrated to be statutory in nature.
What is the scope of judicial review of action by the State in
a matter arising from a contract and what is the effect of the
contract not being statutory?
29
What is the concept of public law in judicial review i n a
contractual matter?
What is ‘arbitrary’ action?
27. In Radhakrishna Agarwal and Ors. v. State of Bihar and
Ors.7 writ petitions were filed against orders of the State Gove rnment
revising the rate of royalty under a lease. The contention was both against
the revision of rate of royalty during the period of the lease and the
cancellation of the lease on various grounds. Though an attempt wa s
sought to draw support from the judgment of this Court in Erusian
Equipment and Chemicals Limited v. State of West Bengal 8, the Court
took the view that the said case involved discrimination at the threshold
or at the time of deciding as to whether the Government should enter
into the contract. The Court took the view that the only question which
normally arises in such cases is as to whether the action complained of
was in conformity with the agreement. We may notice the earlier opinions
of this Court which came to be dealt with in the following statement:
“We do not think that any of these cases could assist the appellants
or is at all relevant. None of these cases lays down that, when the
State or its officers purport to operate within the contractual field
and the only grievance of the citizen could be that the co ntract
between the parties is broken by the action complained of, the
appropriate remedy is by way of a petition under Article 226 of
the Constitution and not an ordinary suit. There is a formidable
array of authority against any such a proposition. In Lekhraj
Satramdas Lalvani v. N.M.Shah, Deputy Custodian-cum -
Managing Officer, Bombay (supra) this Court said:
“In our opinion any duty or obligation falling upon a public servant
out of a contract entered into by him as such public servant cannot
be enforced by the machinery of a writ under Article 226 of the
Constitution.”
In Banchhanidhi Rath v. The State of Orissa and Ors. 9, this Court
declared:
“If a right is claimed in terms of a contract such a right cannot be
enforced in a writ petition.”
7 (1977) 3 SCC 457
8 (1975) 1 SCC 70
9 (1972) 4 SCC 781
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
In Har Shankar and Ors. vs. The Dy. Excise and Taxatio n
Commr. and Ors.10 , a Constitution Bench of this Court observed:
“The appellants have displayed ingenuity in their sear ch for
invalidating circumstances but a writ petition is not an appropriate
remedy for impeaching contractual obligations.”
28. The Court also took the view “the correct view is that it is the
contract and not the executive power regulated by the Constitution which
governs the relations of the parties on facts apparent in the case before
us”. No doubt the learned Additional Solicitor General asserts that the
destiny of the appeals before us must be governed by the law laid down
in Radhakrishna Agarwal (supra). However, as shall be presently noticed
the law has not stood still.
29. In Ramana Dayaram Shetty v. International Airport
Authority of India 11 this court inter alia held as follows:
“10. Now, there can be no doubt that what para (1) of the notice
prescribed was a condition of eligibility which was required to be
satisfied by every person submitting a tender. The condit ion of
eligibility was that the person submitting a tender must be
conducting or running a registered IInd Class hotel or restaurant
and he must have at least 5 years’ experience as such and i f he
did not satisfy this condition of eligibility, his tender would not be
eligible for consideration. This was the standard or no rm of
eligibility laid down by Respondent 1 and since the Respondents 4
did not satisfy this standard or norm, it was not competent to
Respondent 1 to entertain the tender of Respondents 4. It is a
well-settled rule of administrative law that an executive authority
must be rigorously held to the standards by which it professes its
actions to be judged and it must scrupulously observe tho se
standards on pain of invalidation of an act in violation of them.
This rule was enunciated by Mr Justice Frankfurter
in Viteralli v. Saton [359 US 535 : Law Ed (Second series) 1012]
where the learned Judge said:
“An executive agency must be rigorously held to the standards by
which it professes its action to be judged .… Accordingly, if
dismissal from employment is based on a defined procedure, even
10 (1975) 1 SCC 737
11 (1979) 3 SCC 489
31
though generous beyond the requirements that bind such agency,
that procedure must be scrupulously observed .... This judicially
evolved rule of administrative law is now firmly established and,
if I may add, rightly so. He that takes the procedural sword shall
perish with the sword.”
This Court accepted the rule as valid and applicable in India in A.S.
Ahluwalia v. Punjab [(1975) 3 SCC 503, 504 : 1975 SCC (L&S)
27 : (1975) 3 SCR 82] and in subsequent decision gi ven
in Sukhdev v. Bhagatram [(1975) 1 SCC 421, 462 : 1975 SCC
(L&S) 101 : (1975) 3 SCR 619], Mathew, J., quoted the above-
referred observations of Mr Justice Frankfurter with approval. It
may be noted that this rule, though supportable als o as an
emanation from Article 14, does not rest merely on that article. It
has an independent existence apart from Article 14. It is a rule of
administrative law which has been judicially evolved as a check
against exercise of arbitrary power by the executive authority. If
we turn to the judgment of Mr Justice Frankfurter and examine it,
we find that he has not sought to draw support for the rule from
the equality clause of the United States Constitution, but evolved
it purely as a rule of administrative law. Even in Engl and, the
recent trend in administrative law is in that direction as is evident
from what is stated at pp. 540-41 in Prof Wade’s “ Administrative
Law ”, 4th Edn. There is no reason why we should hesitate to
adopt this rule as a part of our continually expanding administrative
law. Today with tremendous expansion of welfare and social
service functions, increasing control of material and economic
resources and large scale assumption of industrial and commercial
activities by the State, the power of the executive Government to
affect the lives of the people is steadily growing. The attainment
of socio-economic justice being a conscious end of State policy,
there is a vast and inevitable increase in the frequency with which
ordinary citizens come into relationship of direct encounter with
State power-holders. This renders it necessary to structure and
restrict the power of the executive Government so as to prevent
its arbitrary application or exercise. Whatever be the concept of
the Rule of Law, whether it be the meaning given by Dicey in his
“The Law of the Constitution ” or the definition given by Hayek
in his “ Road to Serfdom ” and “ Constitution of Liberty ” or the
exposition set forth by Harry Jones in his “ The Rule of Law and
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
the Welfare State ”, there is as pointed out by Mathew, J., in his
article on “The Welfare State, Rule of Law and Natural Justice”
in “ Democracy, Equality and Freedom ” [ Upendra Baxi, Ed. :
Eastern Book Co., Lucknow (1978) p. 28] “substantial agreement
in juristic thought that the great purpose of the rule of law notion
is the protection of the individual against arbitrary exerc ise of
power, wherever it is found”. It is indeed unthinkable that in a
democracy governed by the rule of law the executive Government
or any of its officers should possess arbitrary power over the
interests of the individual. Every action of the ex ecutive
Government must be informed with reason and should be free
from arbitrariness. That is the very essence of the rule of law and
its bare minimal requirement. And to the application of this principle
it makes no difference whether the exercise of the power involves
affectation of some right or denial of some privilege.”
This case while it dealt with the issue of arbitrariness at the stage
of award of largesse by the State, it paved the way for future development
in this field of law.
30. No doubt, in Bareilly Development Authority and another
v. Ajai Pal Singh and others 12 , the appellant-Authority constituted under
the U.P. Planning and Development Act, 1973, issued advertiseme nt
offering to register the names of applicants desirous of purchasing houses/
flats. The terms and conditions were sought to be revised. The C ourt
went on to hold as follows:
“22. There is a line of decisions where the contract entered into
between the State and the persons aggrieved is non-statutory and
purely contractual and the rights are governed only by the terms
of the contract, no writ or order can be issued under Article 226
of the Constitution of India so as to compel the authorities to remedy
a breach of contract pure and simple — Radhakrishna
Agarwal v. State of Bihar [(1977) 3 SCC 457 : (1977) 3 SCR
249], Premji Bhai Parmar v. Delhi Development Authority
[(1980) 2 SCC 129 : (1980) 2 SCR 704] and DFO v. Biswanath
Tea Company Ltd. [(1981) 3 SCC 238 : (1981) 3 SCR 662]”
31. In Mahabir Auto Stores and others v. Indian Oil
Corporation and others 13 , the appellant complained that the respondent,
12 (1989) 2 SCC 116
13 (1990) 3 SCC 752
33
which was a company incorporated under the Companies Act was
denying or discontinuing to deal with the appellant, which had b een
dealing with the respondent for nearly eighteen years. We listen to the
following words spoken by this Court:
“12. It is well settled that every action of the St ate or an
instrumentality of the State in exercise of its executi ve power,
must be informed by reason. In appropriate cases, a ctions
uninformed by reason may be questioned as arbitrary in
proceedings under Article 226 or Article 32 of the Constitution.
Reliance in this connection may be placed on the observations of
this Court in Radha Krishna Agarwal v. State of Bihar [(1977) 3
SCC 457]. It appears to us, at the outset, that in the facts a nd
circumstances of the case, the respondent company IOC is an
organ of the State or an instrumentality of the State as contemplated
under Article 12 of the Constitution. The State acts in its executive
power under Article 298 of the Constitution in entering or not
entering in contracts with individual parties. Article 14 of the
Constitution would be applicable to those exercises of power.
Therefore, the action of State organ under Article 14 can be
checked. See Radha Krishna Agarwal v. State of Bihar [(1977) 3
SCC 457] at p. 462, but Article 14 of the Constitution cannot and
has not been construed as a charter for judicial review of St ate
action after the contract has been entered into, to call upon the
State to account for its actions in its manifold activities by stating
reasons for such actions. In a situation of this natu re certain
activities of the respondent company which constituted State under
Article 12 of the Constitution may be in certain circumstanc es
subject to Article 14 of the Constitution in entering or not entering
into contracts and must be reasonable and taken only upon lawful
and relevant consideration; it depends upon facts a nd
circumstances of a particular transaction whether hea ring is
necessary and reasons have to be stated. In case an y right
conferred on the citizens which is sought to be interfered, suc h
action is subject to Article 14 of the Constitution, and must be
reasonable and can be taken only upon lawful and relevant grounds
of public interest. Where there is arbitrariness in State action of
this type of entering or not entering into contracts, Article 14 springs
up and judicial review strikes such an action down. Every action
of the State executive authority must be subject to rule of law and
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
must be informed by reason. So, whatever be the activity of t he
public authority, in such monopoly or semi-monopoly dealings, it
should meet the test of Article 14 of the Constitut ion. If a
governmental action even in the matters of entering or not entering
into contracts, fails to satisfy the test of reasonableness, the same
would be unreasonable. In this connection reference may be made
to E.P. Royappa v. State of Tamil Nadu [(1974) 4 SCC 3 : 1974
SCC (L&S) 165], Maneka Gandhi v. Union of India [(1978) 1
SCC 248], Ajay Hasia v. Khalid Mujib Sehravardi [(1981) 1 SCC
722 : 1981 SCC (L&S) 258], R.D. Shetty v. International Airport
Authority of India [(1979) 3 SCC 489] and also Dwarkadas
Marfatia and Sons v. Board of Trustees of the Port of Bombay
[(1989) 3 SCC 293]. It appears to us that rule of reason and rule
against arbitrariness and discrimination, rules of fair play and
natural justice are part of the rule of law applicable in situation or
action by State instrumentality in dealing with citizens in a situation
like the present one. Even though the rights of the citizens are in
the nature of contractual rights, the manner, the method and motive
of a decision of entering or not entering into a contract, are subject
to judicial review on the touchstone of relevance a nd
reasonableness, fair play, natural justice, equalit y and non-
discrimination in the type of the transactions and nature of the
dealing as in the present case.
17. We are of the opinion that in all such cases whether pu blic
law or private law rights are involved, depends upon the facts and
circumstances of the case. The dichotomy between rights and
remedies cannot be obliterated by any strait-jacket for mula. It
has to be examined in each particular case. Mr Salve sough t to
urge that there are certain cases under Article 14 of ar bitrary
exercise of such “power” and not cases of exercise of a “rig ht”
arising either under a contract or under a statute. We are of the
opinion that that would depend upon the factual matrix.
18. Having considered the facts and circumstances of the ca se
and the nature of the contentions and the dealing between the
parties and in view of the present state of law, we are o f the
opinion that decision of the State/public authority under Article
298 of the Constitution, is an administrative decision and can be
impeached on the ground that the decision is arbitrary or violative
35
of Article 14 of the Constitution of India on any of the groun ds
available in public law field. It is true that there is discrimination
between power and right but whether the State or th e
instrumentality of a State has the right to function in public field or
private field is a matter which, in our opinion, depends upon the
facts and circumstances of the situation, but such exercise of
power cannot be dealt with by the State or the instrumentality of
the State without informing and taking into confidence, the party
whose rights and powers are affected or sought to be af fected,
into confidence. In such situations most often people feel aggrieved
by exclusion of knowledge if not taken into confidence.”
(Emphasis supplied]
32. In the judgment of this Court rendered by a Bench of two
learned Judges decided in Shrilekha Vidyarthi (Kumari) v. State of U.P 14 ,
the court was concerned with a challenge to a general order by which
the appointment of all government counsel in all the districts of the state
of U.P. came to be terminated. The writ petition was filed under Article
32 of the Constitution of India. Important and apposite are the following
observations:
“22. There is an obvious difference in the contracts be tween
private parties and contracts to which the State is a party. Private
parties are concerned only with their personal interest w hereas
the State while exercising its powers and discharging its functions,
acts indubitably, as is expected of it, for public good and in public
interest. The impact of every State action is also on public interest.
This factor alone is sufficient to import at least t he minimal
requirements of public law obligations and impress wit h this
character the contracts made by the State or its instrumentality. It
is a different matter that the scope of judicial review in respect of
disputes falling within the domain of contractual obligations may
be more limited and in doubtful cases the parties may be relegated
to adjudication of their rights by resort to remedies provided for
adjudication of purely contractual disputes. However, to the extent,
challenge is made on the ground of violation of Article 14 by
alleging that the impugned act is arbitrary, unfair or unreasonable,
the fact that the dispute also falls within the domain of contractual
obligations would not relieve the State of its obligation to comply
14 (1991) 1 SCC 212
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
with the basic requirements of Article 14. To this exten t, the
obligation is of a public character invariably in ev ery case
irrespective of there being any other right or obligation in addition
thereto. An additional contractual obligation cannot divest the
claimant of the guarantee under Article 14 of non-arbitrariness at
the hands of the State in any of its actions.
24. The State cannot be attributed the split personality of Dr Jekyll
and Mr Hyde in the contractual field so as to impress on it all the
characteristics of the State at the threshold while making a contract
requiring it to fulfil the obligation of Article 14 of the Constitution
and thereafter permitting it to cast off its garb of S tate to adorn
the new robe of a private body during the subsistence of t he
contract enabling it to act arbitrarily subject only to the contractual
obligations and remedies flowing from it. It is really the nature of
its personality as State which is significant and must characterize
all its actions, in whatever field, and not the nature of f unction,
contractual or otherwise, which is decisive of the nature of scrutiny
permitted for examining the validity of its act. The requirement of
Article 14 being the duty to act fairly, justly and reasonably, there
is nothing which militates against the concept of requiring the State
always to so act, even in contractual matters. There is a basic
difference between the acts of the State which must invaria bly
be in pubic interest and those of a private individual, engaged in
similar activities, being primarily for personal gain, which may or
may not promote public interest. Viewed in this manner, in which
we find no conceptual difficulty or anachronism, we find no reason
why the requirement of Article 14 should not extend even in the
sphere of contractual matters for regulating the conduct of the
State activity.
27. Unlike a private party whose acts uninformed by reason and
influenced by personal predilections in contractual matters may
result in adverse consequences to it alone without affecting the
public interest, any such act of the State or a public body even in
this field would adversely affect the public interest.
28. Even assuming that it is necessary to import the concept of
presence of some public element in a State action to attract Article
14 and permit judicial review, we have no hesitation in saying that
the ultimate impact of all actions of the State or a pu blic body
37
being undoubtedly on public interest, the requisite public element
for this purpose is present also in contractual mat ters. We,
therefore, find it difficult and unrealistic to exclude the State actions
in contractual matters, after the contract has been made, fr om
the purview of judicial review to test its validity on the anvil of
Article 14.”
(Emphasis supplied)
33. As to what constitutes arbitrariness is captured in paragraph
36 and it reads as follows:
“36. The meaning and true import of arbitrariness is more easily
visualized than precisely stated or defined. The question, whether
an impugned act is arbitrary or not, is ultimately to be answered
on the facts and in the circumstances of a given case. An obvious
test to apply is to see whether there is any discernible p rinciple
emerging from the impugned act and if so, does it satisfy the test
of reasonableness. Where a mode is prescribed for doing an act
and there is no impediment in following that proced ure,
performance of the act otherwise and in a manner which does
not disclose any discernible principle which is reasonab le, may
itself attract the vice of arbitrariness. Every State action must be
informed by reason and it follows that an act uninformed by reason,
is arbitrary. Rule of law contemplates governance by la ws and
not by humour, whims or caprices of the men to whom the
governance is entrusted for the time being. It is trite that ‘be you
ever so high, the laws are above you’. This is what men in power
must remember, always.”
34. The pronouncement made by this Court would later become
the springboard or the charter for the further evolution of the concept of
public law element as also premise for the superior courts invoking Article
14 in various contractual matters.
35. In State of U.P and others v. Bridge and Roof Company
(India) Ltd.15 , the Court was dealing with a case of a writ petition filed
by the respondent therein which was a public sector corpor ation and
seeking payment allegedly due from the appellant state. The Court noted
that the contract in question contained Articles providing inter alia for
15 (1996) 6 SCC 22
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
settlement of disputes by reference to arbitration. The very re sort to
Article 226 was found to be misconceived in the circumstances.
The Court also laid down as follows: -
“Firstly, the contract between the parties is a contract in the realm
of private law. It is not a statutory contract. It is governed by the
provisions of the Contract Act or maybe, also by certain provisions
of the Sale of Goods Act. Any dispute relating to interpretation of
the terms and conditions of such a contract cannot be agitate d,
and could not have been agitated, in a writ petition. That is a
matter either for arbitration as provided by the contract or for the
civil court, as the case may be. Whether any amount is due to the
respondent from the appellant-Government under the contract and,
if so, how much and the further question whether retention or
refusal to pay any amount by the Government is justified, or not,
are all matter which cannot be agitated in or adjudicated upon in a
writ petition. The prayer in the writ petition, viz., to restrain the
Government from deducting a particular amount from the writ
petitioner’s bill(s) was not a prayer which could be granted by the
High Court under Article 226. Indeed, the High Court has not
granted the said prayer.”
36. In Verigamto Naveen v. Govt. of A.P. and others 16 , the case
involved, mining leases granted to a corporation and a sub-lease, which
was permitted by the Government. Thereafter, the permission was sought
to be withdrawn. The withdrawal of the permission, was the s ubject
matter of challenge in writ proceedings, inter alia. Against, the Order of
the Full Bench of the High Court, (which is reported in AIR 1995 A.P.1),
appeals were carried to this Court. On the issue relating to the jurisdiction
of the Court in cases arising out of contract, this Court held as follows:
“21. … Though there is one set of cases rendered by this Court
of the type arising in Radhakrishna Agarwal case [(1977) 3 SCC
457 : AIR 1977 SC 1496] much water has flown in the stream of
judicial review in contractual field. In cases where the decision-
making authority exceeded its statutory power or committed breach
of rules or principles of natural justice in exercise of such power
or its decision is perverse or passed an irrational order, this Court
has interceded even after the contract was entered into b etween
16 (2001) 8 SCC 344
39
the parties and the Government and its agencies. We may advert
to three decisions of this Court in Dwarkadas Marfatia &
Sons v. Board of Trustees of the Port of Bombay [(1989) 3 SCC
293], Mahabir Auto Stores v. Indian Oil Corpn. [(1990) 3 SCC
752] and Shrilekha Vidyarthi (Kumari) v. State of U.P . [(1991)
1 SCC 212 : 1991 SCC (L&S) 742 : AIR 1991 SC 537] Where the
breach of contract involves breach of statutory obligatio n when
the order complained of was made in exercise of statutory power
by a statutory authority, though cause of action arises out of or
pertains to contract, brings it within the sphere of public law because
the power exercised is apart from contract. The freedom of the
Government to enter into business with anybody it likes is subject
to the condition of reasonableness and fair play as well as public
interest. After entering into a contract, in cancelling the contract
which is subject to terms of the statutory provisions, as i n the
present case, it cannot be said that the matter falls p urely in a
contractual field. Therefore, we do not think it would be appropriate
to suggest that the case on hand is a matter arising purely out of a
contract and, therefore, interference under Article 226 of the
Constitution is not called for. This contention also stands rejected.”
(Emphasis supplied)
The basis for interference was located in a statute which m ade
its presence felt.
37. In Binny Ltd. and Another v. V . Sadasivan and Others 17 ,
this Court was dealing with termination of services of respondents who
were working as Members of the Management, staff of the appe llant
company. The appellant company purported to terminate their services.
The respondents thereupon filed a writ petition under Article 226 of the
constitution of India. The appellant company contended that it was neither
a public authority nor did its action involve a public law element, and a
writ of Mandamus would not lie. The High Court granted only the
declaratory relief to the effect that the termination was illegal. We notice
the following: -
“30. A contract would not become statutory simply because it is
for construction of a public utility and it has been awarded b y a
statutory body. But nevertheless, it may be noticed that the
17 (2005) 6 SCC 657
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
Government or government authorities at all levels are increasingly
employing contractual techniques to achieve their regulatory aims.
It cannot be said that the exercise of those powers are free fr om
the zone of judicial review and that there would be no limits to the
exercise of such powers, but in normal circumstances, judi cial
review principles cannot be used to enforce contractual obligations.
When that contractual power is being used for public purpose, it
is certainly amenable to judicial review. The power must be used
for lawful purposes and not unreasonably. ”
(Emphasis supplied)
38. The Court went to hold that the decision of the employer to
terminate the services of the employees could not be sa id to have any
element of public policy. The Court did not find any public element in the
termination of the employees. We may at once notice that the appellant
in the said case was not a public sector unit as the appel lant in the
present case.
39. In G . Bassi Reddy v. International Crops Research Institute
and another 18 , the services of the appellant came to be terminated by
the respondent-ICRISAT. The Court went on to hold that the respondent
could not be treated as State under Article 12. The Court further
proceeded to hold that the Writ Petition was not maintainable against the
respondent, noticing that neither was the respondent set up by a Statute
nor were its activities statutorily controlled.
40. ABL (supra) marks a milestone, as it were, in the matter of
the superior court interfering in contractual matters where the State is a
player even after the contract is entered into. A petition was filed under
Article 226 wherein the respondent which was incorporated under the
Companies Act repudiated an insurance claim made by the appellant-
writ petitioner. This Court undertook an elaborate discussion of the earlier
case law. We find that this Court dealt with several obsta cles which
were sought to be posed by the respondent. They included disputed
questions of facts being involved, availability of alternate remedy, and
the case involving entertaining a money claim. This court went on to
hold as follows:
“27. From the above discussion of ours, the following legal principles
emerge as to the maintainability of a writ petition:
18 (2003) 4 SCC 225
41
(a) In an appropriate case, a writ petition as against a State or an
instrumentality of a State arising out of a contractual obligation is
maintainable.
(b) Merely because some disputed questions of fact arise for
consideration, same cannot be a ground to refuse to entertai n a
writ petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of monetary
claim is also maintainable.”
41. No doubt, we must also notice para 28 which serves as an
admonition against considering the availability of the remedy under Article
226 as an absolute charter to invoke jurisdiction in all cases.
“28. However, while entertaining an objection as to the
maintainability of a writ petition under Article 226 of the Constitution
of India, the court should bear in mind the fact that the power to
issue prerogative writs under Article 226 of the Constitution is
plenary in nature and is not limited by any other provisions of the
Constitution. The High Court having regard to the facts of the
case, has a discretion to entertain or not to entertain a writ petition.
The Court has imposed upon itself certain restrictions i n the
exercise of this power. (See Whirlpool Corpn. v. Registrar of
Trade Marks [(1998) 8 SCC 1].) And this plenary right of the
High Court to issue a prerogative writ will not normally be exercised
by the Court to the exclusion of other available remedies unless
such action of the State or its instrumentality is arbit rary and
unreasonable so as to violate the constitutional mandate of Article
14 or for other valid and legitimate reasons, for which the Court
thinks it necessary to exercise the said jurisdiction. ”
(Emphasis supplied)
42. We may also notice how this Court steered clear o f the
criticism that it was not following the principle laid down by this Court in
State of U.P . v. Bridge & Roof Co. (India) Ltd. 19 . The Court noted
that the said case did involve a contract which contained an arbitration
clause. It is found that in the case before it there was no arbitration
clause. In regard to the question as to whether the first respondent in the
said case was discharging a public duty or public function was involved
19 (1996) 6 SCC 22
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
while repudiating the claim of the appellants arising out of the contract,
the Court drew support from the judgment in Kumari Shrilekha
Vidyarthi (supra).
43. In Noble Resources Ltd. v. State of Orissa 20 , this court
followed ABL (supra). However, in the facts of the said case again the
matter involving refusal by a public authority to honour the contract in
the matter of purchase of Iron ore, the Court held as follows:
“15. It is trite that if an action on the part of the State is violative
of the equality clause contained in Article 14 of the Constitution
of India, a writ petition would be maintainable eve n in the
contractual field. A distinction indisputably must be made between
a matter which is at the threshold of a contract and a breac h of
contract; whereas in the former the court’s scrutiny would be
more intrusive, in the latter the court may not ordinarily exercise
its discretionary jurisdiction of judicial review, unless it is found to
be violative of Article 14 of the Constitution. While e xercising
contractual powers also, the government bodies may be subjected
to judicial review in order to prevent arbitrariness or favouritism
on their part. Indisputably, inherent limitations exist, but it would
not be correct to opine that under no circumstances a writ will lie
only because it involves a contractual matter.”
44. The court went on to approve of ABL (supra) and observed
that this Court had declared that no decision lays down as an a bsolute
rule that in all cases of disputed questions of fact, the parties should be
relegated to a civil Court. We may also notice paragraph 29:
“29. Although the scope of judicial review or the development of
law in this field has been noticed hereinbefore particularly in the
light of the decision of this Court in ABL International Ltd. [(2004)
3 SCC 553] each case, however, must be decided on its own
facts. Public interest as noticed hereinbefore, may be one of the
factors to exercise the power of judicial review. In a case where
a public law element is involved, judicial review may be permissible.
(See Binny Ltd. v. V . Sadasivan [(2005) 6 SCC 657 : 2005 SCC
(L&S) 881] and G .B. Mahajan v. Jalgaon Municipal Council
[(1991) 3 SCC 91]”
20 (2006) 10 SCC 236
43
45. Of further relevance to notice is the case of the responde nt
therein that only because the price of iron ore increased in the international
market, the appellant had filed the writ petition only in February 2004. It
was found that the said contention was not wholly miscon ceived.
Thereafter the court went on to following observations:
“41. The submission of Mr Desai that rise in international price
would not by itself be a relevant consideration to rescind the
contract may be correct, but then the same was not the sole ground
for Respondent 2 to refuse to supply iron ore fines to the appellant.
42. Moreover, certain serious disputed questions of fact have arisen
for determination. Such disputed questions of fact ordinarily could
not have been entertained by the High Court in exercise of its
power of judicial review.”
46. In the context of upgradation of aided schools and a complaint
of discrimination, we notice the following observations of this court in
State Of Kerala and others v. K. Prasad and another 21 .
“ Para 11. This Court in Shrilekha Vidyarthi v. State of U.P. [(1991)
1 SCC 212: 1991 SCC (L&S) 742] held that every State action, in
order to survive, must not be susceptible to the vice of arbitrariness
which is the crux of Article 14 and basic to the rule of law , the
system which governs us, arbitrariness being the negation of the
rule of law. Non-arbitrariness, being a necessary concomitant of
the rule of law, it is imperative that all actions of e very public
functionary in whatever sphere must be guided by reason and not
humour, whim, caprice or personal predilections of the pe rsons
entrusted with the task on behalf of the State and exercise of all
powers must be for public good instead of being an abuse of
power.”
47. We may notice that as to what constitutes arbitrar iness fell
for consideration by this court in a case which involved cancellation of
the examination held as part of a recruitment process, in E ast Coast
Railway and another v. Mahadev Appa Roa and others 22 . We notice
the following passages which are apposite for this case.
“19. Black’s Law Dictionary describes the term “arbitrary” in the
following words:
21 (2007) 7 SCC 140
22 (2010) 7 SCC 678
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
“Arbitrary. —1. Depending on individual discretion; spe cif.,
determined by a judge rather than by fixed rules, procedures, or
law. 2. (Of a judicial decision) founded on prejudice or preference
rather than on reason or fact. This type of decision is often termed
arbitrary and capricious.”
20. To the same effect is the meaning given to the expressi on
“arbitrary” by Corpus Juris Secundum which explains the term in
the following words:
“Arbitrary.—Based alone upon one’s will, and not upon any course
of reasoning and exercise of judgment; bound by no law;
capricious; exercised according to one’s own will or caprice and
therefore conveying a notion of a tendency to abuse possession
of power; fixed or done capriciously or at pleasure, wi thout
adequate determining principle, non-rational, or not done or acting
according to reason or judgment; not based upon actuality but
beyond a reasonable extent; not founded in the nature of things;
not governed by any fixed rules or standard; also, in a somewhat
different sense, absolute in power, despotic, or tyrannical; harsh
and unforbearing. When applied to acts, ‘arbitrary’ has been held
to connote a disregard of evidence or of the proper weight thereof;
to express an idea opposed to administrative, executive, judicial,
or legislative discretion; and to imply at least an element of bad
faith, and has been compared with ‘willful’.”
xxx xxx xxx
23. Arbitrariness in the making of an order by an authority can
manifest itself in different forms. Non-application of mind by the
authority making the order is only one of them. Every order passed
by a public authority must disclose due and proper application of
mind by the person making the order. This may be evident from
the order itself or the record contemporaneously main tained.
Application of mind is best demonstrated by disclosure of mind by
the authority making the order. And disclosure is best done b y
recording the reasons that led the authority to pass the orde r in
question. Absence of reasons either in the order passed by the
authority or in the record contemporaneously maintained is clearly
suggestive of the order being arbitrary hence legally unsustainable.”
45
48. We would, therefore, sum up as to when an act is to be treated
as arbitrary. The court must carefully attend to th e facts and the
circumstances of the case. It should find out whether the impugne d
decision is based on any principle. If not, it may unerringly point to
arbitrariness. If the act betrays caprice or the mere exhibition of the
whim of the authority it would sufficiently bear the insignia of arbitrariness.
In this regard supporting an order with a rationale which in the
circumstances is found to be reasonable will go a long way t o repel a
challenge to state action. No doubt the reasons need not in e very case
be part of the order as such. If there is absence of good faith and the
action is actuated with an oblique motive, it could be chara cterised as
being arbitrary. A total non-application of mind without due regard to the
rights of the parties and public interest may be a clear indicator of arbitrary
action. A wholly unreasonable decision which is little different from a
perverse decision under the Wednesbury doctrine would qualify as an
arbitrary decision under Article 14. Ordinarily visiting a party with the
consequences of its breach under a contract may not be an arbi trary
decision.
49. We may now notice the judgment of this court in J oshi
Technologies International Inc. v. Union of India and others 23 , which
is also relied upon by the learned Additional Solicitor General. The said
case actually involved the complaint of the writ petitioner therein that it
was entitled to the benefit of Section 42 of the Income Tax Act , 1961
which provided for certain deductions. The petitioner had entered into
an agreement with the respondent, the Government of India. The case
of the respondent, inter alia, was one denying the case of the petitioner
that the omission of Section 42 was by oversight. The prayer in the writ
petition itself inter alia was essentially to declare entitlement to the
deduction under Section 42, inter alia. It is while dealing with the said
case that this court no doubt proceeds to, inter alia, lay down as following
after adverting to ABL limited (supra) also:-
“69. The position thus summarised in the aforesaid principles has
to be understood in the context of discussion that preceded which
we have pointed out above. As per this, no doubt, there is no
absolute bar to the maintainability of the writ petition e ven in
contractual matters or where there are disputed questions of fact
or even when monetary claim is raised. At the same time,
23 (2015) 7 SCC 728
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
discretion lies with the High Court which under cer tain
circumstances, it can refuse to exercise. It also follows that under
the following circumstances, “normally”, the Court would n ot
exercise such a discretion:
69.1. The Court may not examine the issue unless the action has
some public law character attached to it.
69.2. Whenever a particular mode of settlement of dispute is
provided in the contract, the High Court would refuse to exercise
its discretion under Article 226 of the Constitution and relega te
the party to the said mode of settlement, particula rly when
settlement of disputes is to be resorted to through the mea ns of
arbitration.
69.3. If there are very serious disputed questions of fact which
are of complex nature and require oral evidence for their
determination.
69.4. Money claims per se particularly arising out of contractual
obligations are normally not to be entertained except in exceptional
circumstances.”
“70. Further, the legal position which emerges from va rious
judgments of this Court dealing with different situations/aspects
relating to contracts entered into by the State/public authority with
private parties, can be summarised as under:
70.1. At the stage of entering into a contract, the State acts purely
in its executive capacity and is bound by the obligations of fairness.
70.2. State in its executive capacity, even in the contractual field,
is under obligation to act fairly and cannot practi se some
discriminations.
70.3. Even in cases where question is of choice or consideration
of competing claims before entering into the field of contr act,
facts have to be investigated and found before the question of a
violation of Article 14 of the Constitution could arise. If those
facts are disputed and require assessment of eviden ce the
correctness of which can only be tested satisfactorily by taking
detailed evidence, involving examination and cross-examination
of witnesses, the case could not be conveniently or satisfactorily
decided in proceedings under Article 226 of the Constitution. In
47
such cases the Court can direct the aggrieved party to re sort to
alternate remedy of civil suit, etc.
70.4. Writ jurisdiction of the High Court under Article 226 of the
Constitution was not intended to facilitate avoidance of obligation
voluntarily incurred.
70.5. Writ petition was not maintainable to avoid contractua l
obligation. Occurrence of commercial difficulty, inconvenience
or hardship in performance of the conditions agreed to in the
contract can provide no justification in not complying with the
terms of contract which the parties had accepted with open eyes.
It cannot ever be that a licensee can work out the licence if he
finds it profitable to do so: and he can challenge the conditions
under which he agreed to take the licence, if he fi nds it
commercially inexpedient to conduct his business.
70.6. Ordinarily, where a breach of contract is complained of, the
party complaining of such breach may sue for specif ic
performance of the contract, if contract is capable of being
specifically performed. Otherwise, the party may sue for damages.
70.7. Writ can be issued where there is executive a ction
unsupported by law or even in respect of a corporation th ere is
denial of equality before law or equal protection of law or if it can
be shown that action of the public authorities was without giving
any hearing and violation of principles of natural justice after holding
that action could not have been taken without observing principles
of natural justice.
70.8. If the contract between private party and the State/
instrumentality and/or agency of the State is under the realm of a
private law and there is no element of public law, the normal course
for the aggrieved party, is to invoke the remedies provided under
ordinary civil law rather than approaching the High Court under
Article 226 of the Constitution of India and invoki ng its
extraordinary jurisdiction.
70.9. The distinction between public law and private law element
in the contract with the State is getting blurred. However, it has
not been totally obliterated and where the matter falls p urely in
private field of contract, this Court has maintained the position
that writ petition is not maintainable. The dichotomy between public
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
law and private law rights and remedies would depend on the
factual matrix of each case and the distinction between the public
law remedies and private law field, cannot be demarcated w ith
precision. In fact, each case has to be examined, on its facts
whether the contractual relations between the parties bear insignia
of public element. Once on the facts of a particular case it is
found that nature of the activity or controversy involves publ ic
law element, then the matter can be examined by the High Court
in writ petitions under Article 226 of the Constitution of India to
see whether action of the State and/or instrumentality or agency
of the State is fair, just and equitable or that relevant factors are
taken into consideration and irrelevant factors have not gone into
the decision-making process or that the decision is not arbitrary.
70.10. Mere reasonable or legitimate expectation of a citizen, in
such a situation, may not by itself be a distinct enforceable right,
but failure to consider and give due weight to it may render t he
decision arbitrary, and this is how the requirement s of due
consideration of a legitimate expectation forms part of the principle
of non-arbitrariness.
70.11. The scope of judicial review in respect of disputes falling
within the domain of contractual obligations may be more limited
and in doubtful cases the parties may be relegated to adjudication
of their rights by resort to remedies provided for adjudication of
purely contractual disputes.”
50. In State of Kerala v. M.K. Jose 24 , the specific question with
which we are concerned with, namely, entertaining a writ petition in a
contractual matter and where the specific question was the validity of
the termination of the contract, fell for consideration. We may notice
the following:
“13. A writ court should ordinarily not entertain a writ petition, if
there is a breach of contract involving disputed questions of fact.
The present case clearly indicates that the factual dis putes are
involved.”
51. Thereafter, the court went on to consider in detail the judgment
of this Court in ABL (supra) and found that it was a case where the
court granted relief as the facts were absolutely c lear from the
24 (2015) 9 SCC 433
49
documentary evidence and it pertained to interpretation of such clauses
of the contract of insurance. We need notice only paragraph 20 in M.K.
Jose (supra). It reads as under:
“20. We have referred to the aforesaid authorities to highlight under
what circumstances in respect of contractual claim or challen ge
to violation of contract can be entertained by a writ court. It depends
upon facts of each case. The issue that had arisen in ABL
International [(2004) 3 SCC 553] was that an instrumentality of
a State was placing a different construction on the clauses of the
contract of insurance and the insured was interpreting the contract
differently. The Court thought it apt merely because something is
disputed by the insurer, it should not enter into the realm of disputed
questions of fact. In fact, there was no disputed question of fact,
but it required interpretation of the terms of the c ontract of
insurance. Similarly, if the materials that come on reco rd from
which it is clearly evincible, the writ court may exercise the power
of judicial review but, a pregnant one, in the case at ha nd, the
High Court has appointed a Commission to collect the evidence,
accepted the same without calling for objections fr om the
respondent and quashed the order of termination of contract. ”
(Emphasis supplied)
52. In State of U.P . v. Sudhir Kumar Singh and Others 25 , the
first respondent the successful tenderer had worked the contrac t for a
year when he was visited with cancellation. This Court exhaus tively
referred to the earlier case law including ABL (supra) and Joshi
Technology (supra) and held, inter alia, as follows: -
“23. It may be added that every case in which a citizen/per son
knocks at the doors of the writ court for breach of his o r its
fundamental rights is a matter which contains a “publi c law
element”, as opposed to a case which is concerned only with
breach of contract and damages flowing therefrom. Whenever a
plea of breach of natural justice is made against the St ate, the
said plea, if found sustainable, sounds in constitutional law as
arbitrary State action, which attracts the provisions of Article 14
of the Constitution of India - see Nawabkhan Abbaskhan v. State
of Gujarat (1974) 2 SCC 121 at paragraph 7. The present case is,
25 2020 SCC Online 847
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
therefore, a case which involves a “public law element ” in that
the petitioner (Respondent No. 1 before us) who knocked at the
doors of the writ court alleged breach of the audi alteram partem
rule, as the entire proceedings leading to cancellation of the tender,
together with the cancellation itself, were done on an ex p arte
appraisal of the facts behind his back.”
53. We have already concluded that PPA is not a Stat utory
Contract. However, that would not be the end of enquiry. Dr. A .M.
Singhvi, learned Senior Counsel, would point out that the contract, not
being a statutory contract, assumes relevance only for the p urpose of
deciding as to whether the Court should relegate the writ applica nt, to
alternate remedies. In other words, while the Court would retain its
discretion to entertain the petition or decline to do so, in the facts of each
case, there is no absolute taboo against the Court granting relief, even if
the challenge to the termination of a contract is made in th e case of a
contract, which is not statutory in nature, when the offending party is the
State. In other words, the contention is that the law in this field has
witnessed an evolution and, what is more, a revolution of sorts an d a
transformatory change with a growing realisation of the true ambit of
Article 14 of the Constitution of India. The State, he points out, cannot
play the Dr. Jekyll and Hyde game anymore. Its nature is cast in stone.
Its character is inflexible. This is irrespective of the activity it indulges
in. It will continue to be haunted by the mandate of Article 14 to act
fairly. There has been a stunning expansion of the frontiers of the Court’s
jurisdiction to strike at State action in matters arisi ng out of contract,
based, undoubtedly, on the facts of each case. It remains open t o the
Court to refuse to reject a case, involving State action, on the basis that
the action is, per se , arbitrary.
54. We may cull out our conclusions in regard to the points, which
we have framed:
i. It is, undoubtedly, true that the writ jurisdiction is a public
law remedy. A matter, which lies entirely within a private
realm of affairs of public body, may not lend itself for being
dealt with under the writ jurisdiction of the Court.
ii. The principle laid down in Bareilly Development Authority
(supra) that in the case of a non-statutory contract the rights
are governed only by the terms of the contract and the
decisions, which are purported to be followed, including
51
Radhakrishna Agarwal (supra), may not continue to hold
good, in the light of what has been laid down in ABL (supra)
and as followed in the recent judgment in Sudhir Kumar
Singh (supra).
iii. The mere fact that relief is sought under a contract which
is not statutory, will not entitle the respondent-State in a
case by itself to ward-off scrutiny of its action or inaction
under the contract, if the complaining party is able to
establish that the action/ inaction is, per se , arbitrary.
iv. An action will lie, undoubtedly, when the State purports to
award any largesse and, undoubtedly, this relates to the stage
prior to the contract being entered into [See R.D. Shetty
(supra)]. This scrutiny, no doubt, would be undertaken within
the nature of the judicial review, which has been declared
in the decision in Tata Cellular vs. Union of India 26 .
v. After the contract is entered into, there can be a variety of
circumstances, which may provide a cause of action to a
party to the contract with the State, to seek relief by filing a
Writ Petition.
vi. Without intending to be exhaustive, it may include the relief
of seeking payment of amounts due to the aggrieved party
from the State. The State can, indeed, be called upon to
honour its obligations of making payment, unless it be that
there is a serious and genuine dispute raised relating to the
liability of the State to make the payment. Such dispute,
ordinarily, would include the contention that the aggrieved
party has not fulfilled its obligations and the Court finds that
such a contention by the State is not a mere ruse or a
pretence.
vii. The existence of an alternate remedy, is, undoubtedly, a
matter to be borne in mind in declining relief in a Writ Petition
in a contractual matter. Again, the question as to whether
the Writ Petitioner must be told off the gates, would depend
upon the nature of the claim and relief sought by th e
petitioner, the questions, which would have to be decided,
26 (1994) 6 SCC 651
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
and, most importantly, whether there are disputed questions
of fact, resolution of which is necessary, as an indispensable
prelude to the grant of the relief sought. Undoubtedly, while
there is no prohibition, in the Writ Court even deciding
disputed questions of fact, particularly when the dispute
surrounds demystifying of documents only, the Court may
relegate the party to the remedy by way of a civil suit.
viii. The existence of a provision for arbitration, which is a forum
intended to quicken the pace of dispute resolution, is viewed
as a near bar to the entertainment of a Writ Petition (See in
this regard, the view of this Court even in ABL (supra)
explaining how it distinguished the decision of this Court in
State of U.P . and others v. Bridge & Roof Co. 27 , by its
observations in paragraph-14 in ABL (supra)].
ix. The need to deal with disputed questions of fact, cannot be
made a smokescreen to guillotine a genuine claim raised in
a Writ Petition, when actually the resolution of a disputed
question of fact is unnecessary to grant relief to a writ
applicant.
x. The reach of Article 14 enables a Writ Court to deal with
arbitrary State action even after a contract is entered into
by the State. A wide variety of circumstances can generate
causes of action for invoking Article 14. The Court’s
approach in dealing with the same, would be guided by,
undoubtedly, the overwhelming need to obviate arbitrary
State action, in cases where the Writ remedy provides an
effective and fair means of preventing miscarriage of justice
arising from palpably unreasonable action by the State.
xi. Termination of contract can again arise in a wide variety of
situations. If for instance, a contract is terminated, by a
person, who is demonstrated, without any need for any
argument, to be the person, who is completely unauthorised
to cancel the contract, there may not be any necessity to
drive the party to the unnecessary ordeal of a prolix and
avoidable round of litigation. The intervention by the High
Court, in such a case, where there is no dispute to be
27 (1996) 6 SCC 22
53
resolved, would also be conducive in public interest, apart
from ensuring the Fundamental Right of the petitioner under
Article 14 of the Constitution of India. When it comes to a
challenge to the termination of a contract by the State, which
is a non-statutory body, which is acting in purported exercise
of the powers/rights under such a contract, it would be over
simplifying a complex issue to lay down any inflexible Rule
in favour of the Court turning away the petitioner to alternate
Fora. Ordinarily, the cases of termination of contract by
the State, acting within its contractual domain, may not lend
itself for appropriate redress by the Writ Court. This i s,
undoubtedly, so if the Court is duty-bound to arrive at
findings, which involve untying knots, which are presented
by disputed questions of facts. Undoubtedly, in view of
ABL Limited (supra), if resolving the dispute, in a case of
repudiation of a contract, involves only appreciating the true
scope of documentary material in the light of pleadings, the
Court may still grant relief to an applicant. We must enter a
caveat. The Courts are today reeling under the weight of a
docket explosion, which is truly alarming. If a case involves
a large body of documents and the Court is called upon to
enter upon findings of facts and involves merely the
construction of the document, it may not be an unsound
discretion to relegate the party to the alternate remedy. This
is not to deprive the Court of its constitutional power as laid
down in ABL (supra). It all depends upon the facts of each
case as to whether, having regard to the scope of the dispute
to be resolved, whether the Court will still entertain the
petition.
xii. In a case the State is a party to the contract and a brea ch
of a contract is alleged against the State, a civil action in
the appropriate Forum is, undoubtedly, maintainable. But
this is not the end of the matter. Having regard to the position
of the State and its duty to act fairly and to esch ew
arbitrariness in all its actions, resort to the constitutiona l
remedy on the cause of action, that the action is arbitrary,
is permissible (See in this regard Kumari Shrilekha
Vidyarthi and others v. State of U.P. and others 28 ).
28 (1991) 1 SCC 212)
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
However, it must be made clear that every case involving
breach of contract by the State, cannot be dressed up and
disguised as a case of arbitrary State action. While the
concept of an arbitrary action or inaction cannot be cribbed
or confined to any immutable mantra, and must be laid bare,
with reference to the facts of each case, it cannot be a
mere allegation of breach of contract that would suffice.
What must be involved in the case must be action/inaction,
which must be palpably unreasonable or absolutely irrational
and bereft of any principle. An action, which is completely
malafide, can hardly be described as a fair action and may,
depending on the facts, amount to arbitrary action. The
question must be posed and answered by the Court and all
we intend to lay down is that there is a discretion available
to the Court to grant relief in appropriate cases.
xiii. A lodestar, which may illumine the path of the Court, would
be the dimension of public interest subserved by the Court
interfering in the matter, rather than relegating the matter
to the alternate Forum.
xiv. Another relevant criteria is, if the Court has entertained the
matter, then, while it is not tabooed that the Court should
not relegate the party at a later stage, ordinarily, it would be
a germane consideration, which may persuade the Court to
complete what it had started, provided it is otherwise a sound
exercise of jurisdiction to decide the matter on merits in the
Writ Petition itself.
xv. Violation of natural justice has been recognised as a ground
signifying the presence of a public law element and can
found a cause of action premised on breach of Article 14.
[See Sudhir Kumar Singh and Others (supra)].
WHETHER THERE IS AN ARBITRATION CLAUSE?
55. Before we proceed to deal further with the matter, we would
have to first find whether there is any arbitration clause. We have already
referred to the dispute resolution clause, namely, Article 13.2.1 and Article
13.2.3. They would appear to indicate that the clauses may not constitute
an arbitration clause. As far as Article 13.3.1. is concerne d, to which
resort is to be made when the dispute remains unresolved under 13.2.3,
55
it deals with disputes arising from a claim for any matter relating to the
tariff. Therefore, we would take the view that it may not b e a case
where the PPA provides for an arbitration clause capable of determining
the lis in question. The situation therefore contemplated in U.P . Roof
(supra) as laid down in ABL (supra) does not exist.
THE IMPACT OF THE JUDGMENT IN THE FIRST
WRIT PETITION
56. Taking up point no. 5., viz. , the effect of the judgment of the
High Court in the earlier round, we must notice indeed that this is a case
which represents the second round of the litigation. In the earlier round
the respondents had successfully invoked the jurisdiction under Article
226 when it was served with the order of termination of the contract
dated 11.08.2017. We have already noticed the fate of the said ca se.
The first battle which commenced in the year 2017 resumed as it were
with the present writ petition. We are not oblivious to the fact that the
appellant did not think it fit to challenge the verdict in the first round of
litigation. No doubt, the case of the appellant is that the appellant was of
the view that the court has left it free to the appellant to take steps under
the contract for termination of the contract. It is the case of the appellant
in fact, that the judgment of the High Court in the earlier round would
not be an obstacle for the appellant to revisit and terminate the contract
for the reason that the PPA made it incumbent on the ap pellant to
terminate the contract under Article 2.1(d) if the contractor did not fulfil
the conditions subsequent even after the expiry of 210 days and a further
period of nine months after the commencement of PPA. We must
examine whether the earlier judgment, in fact, in law permits the appellant
to re-open the said issue. A perusal of the judgment dated 20.6.2017
would reveal that the court was dealing with the challenge to the order
dated 11.08.2017. The order dated 11.08.2017 would reveal that the
appellant has found that there is a delay of 54 days in achiev ing the
condition subsequent deadline. After considering the representation by
the respondent, the appellant found that there is no merit in the case of
force majeure and there was no justification for the delay in achieving
conditions subsequent. Thereafter, the appellant, in terms o f Article
2.5.1(d), terminated the PPA. Still further, a sum of Rs.1180.50 la khs
was found recoverable as penalty in terms of Article 2.5. It is this order
which was challenged. Thereafter we find that the High court went on
to notice that in a similar case, viz ., relating to New Clean Energy Pvt.
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
Ltd., the petitioner therein admittedly commissioned the project within
the time prescribed except that there was a delay of 16 days in achieving
the first milestone.
57. Here we must understand the word ‘first milesto ne’ as
fulfilment of the conditions subsequent. In regard to fulfilment of said
milestone for which there was a delay of 16 days in the case of Renew
clean Energy, there was a delay of 54 days in the case o f the first
respondent. It is further noticed by the High Court that there w as an
order passed in favour of the Renew clean energy setting a side the
termination of the contract in the said petitioner’s case as confirmed by
this Court. Next the High Court went on to record that there is a dispute
as to whether the respondent had commissioned the power proje ct in
the present case. We notice that an attempt was made by the appellant
to justify the termination on the basis that the res pondent had not
commissioned the power project within the time fixed. The High Court
proceeds to notice that the aspect of commissioning the project was not
the basis for terminating the contract. Relying on Mohinder Singh Gill 29 ,
the appellants were not permitted to supplement the reasons for
termination. Finally, the High court has proceeded to find that since the
similar reason for termination of the agreement in the com munication
dated 11.8.2017 was not found justified in the case of Renew Clean
Energy, the impugned communication dated 11.08.2017 was set aside.
It is thereafter that the liberty was given to the appellants to pass fresh
orders in terms of the PPA in accordance with law.
58. The appellants would persuade us to hold that the High Court
intended, by the liberty granted to leave it open to the appellant to pass
orders invoking its power under the PPA which would not only include
termination of the PPA based on respondent not commissioning the project
within the time but also revisit the aspect relating to non-fulfilment of the
conditions subsequent. The respondent would join issue with the appellant
on the score that judgment of the High Court must be understood as
meaning that on the issue relating to non-fulfilment of the conditi ons
subsequent the court made its pronouncement on merits with reference
to the decision in Renew Clean Energy. All that was left open was the
question related to the delay in commissioning the project.
59. Learned Additional Solicitor General apart from reitera ting
his contention would point out that the earlier judgment should not be
29 (1978) 1 SCC 405
57
treated as res judicata and the only reason appellant did not challenge
the High court judgment, dated 20.06.2018, was the liberty granted. He
would further submit that at any rate even proceeding on the basis that
the High court could not revisit the issue of the non-fulfilment of the
conditions subsequent, the decision of the High Court would not stand in
the way of this Court considering whether the order which is impugned
in this case which includes the issue relating to non-fulfi lment of the
conditions subsequent is sustainable. This is apart from pointing out that
even in the case of Renew Clean Energy, this Court in its order refusing
to interfere in the judgment of the High Court has made it cle ar that it
was not going into the merits of the said contention having regar d to
observations which had been made, namely, that the contractor therein
being faced with unavoidable circumstances as also the factum of huge
investment made in the project.
60. Having noticed the contents of the decision of the High court
dated 20.06.2018 and also bearing in mind the terms of the notice of
termination dated 11.08.2017 we are of the view that the High C ourt
must be treated as having interfered with the order base d no doubt on
the order of the said court as affirmed by this Court in the case of
Renew Clean Energy. Noticing, however, the contentions based on the
aspect relating to project not being commissioned by t he respondent
within time and further clearly finding that the impugned order was not
premised on project not being commissioned the impugned order was
set aside finding that the termination was not justified as regards to non-
fulfilment of conditions subsequent. It is thereafter that the liberty was
granted and it had to pass fresh order in terms of the PPA. We have to
take the order as it is and we are of the firm view that the analysis of the
order leads us to only one conclusion which is that the High Court intended
to only leave open the right of the appellant to invoke its power under the
contract in regard to the issue relating to commissioning of the project or
rather in the matter of default in commissioning the proje ct. It would
neither be legal nor equitable to permit the appellant to contend that the
issue relating to not having fulfilled the conditions subsequent c an be
canvassed all over again.
AN ASIDE ?
THE STATE LOAD DISPATCH CENTRE (RESPONDENT
NO.5): ITS STAND AND THE IMPACT OF THE SAME
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
61. Respondent No.5 filed a counter affidavit in this Court. It
claims to be the ‘Authority charged to perform functions under Section
32 (2) of the Electricity Act, 2003. Its responsibility is limited to monitoring
and controlling of existing Grid elements and generating stations keeping
the account of energy transmitted through the Grid. It specifically states
that its role emerges after commissioning of the generating plant. It further
states all activities prior to readiness of generator to inject power into
the Grid are beyond its purview. The further stand is that none of the
regulatory provisions allows it to interfere in pre-requisit e regulatory
compliance by the generator before injecting of power int o the Grid.
There is reference to short-term open access for wh ich there are
regulations. In respect of Renewable Energy generators intend ing to
connect with the Grid, certain regulatory requirements, before injecting
of power therein, are to be complied with. They are regis tration, data
and speech communication facility, interface metering and communication
of meter data through automatic meter reading.
Single line diagram indicating connectivity with the grid duly
certified by MPPTCL (fourth respondent), when connected to 132KV
and above, inter alia , copy of connection agreement with the fourth
respondent, inter alia , information regarding sale of power under long-
term access, medium-term open access or short-term open access,
approval of CEIG for construction, operation and maintenance of electrical
plans and electrical lines under Section 73C of the Electricity Act, 2003
and approval of Power, Telecommunication and Coordination Committee
(PTCC). It is further stated that on compliance with procedures it first
issues a unique code for charging power evacuation line. When the line
holds for a reasonable time, unique code for injection is issued. Real
time generation is monitored. If it is satisfied with the data recorded by
the interface meters (Main and check) then a generating station is deemed
to be commissioned. It is pointed out by letters dated 2.12.2015 an d
3.11.2016 respondent No.5 requested Respondent No.1 for compliance
of the procedure/response. Mandatory documents were not submit ted
for injecting of Grid except registration. CEIG approval is only for
renewable energy generation units and equipments insta lled in the
Switchyard. Respondent No.1 has not obtained CEIG ap proval of
transmission line. The details of the interface meters, metering equipments
are not mentioned in the report of CGIG. It is pointed out that other units
including M/s. New Clean Energy was ready for evacuation of powe r
with all regulatory requirements.
59
62. In the reply affidavit filed by the first respondent to the said
counter affidavit, it is complained that respondent No.5 though a party in
the earlier writ petition as also in the present writ p etition it never
responded, objecting to the readiness of first respondent in August 2017.
The belated reply in the High Court is stated to seem as ill motivated and
done at the instance of the appellant. Furthermore, the first respondent
points out that it is not the case of the first respondent t hat its project
was commissioned. Its case was that it was complete in all respects and
would have commissioned before the expiry of 24 months but for the
illegal termination on two occasions as noted. In regard to non-compliance
with certain regulatory requirements, various steps taken by it are referred
to.
63. As far as registration is concerned, it was comple ted on
15.12.2016. In regard to data and speech communication facility, it is
stated by Respondent No.1 that it is completed on 23.03.2017. In the
said communication, on a letterhead showing the name of the fourth
respondent and also showing the name of the fifth respondent, it is stated
that the telemetry scheme for the 100MW solar power plant was generally
in order and accepted for implementation, subject to four condi tions
stipulated therein. Thereafter, it is stated that “ it is, therefore, required
that the telemetry and voice communication from the control centre
of the proposed power plant upto Back Up SLDC Bhopal/Sub-LD C
Indore/SLDC Jabalpur be arranged before synchronization of your
power plant. It may please be noted that synchronizat ion of plant
with grid shall not be allowed without commissioning of telemetry
and voice communication.” It is seen signed by the Superintending
Engineer (LD:E&T), SLDC, MPPTCL, Jabalpur. As far a s the
requirement of connection agreement, it has been stated in t he reply
affidavit of the first respondent that such connection agreement was,
indeed, executed between Respondent No.1 and Respondent No.4. The
agreement is dated 18.05.2017. At this juncture, we may notice that a
Sur-Rejoinder has been filed by Respondent No.5. Having regard to the
connection agreement, all that is stated is, till date, Resp ondent No.5
was not provided with a copy by the first respondent. It is also stated
that Respondent Nos. 4 and 5 are two distinct entities and, therefore, it
was required for compliance that the same should have been submitted
to Respondent No. 5. We have already noticed that letter dated 23.07.2017
is on the same letterhead, showing the names of Respondent Nos. 4 and
5 and signed by the Superintending Engineer, wherein also, the names of
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
Respondent Nos. 4 and 5 appear. It is a little intriguing and strange, that
the fifth respondent did not know about the agreement and referred to it
as a requirement and as though it had not been complied with by the first
respondent. The first respondent has stated that, with regard to the single-
line diagram indicating connectivity with the grid, that it was completed
on 19.10.2016. An extension was sought for by Respondent No.1, in
which required diagrams were furnished to Responden t No. 4.
Respondent No.4, it is stated, has granted permission for cha rging the
transmission line connected from the project to the STU. Diagrams were
also, it is stated, approved by the CEIG. The answer of Respondent
No.5 in the Sur-Rejoinder that the letter dated 29.08.2017 was not issued
by Respondent No.5 but by Respondent No.4. It is admitted that it is
stated therein that the line is ready for charging but fur ther necessary
action, like issuing of charging code, has to be taken from Respondent
No.5 by Respondent No.1. It is again stated that Respondent No.1 has
never approached Respondent No.5 with copy of letter dated 29.08.2017
and CEIG approval for readiness of evacuating line. It is aga in stated
that Respondent No.5 is not an arm or even unit of Respondent No.4. In
regard to the contention that information regarding sale of pow er for
access, including long-term access, was not made available by the first
respondent. It is pointed out that the first respondent set up the project to
supply power to the appellant only as per the PPA a nd the said
requirement was not applicable.
64. The fifth respondent in the Sur-Rejoinder responded by pointing
out that Respondent No.5 is the Nodal Body for managing the grid
operations and within the State and it is generally seen that if the plant is
commissioned the same cannot be left idle and be allowed to inject power
into the grid, and it was in this regard, it was mentioned that if a third-
party sale was to be undertaken by Respondent No.1 so that its plant
was not left idle, then, it was incumbent on Respondent No.1 to have
obtained open access. We find that as per Article 9.8 of the PPA, the
first respondent was obliged to sell the contracted capacity for a period
of twenty-five years from COD. Elaborate provisions have been made,
which would visit the first respondent with monetary compensation to
be paid to the appellant, in case of breach. Article 9.7 also provides for
the obligation of the appellant to buy power for twenty-five years. It is
only if there was refusal or inability to buy by the appella nt, fully or
partially, or in the event of default, as per Article 9.5, leading to termination,
61
the first respondent was left free to sell power to a third party, which
sale was to be regulated by certain terms.
65. As regards another requirement, viz., approval of the CE IG
for construction, operation and maintenance of the electrical plants and
electrical lines, it is the case of the first respondent that such a pproval
was obtained by letter dated 10.08.2017. It was als o marked to
Respondent No.4. CEIG approval for the electrical plant was received
on 09.08.2017. Respondent No.4, it is pointed out, had also, on 24.08.2017,
issued a Joint Inspection Report certifying that the proj ect may be
charged. In fact, we find, in the Joint Inspection Report is sued by the
fourth respondent that:
“Newly constructed 132KV D.C.D.S. line from 400KV P S
Chhegaon to 50MW Pooling Station of M/S Sky Power Solar
India Pvt. Ltd. And 50MW Pooling Station of M/S Sky Power
Southeast Solar India Pvt. Ltd. At village Chhirbel has be en
jointly inspected with EE (EHT-M) MPPTCL, Indore on dt.24 /
08/2017. During Joint Inspection No. any major defects has
been found and line. May be charged.”
(Emphasis supplied)
66. In regard to the same, Respondent No.5 in the Sur-Rejoinder
would state that it is misleading and incorrect on the basis th at it has
been averred by Respondent No.1 that the approval of the CEIG f or
readiness of 132KV double circuit line for connection with the grid was
submitted by the sister concern of Respondent No.1, while reque sting
code for charging the 132KV line for the sister concern. It is stated that
in the approval issued on 10.08.2017, there is no mention that the second
line will be utilised by Respondent No.1. The letter of the CEIG dated
10.08.2017 is said to be addressed to the sister concern. There wa s to
be a specific approval of CEIG in favour of Respondent No .1. Copy
was not marked to Respondent No.5 but only marked to Respondent
No.4. It again reiterated that they are two different entities.
67. It appears to us that though letter dated 10.08.2017 is addressed
to the sister concern of Respondent No.1, viz., Sky Power Solar India
Pvt. Ltd., what was the subject matter of the communication wa s for
100MW solar power project, and what is more, and it wa s for the
establishment of 132KV ‘dual’ circuit transmission. This understanding
of this CEIG Report is clear from the Joint Inspecti on Report of
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
Respondent No.4 as Respondent No.1 has entered into a PPA for 50MW,
and the sister concern, apparently, had a PPA for 50MW. Lastly, even
given an opportunity, this is a matter which could have been clarified by
the CEIG, for which no opportunity appears to have been given. We
bear in mind Article 9.1 of the PPA. From the Joint Inspection Report,
bearing in mind that 132KV line had a dual circuit, the same line was to
be used by the first respondent and its sister concern. This appears to be
the only possible meaning on a joint reading of the CEIG Report dated
10.08.2017 and Joint Inspection Report dated 24.08.2017. We stand
fortified in this regard by the report dated 21.04.2018 als o where it is
inter alia stated as follows:-
“1. Present Status of Transmission Line for power evacuation
from Power Plant to Grid Substation
132 kV DCDS line is found erected between Pooling Substation
to 400 kV Chhegaon (Torni)Substation. One circuit is used for
already existing 50 MW plant of M/s Sky Power and 2 nd circuit is
proposed to be used for M/s Sky Power South East Solar India
Pvt. Ltd. at village Chirbel, Distt. Khandwa, for whi ch site
verification visit is conducted.”
68. The next requirement, according to the fifth respondent was
that approval of the PTCC was required. The first respondent has, in
the reply, stated the said requirement was completed on 05.09.2017. We
find that Chief Engineer (Procurement) of the fourth respondent has
recorded in the communication dated 05.09.2017 that PTCC had accorded
PTCC route approval:
“With reference to the subject cited above, DET (PTCC), Mumbai
has accorded PTCC route approval for charging 132KV DCDS
line from 400kV S/s Chhegaon to 100MW Solar Power Project
of M/s SkyPower Solar India & M/s SkyPower Southeast Solar
India Pvt. Ltd. Chhirbel, Dist. Khandwa.”
69. The fifth respondent, in the Sur-Rejoinder, in response to the
same, would respond by stating that the Respondent No.4 gr anting
approval, did not mean that the same was issued with the knowledge or
concurrence of Respondent No.5. We only remind ourselves that in the
Counter Affidavit filed by Respondent No.5, Respondent No.5 had only
stated against Requirement No.VIII that there was the requi rement of
approval of PTCC. What is reflected in letter dated 05.09.2017 is that
63
DET [PTCC] has accorded PTCC route approval. The approval i s not
granted by the fourth respondent. We are a little mys tified by the
statement that the PTCC approval should be one issu ed with the
knowledge and concurrence of the fifth respondent.
70. It is, no doubt, true that as regards the contention of the fifth
respondent that there must be interface metering and communication of
the meter data through automatic meter reading (AMR), which details
are to be provided to the SLDC before the commissioning of the plant,
there is no specific averment by the first respondent. Her e we must
notice that it is for the first time such a plea is being raised by the fifth
respondent. Even proceeding on the basis that it was a requirement; it is
required to be provided before commissioning. This is not a matter, which
could not be set right at any rate, if an opportunity to remove a defect
was provided, as we shall see, may be contemplated under Article 9.1.
It is also true that as far as the data and speech communication facility,
the first respondent has claimed that it was completed on 23 .03.2017.
We have already referred to it also. The stand of the fifth respondent is
that there is approval but it is only in principle. It is complained that till
date, the telemetry and voice communication was not working, in spite
of the fact that by letter dated 03.04.2017, relevant IP addres s for real
time data communication was furnished. It is not functional till date, in
the case of the first respondent, whereas, in regard to its sister concern,
it is operational. A letter dated 14.10.2021 is produced to indicate that
the telemetry of the first respondent was not integrated and no real time
data was received from the IP address provided to it. Even, in regard to
this matter, if an opportunity was to be given in law, to the first respondent
under Article 9.1, it is not something which may be not achievable.
71. We are also dealing with these aspects on the basis of an
affidavit filed raising such issues for the first time by the fifth respondent.
The fifth respondent had all the opportunity in the writ petition to raise
such contentions. Even in the Review Petition, there is only adoption of
the contentions of the appellant.
72. Emphasis is placed on the statement of Respondent no.5 by
respondent no.1 wherein it is stated “whereas though the generati ng
station is ready for generation of power but the powe r cannot be
evacuated into the grid in the absence of transmission line”. This is taken
as an admission of the readiness of the first respondent for generation of
power. It is pointed out further that necessary approval was taken before
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
December 2016 to August 2017 for operating the transmission line .
Respondent No.1 was not allowed to commission. Reliance is also placed
on the inspection report of the appellant to show that the tra nsmission
line was ready. The examples about other operators are br ushed aside
as irrelevant. It is the generator’s prerogative to sell power in the open
market.
73. A Sur-Rejoinder is filed by respondent No.5. Therein, it has
interestingly produced its return in the review petition filed by the appellant
before the High court. Therein we may notice that it referred to Section
32(2) of the Electricity Act and its functions. Thereafter it has stated as
follows:
“3. That, in accordance with Electricity act, 2003, role of SLDC
comes after commissioning of the generating plant a nd its
evacuating transmission lines. On receipt of commissi oning
certificate of a generator, connectivity with the Grid, m etering
arrangement and other regulatory compliances, SLDC accords
permission of injection of power into the Grid. Further, SLDC
schedules power of generator to the beneficiary/consumer if the
valid Power Purchase Agreement exists between buyer and seller.
4. That, writ proceeding in the instant petition is regarding
completion of commissioning of solar Generating Plant of M/ s.
Sky Power Southeast Solar India Pvt. Ltd., whereas the
responsibility of SLDC begins after commissioning of the Solar
Generating Plant and other regulatory compliances. As per
provisions of Electricity Act, 2003 and MPEGC, commissioning
certification is beyond the jurisdiction of SLDC.
6. That, the answering respondent is more of a formal respondent
as the agreement was entered into between MPPMCL and the
Original Petitioner in Writ Proceedings which is M/s. Sky Power.”
74. No doubt, it has also stated in paragraph-7 that it adopts all the
facts and grounds raised by the review petitioner, namely, the appellant.
75. It will be noticed that though respondent no.5 was a party to
the earlier writ petition as much as it is a party in the present writ petition,
respondent no.5 has not filed any counter affidavit in either of the writ
petitions. It is only in the review petition that the respon dent no.5 has
filed a reply and we have noticed its stand. The stand appears to be that
it is more of a formal respondent. Its role comes i n only after
65
commissioning. It is in this Court that there has been blossoming of its
case for the first time. It is also admitted by respondent No.5 that it is
not concerned with the pre-commissioning. It is its specific stand that all
the activities prior to readiness of the generator to inject power are beyond
its purview. It has specifically stated that its role c omes only after
commissioning the project. First respondent states t hat it has not
commissioned the project. Its only case is that it was ready to commission
the project within 24 months as provided in the PPA but it was illegally
prevented from doing it.
76. We may only observe that the fifth respondent has, in the Sur-
Rejoinder, owned up letter dated 23.03.2017 as the letter it has sent. The
said letter is in the letterhead of the fourth responden t and therein the
name of the fifth respondent is also shown. It would appear that the fifth
respondent is created under Section 31 of the Electricity Act, 2003.
Section 31 reads as follows:
“Constitution of State Load Despatch Centres.—(1) The State
Government shall establish a Centre to be known as the St ate
Load Despatch Centre for the purpose of exercising the powe rs
and discharging the functions under this Part.
(2) The State Load Despatch Centre shall be operated by a
Government company or any authority or corporation established
or constituted by or under any State Act, as may be notifie d by
the State Government:
Provided that until a Government company or any authority
or corporation is notified by the State Government, the St ate
Transmission Utility shall operate the State Load Despatch Centre:
Provided further that no State Load Despatch Centre shall
engage in the business of trading in electricity.”
77. Therefore, it would appear to us that actually t he fifth
respondent is to be operated by the State Transmission Utility, which is
defined in Section 2(67) as the Board (defined as the State Electricity
Board) or the Government company specified by the State Government
under Section 39(1), unless it is operated by a Government company or
any authority or corporation established or constituted by or under and
State Act. It would, therefore, appear to us that if the fourth respondent
is the State Transmission Utility, it would be the Body to operate the fifth
respondent. The attempted disassociating of the fifth responde nt from
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
the fourth respondent, appears to us to be without justification. However,
we leave the matter there. We may conclude nearly th at all the
requirements were met. There remained the metering requests and the
aspects about furnishing data. They clearly appear to be matters which
could have been remedied at any rate if a default notice was given.
THE NARRATIVE RESUMES
78. At this juncture, we must make certain observations. Wh ile
the law has evolved from the hands-off approach to one of contract s
lending ground for writ courts making a foray into decisions by State and
its instrumentalities even in contractual matter, there are certain principles
which we have already in fact generally noticed. We have already found
that the contract in question, i.e., the PPA, is not a statutory c ontract.
We have also noticed that even if it is a non-statutory contract, there is
no absolute bar in dealing with a cause of action based on acts or omission
by the State or its instrumentalities even during the course of the working
of a contract. We again reiterate that a monetary claim ari sing from a
contract may be successfully urged by a writ applicant but the premise
would not be a mere breach of contract. Being part of publ ic law the
case must proceed on the basis of there being arbitrariness vitiating the
decision. The matter should not fall within a genuinely disputed question
of facts scenario. The dispute which must be capable of being resolved
on a proper understanding of documents which are not in dispute may
furnish a cause of action in a writ court. Such was the ca se in ABL
(supra). What is this litigation all about? This litigation is not about
enforcing a monetary claim. The writ petition lays a challen ge to the
termination of the contract. A termination of the contract, no doubt, again
may not be immune if it is found to be afflicted with the vice of
arbitrariness. Interference again may be refused if the c ourt finds that
the case really belongs to the small area with unclear contours where it
can be appropriated as a private law dispute. The disti nction between
public law and private law has concededly been reduce d to nearly
imperceptible terms but the distinction in law remains. As far as the
public law aspect is concerned, we are inclined to take the view that in
view of what has been laid down in Shri Vidhyarthi Lekha (supra), the
impact of the action in a contractual matter in the facts by public authority
is felt in public domain. We are dealing with the action of the appellant in
terminating the contract dealing with the right to generate r enewable
energy and for supplying it to the consumers. Supply of power and i ts
67
consumption are imperative and indispensable needs for not only the
common man but also for the efficient functioning of trade and industry.
Decisions in this domain do impinge on public interest. Therefore, we
would not be inclined to shut the doors on the first respondent in this
matter. We also bear in mind that this is the second round of litigation.
As noticed already, in the first round, the first respondent did succeed.
79. Having found that though a non-statutory contract and that
there is no absolute prohibition against judicial review on the score that
action is shown to be arbitrary, the questions which would fall for further
consideration are: (1) whether action is arbitrary (2) the projected disputes
of facts and their impact; (3) what is the impact of the principle that
there must be overwhelming public interest in favour of the writ applicant
for the writ court to interfere.
THE ARGUMENT OF ‘OVERWHELMING PUBLIC
INTEREST’
80. The case based on ‘overwhelming public interest not b eing
present in this case is based on the following submissions by the learned
Additional Solicitor General. It is pointed out that under the PPA, if the
appellants are compelled to comply with the impugned Judgme nt and
that too for a period of twenty-five years, it would be liable to purchase
power at the rate of Rs. 5.109/- unit. On the other hand, if the Writ
Petition filed by the first respondent is dismissed, there woul d be no
obligation and consequent burden. It is important to notice t hat the
appellant would be compelled to pass on the burden to the ul timate
consumers. All of this is to be viewed in the scenario, when power is
available at a cheaper rate in the market. In other words, public interest
lies not in favour of exercise of jurisdiction under Article 226 of the
Constitution of India. The High Court erred in not bearing in mind this
fundamental principle the argument runs. The appellant relied on the
decision in All India Power Engineer Federation and others v. Sasan
Power Limited and others 30 , for the proposition that the Court must be
mindful of public interest, which consists of interest of the cons umers
ultimately.
81. Per contra , the submission of the first respondent is that the
Court must not be oblivious to certain facts. The rate per unit, in the
case of the first respondent, is Rs.5.109 per unit. In respect of anot her
30 (2017) 1 SCC 487
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
project, where the PPA was entered into with a sister concer n of the
first respondent, the project price was Rs.5.298 per unit . The project
stands commissioned. The tariff was arrived at on the bas is of highly
competitive bids. There were, in fact, 183 bids. It is further contended
that the bid of the first respondent was found to be the lowest in the
competitive bidding. The appellant is, in fact, buying power at higher
tariff from at least 5 generators, who commissioned their projects in the
year 2017-2018. It was further contended that the daily demand of the
appellant is approximately 15000 megawatts. The quantum of the project
of the first respondent is only 50 megawatts, which constitutes 0.33 per
cent of the total demand. Purchasing such a small capacity, in terms of
the rate under the PPA, would make no difference to the consumer
tariff. This is apart from countenancing the appellant reneging on a binding
contract, which involves reaching a reward for arbitrary State action,
besides, destroying an investment of Rs.331 crores. In this regard, reliance
is placed on the Judgment of this Court in Vice Chairman & Managing
Director, City and Industrial Development Corporation of Maharashtra
Ltd. and another v. Shishir Realty Private Limited and others 31 . Public
interest cannot be determined with reference to monetary considerations
alone, it is pointed out.
82. As far as All India Power Engineer Federation (supra) is
concerned, in fact, the Court was dealing with Civil Appeals, which were
filed under the Electricity Act, 2003. The question about public interest
arose in the context of the provision in the contract, which provided for
waiver, which would be a unilateral act under Article 18.3 of the PPA
therein. The Court also discussed the effect of Section 63 of the Indian
Contract Act, 1872. The Court, while dealing with waiver and publ ic
interest, held as follows:
“21. Regard being had to the aforesaid decisions, it is clear
that when waiver is spoken of in the realm of contract, Section 63
of the Contract Act, 1872 governs. But it is important to note that
waiver is an intentional relinquishment of a known right, and that,
therefore, unless there is a clear intention to relinquish a right that
is fully known to a party, a party cannot be said to waive it. But
the matter does not end here. It is also clear that if any element of
public interest is involved and a waiver takes place by one of the
parties to an agreement, such waiver will not be given effect to if
31 (2021) SCC Online SC 1141
69
it is contrary to such public interest. This is clear from a reading
of the following authorities.
xxx xxx xxx
25. It is thus clear that if there is any element of publi c
interest involved, the court steps in to thwart any waiv er which
may be contrary to such public interest.”
83. In the said case, the Court further held that the moment the
electricity tariff gets affected, the consumer interest comes in and public
interest gets affected and further that there is a statutory recognition for
the same in Sections 61 to 63 of the Electricity Act, 2003. The refore,
this Judgment, though in the context of a Statutory Appeal, has laid down
that consumer interest in tariff is intertwined with public interest.
84. On the other hand, in Vice Chairman & Managing Director,
City and Industrial Development Corporation of Maharashtra Ltd. (supra),
this Court, while dealing with a case involving the question of award of
contract, held as follows:
“58. When a contract is being evaluated, the mere possibility of
more money in the public coffers, does not in itself serve public
interest. A blanket claim by the State claiming loss of public money
cannot be used to forgo contractual obligations, especially when it
is not based on any evidence or examination. The larger public
interest of upholding contracts and the fairness of public authorities
is also in play. Courts need to have a broader understanding of
public interest, while reviewing such contracts.”
85. In fact, the principle of public interest has found expression in
cases which involved challenge to the legality of t he award of
contract.[See in this regard Tata Cellular v. Union of India (1994) 6
SCC 651 32 (supra) and Raunaq International Ltd. v. I.V.R. Construction
Ltd. and Others, (1999) 1 SCC 492.
86. In Michigan Rubber (India) Limited v. State of Karnataka
and Others 33 after referring to Tata Cellular and Raunaq International
Limited (supra), the Court inter alia held as follows: -
“35. As observed earlier, the Court would not normally interfere
with the policy decision and in matters challenging the award of
32 (2017) 1 SCC 487
33 (2012) 8 SCC 216
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
contract by the State or public authorities. In view of the above,
the appellant has failed to establish that the same was contrary to
public interest and beyond the pale of discriminati on or
unreasonable.”
87. In Raunaq International Ltd. v. I.V.R. Construction Lt d.
and Others 34 the case involved award of contract for the purpose of
Thermal Power Station. In fact, the Appeals in this court were maintained
against the grant of an interim order against the appellant to whom the
contracts stood awarded. The case also involved relaxation of the criteria
which was based on valid principles it was found. It was further found
that the construction of two Thermal Power Units was being held up
due to the dispute. The Court, inter alia, held as follows: -
“9. However, because the State or a public body or an agency of
the State enters into such a contract, there could be, in a given
case, an element of public law or public interest involved even in
such a commercial transaction.
10. The elements of public interest are: (1) Public money would
be expended for the purposes of the contract. (2) The goods or
services which are being commissioned could be for a public
purpose, such as, construction of roads, public buildings, power
plants or other public utilities. (3) The public would be di rectly
interested in the timely fulfilment of the contract so that the services
become available to the public expeditiously. (4) The public would
also be interested in the quality of the work undertaken or goods
supplied by the tenderer. Poor quality of work or goods can lead
to tremendous public hardship and substantial financial outlay either
in correcting mistakes or in rectifying defects or even at times in
redoing the entire work — thus involving larger outlays of public
money and delaying the availability of services, facilities or goods,
e.g., a delay in commissioning a power project, as in the present
case, could lead to power shortages, retardation of in dustrial
development, hardship to the general public and substantial cost
escalation.
11. When a writ petition is filed in the High Court challenging the
award of a contract by a public authority or the State, the court
must be satisfied that there is some element of public interest
34 (1999) 1 SCC 492
71
involved in entertaining such a petition. If, for example, the dispute
is purely between two tenderers, the court must be very c areful
to see if there is any element of public interest invol ved in the
litigation. A mere difference in the prices offered by the t wo
tenderers may or may not be decisive in deciding whether any
public interest is involved in intervening in such a comme rcial
transaction. Price may not always be the sole criterion for awarding
a contract.”
88. Therefore, on a conspectus of the case law, we find that the
concept of overwhelming public interest has essentially evolved in the
context of cases relating to the award of contract by the State. It becomes
an important consideration in the question as to whether then the State
with whatever free play it has in its joints decides to award a contract, to
hold up the matter or to interfere with the same should be accompanied
by a careful consideration of the harm to public interest. We do not go
on to say that consideration of public interest should not at all enter the
mind of the court when it deals with a case involving repudiatio n of a
claim under a contract or for that matter in the termination of the contract.
However, there is a qualitative difference in the latter categories of cases.
Once the State enters into the contract, rights are created. If the case is
brought to the constitutional court and it is invited to interfere with State
action on the score that its action is palpably arbitrary, if the action is so
found then an appeal to public interest must be viewed depending on the
facts of each case. If the aspect of public interest flows entir ely on the
basis that the rates embodied in the contract which is arbitrarily terminated
has with the passage of time become less appealing to the State or that
because of the free play of market forces or other developments, there
is a fall in the rate of price of the services or goods the n this cannot
become determinative of the question as to whether court should decline
jurisdiction. In this case, it is noteworthy that the rate s were in fact
settled on the basis of international competitive bidding and in which as
many as 182 bidders participated and the rate offered by the first
respondent was undoubtedly the lowest. The fact that power has become
cheaper in the market subsequently by itself should not r esult in non-
suiting of the complaint of the first respondent, if it is found that a case
of clear arbitrariness has been established by the first respondent.
89. In other words, public interest cannot also be conflated with
an evaluation of the monetary gain or loss alone.
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
POINTS NO. 6 - 8 AND 10
90. The time is now ripe to take a closer look at the rel evant
clauses of the PPA. Article 2 deals with the pre commissioning activities.
Article 2.1 deals with satisfaction of the conditions subseque nt by the
respondent. Clause 2.1.1 contemplates that the respondent must complete
all the conditions which are set out at his own cost and risk within 210
days from the effective date. The only two exceptions were ‘force
maejure’ or if any of the conditions subsequent was specifically waived
by the appellant in writing. The consequences of non-fulfilling the condition
subsequent is dealt with in Article 2.2 which related t o force majeure
obstructing the fulfilment of the conditions subsequent. Article 2.2.2 in
fact provided that any increase in the time period for completion of the
conditions subsequent mentioned under Article 2.1 would also lead to an
equal extension in the scheduled commissioning date. Article 2.5 provided
for delay in achieving the conditions subsequent. Article 2.5.1 reads as
follows:
“2.5.1. In case of delay in achieving any of the Co nditions
Subsequent under clause 2.1 (a to h), as may be appli cable,
MPPMCL shall encash CPG (submitted by Seller @ Rs. 30 Lakhs/
MW) as under, subject to Force Majeure: -
a) Delay from 0-3 months - 1 % per week.
b) Delay from 3-6 months - 2% per week for the period
exceeding 3 months, apart from (a) above.
c) Delay from 6-9 months - 3% per week for the period
exceeding 6 months, apart from (a) and (b) above.
d) In case of delay of more than 9 months, MPPMCL shall
terminate PPA and release balance amount of CPG.”
91. Thereafter, PPA deals with the aspect of commiss ioning.
Article 2.6 deals with commissioning and it reads as follows:
“2.6. COMMISSIONING
In case of Solar Project of capacity up to 50 MW, commissioning
of plant shall be within 12 months from the date of financial closure
subject to Force Majeure. In case of Solar Project of capa city
beyond 50 MW and up to 100 MW, commissioning of plant shall
be within 15 months from the date of financial closure subject to
73
Force Majeure For capacity beyond 100 MW, commissioning
period shall be within 18 months from the date of financial closure
subject to Force Majeure..1
In case of failure to achieve this milestone, provision of PP A as
mentioned below shall apply: -
MPPMCL shall en cash the CPG in the following manner for the
capacity not commissioned, subject to Force Majeure:-
a) Delay from 0-3 months - 1% per week.
b) Delay from 3-6 months - 2% per week for the period exceeding
3 months, apart from (a) above..
c) Delay of more than 6 months – 3% per week for the period
exceeding 6 months, apart from (a) and (b) above.
Part Commissioning: In case of Solar PV Projects, P art
commissioning of the Project shall be accepted by MPPMCL
subject to the condition that the minimum capacity for acceptance
of part commissioning shall be 5 MW. Or in multiple of 5 MW
COD means the commissioning date of just units (s) of the power
project where upon the seller starts injecting power f rom full
contracted capacity of the power project to the delivery point; as
approved by competent authority of the Transco/Discom. The
PPA will remain in force for a period of25 month from the COD.”
92. There are other Articles which need not detain us. Article 3
deals with Supply Arrangements under Open Access. Article 3.1.1 reads
as under:
“3.1.1. The power generated through 50 MW Solar Power Project
(PY/Thermal Technology) installed by the Seller Located at Village
bedhsya, Tai: Khandwa, Dist: Khandwa, State: Madhya Pradesh
shall be injected into the Transmission/Distribution syste m of
Transco/Discom on 33kV or above side of 33kV /EHV Substation
situated at Deshgaon at injection point for sale to MPPMCL, subject
to fulfilling the terms and conditions and protection schemes by
the Seller as approved by the concerned
Transco/Discom’s.
3.1.2. The Seller shall ensure to interconnect and operate the solar
power plant in parallel with the grid of Transco/Discom ( in the
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
area of the location of the generating unit) system subject to the
terms and provisions of this agreement. The Seller shall be fully
responsible for obtaining and maintaining any or all licenses and
permissions required by law. The Seller shall abide by any law,
rules, regulations or any notification or order issued there under
by the Central Govt. or State Govt. or Commission or Loca l
Authority or any other Authority prescribed under t he law
connected with the project of the Seller.
The Seller shall be fully responsible for the design, construction,
testing, operation and maintenance of the solar power plant in
accordance with Standard Utility Practices, relevant tec hnical
standards and specifications.
b) For the power plant situated in MP State, the power evacuation
infrastructure laid by the Seller shall be the proper ty of the
concerned licensee (Transco/Discom) in whose territorial a rea
the above lines are located - notwithstanding the fact that the cost
of the said infrastructure has been paid by the Seller and the same
. shall then be maintained by the concerned licensee at its cost. A
separate transfer agreement shall be subsequently signed in t his
regard with the concerned licensee, if required.
3.1.3. The Seller shall obtain all statutory and non-stat utory
permissions as required. The seller supplying power from outside
of MP State shall require to obtain long term open access
permission as per relevant regulations of central a nd state
regulators, as the case may be, from the state or regional l oad
dispatch center and/or the state/central transmission utilities.”
93. Article 4 deals with System Operations. Article 4.2 deals with
system operation and scheduling. We may notice Articles 4.2.1 and 4.2.4.
“4.2.1. The State Load Despatch Center shall be the Nodal
Agency if the project is located in MP, for system operation, power
accounting, scheduling, etc. The foes and charges of SLDC as
approved by the MPERC shall be payable by the Seller to t he
SLDC. In case of the system is located in any other state, t he
Seller has to follow the regulations of the particular SLDCIRLDC
and the fees and charges shall be payable by the seller accordingly.”
“4.2.4. SLDCs/Control Centers of the States/UTs/DVC, in which
the solar power plant is located, shall provide the 15-minute block-
75
wise data of schedule and actual generation from Sol ar Grid
Connected Power Plant as recorded in the Energy Meters to the
concerned RLDC and NLDC on a weekly basis as per th e
requirement of SLDCIRLDC/NLDC. All the data shall b e
submitted in the form prescribed by the NLDC.”
94. Article 4.3 deals with open access. Article 5.1 deals wi th
commercial operations date (COD). COD has been defin ed in the
agreement as meaning the commissioning date of the last unit(s) of the
power project whereupon the seller starts injecting po wer from full
contracted capacity of the power project to the delivery point as approved
by competent authority of the TRANSCO/DISCOM. DISCOM ha s
been defined as a licensee authorised to operate an d maintain a
distribution system for supplying electricity to the consumers in the State
of Madhya Pradesh. Article 5.1 reads as under:
“5.1. COMMERCIAL OPERATIONS DATE
The Commercial Operation Date of the plant shall mea n the
commissioning date of last unit (s) of the power project where
upon the seller starts injecting power from contracted capacity of
the power project to the delivery point as approved by competent
authority of the Transco/discom.
After Each part commissioning and/por CoD of the contracte d
capacity, the commissioning certificate (s) certified by Transco/
Discom shall be attached as Annezure- XII to the Power Purchase
Agreement
However part commissioning of the plant shall be accepted as
laid out in clause 2.6 and the energy supplied from the same shall
be considered for billing and payment of the energy supplied from
such commissioned units.”
95. Article 5.2. deals with Pre-Commercial Operations and it inter
alia provides that the discom shall take all power produced through the
STU/CTU during the testing of the plant without any charges. Thereafter
5.3 deals with Notice of Commercial Operations. It reads as follows:-
“5.3 NOTICE OF COMMERCIAL OPERATIONS:-
The Seller will specify in a written notice to the MPPMCL that:
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
a) The Plant is constructed in accordance with this Agreement
and is ready to deliver Solar Power in accordance with the
terms hereof;
b) All permissions and approvals required for the Plant to sell
Solar Power at the rates and terms specified under this
Agreement have been obtained and
c) All interconnection facilities are available to receive Solar
Power from the Plant.
Such notice shall take effect and the Commercial Operations Date
will be achieved following the Transco/Discom’s declaration that
all of the conditions set forth in this Article have been satisfied or
waived by the STU/CTU/MPPMCL/Transco/Discom i.e.:
a) The Seller has successfully completed the testing of
the Plant in accordance with the manufacturer’s
recommendations and the Seller has obtained and
provided to the STU/CTU/Transco/Discom Certificates
from the Electrical Inspectorate of GoMP or any other
state government authorised agency, and the STU/
Transco/Discom’s officer as may be designated; in case
project is located in MP. In case project is located outside
MP, similar certificates be obtained from the concern
authority of respective state.
b) The Seller has delivered to the Transco/Discom a list
of the Plant’s equipment, showing the make, model,
serial number and certified the installed capacity of the
Plant;
c) The Plant has achived initial synchronization with the
Transco/Discom’s/STU/CTU Grid System and has
demonstrated the reliability of its communications
systems and communications with the STU/CTU/
Transco/Discom;
d) The Seller has operated the Plant without experiencing
any abnormal or unsafe operating conditions on any
interconnected system;
e) The Seller shall also have notified the MPPMCL/
Trancso/Discom/STU/CTU no later than 30 days prior
77
to the Commercial Operations Date that all the
Conditions Subsequent as laid out in clause 1.01 have
been met and MPPMCL shall verify the same and shall
provide the Seller a written endorsement in this behalf
acknowledging the documents, certificates, approvals
etc provided by the Seller in this regard.”
The respondent was duty bound to notify to the appellant that the
plant is constructed as per PPA and it was ready to produce solar power
and that all permissions and approvals to sell power at th e rates and
terms under the agreement had been obtained and all inter connection
facilities were available to receive solar power from the plant. The PPA
further contemplates that the said notice would take effect and the COD
be achieved upon the TRANSCO/DISCOM declaring that all conditions
in this Article were either fulfilled or waived. The PPA f urther deals
with Sale and Purchase of Solar Power in Article 6 commenci ng at
COD date. The seller, that is, the respondent was to sell and the appellant
was to purchase and accept 50MW solar power at the point of delivery.
The respondent undertook not to sell any solar power (all of which is
committed to the appellant) to any other person. Article 7 deals with
Metering and Measuring. Article 8 deals with Billing and Power
Accounting. Article 9 deals with Events of Default and Remedies. Article
9.1 is relevant and it deals as follows:
“9.1. DEFAULTS AND TERMINATION.
In case of default, the non-defaulting party shall issue a default
notice to the defaulting party. If the default is not fully set right
within three months from the date of issue of the default notice,
then in case of default by the Seller, the MPPMC.L by gi ving
seven days termination notice in writing, may terminat e the
agreement. In case of default by MPPMCL, the Seller may in the
same way terminate the agreement.”
96. Article 9.4 deals with various events which are described as
seller event of default. The relevant provision reads, inter alia:
“9.4. SELLER EVENT OF DEFAULT
The occurrence and continuation of any of the following events,
unless any such event occurs as a result ofa Force Majeure Event,
shall constitute Seller Event of Default:
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
a) The failure to commence supply of power to MPPMCL up to
the Contracted, Capacity, relevant to the Scheduled Commissioning
Date, by the end of 24 months; or”
97. Article 9.5 provides for appellant’s events of default. Article
9.7 falling under 9.6 which generally deals with ‘Remedy’. It reads as
follows:
“9.7. MPPMCL commits to buy power, as indicated in Article
Error! Reference source not found. of PPA, from Seller at Rs.
5.051 per kWh for a period of 25 years from COD. In case
MPPMCL refuses or is unable to buy the said power, fully or
partially, or there is an event of default as per Clause 9 .5 of PPA
leading to termination of the PPA, the seller would be free to sell
the said power to a Third Party at any rate which will be decided
between the Seller and the said Third Party and such sale would
be governed by the following principles:”
(Emphasis supplied)
The principles are set out providing for two cases.
98. Article 11.6.3 deals with Change in Law. Article 13 deals
with Jurisdiction and Dispute Resolution. Article 13.2.1 reads as follows:
“13.2.1. Either Party is entitled to raise any claim, dispute or
difference of whatever nature arising under, out of or in connection
with this Agreement (“Dispute”) by giving a written notice (Dispute
Notice) to the other Party, which shall contain:
• a description of the Dispute;
• the grounds for such Dispute; and
• all written material in support of its claim
13.2.2. The other Party shall, within thirty (30) days of issue of
Dispute Notice issued under 13.2.1, furnish:
• counter-claim and defences, if any, regarding the Dispute; and
• all written material m support of its defences and counter-claim.
13.2.3. Within thirty (30) days of issue of Dispute Notice by any
Party pursuant to Article 13 .2.1 if the other Party does - not
furnish any counter claim or defence under Article 13.2.2 or thirty
(30) days from the date of furnishing counter claims or defe nce
79
by the other Party, both the Parties to the Dispute shall meet to
settle such Dispute amicably. If the Parties fail to res olve the
Dispute amicably within thirty (30) days from the later of t he
dates mentioned in this Article, the Dispute shall be referred for
dispute resolution in accordance with Article 13.3.”
99. Article 12.2 reads as follows:
“12.2 GRID CODE DISCIPLINE
The concerned Transco/Discom and the Seller shall
observe the State/Indian Electricity Grid Code or its amendment
if any, and operate their systems to the best of their c apacity
and resources.”
100. Article 13.3.1 reads as follows:
“13.3.1. Where any Dispute arising from a claim made by any
Party for any matter related to Tariff or claims made by any
Party which partly or wholly relate to any change in the Tariff
or determination of any of such claims could result in change
in the Tariff, shall be submitted to adjudication by the MPERC.
Appeal against the decisions of MPERC shall be made only as
per the provisions of the Electricity Act, 2003, as amend ed
from time to time.”
101. Article 15.1.4. deals with Compliance with Law an d in
substance it provides that the provisions of the Electricity Act, 2003 will
prevail in case of repugnancy or deviation from the terms of the
agreement from the Act.
102. In the impugned judgment the High Court has proceeded to
hold inter alia that the respondent has invested Rs . 350 crores in
establishing the unit and after replacing the stolen parts, the unit is ready
for commissioning on any date. The High court has further proceede d
on the basis that the project involved two milestones and the High court
has set aside the earlier order which dealt with delay in a chieving the
first milestone. Thereafter, the finding is that the project was certified to
be completed much prior to 24 months which period ended on 19.9.2017
and the notice of commissioning was given on 4.7.2017. The CEIG
approval was also granted on 9.8.2017. It is further found that another
inspection was done on 19.04.2018 after nine months of the notice of
commissioning and the CEIG approval. It is despite the sam e that the
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
impugned order has been passed. Still further the High court proceeds
to find that it is undisputedly established that both the milestones of the
project were completed whereas only some of the invertors were stolen
for which an FIR was also lodged. It is again found that it i s not in
dispute that the aforesaid parts have been replaced by t he respondent.
Support was drawn from the case of Renew Energy and the courts
discretion to interfere in the matter was reiterated. T he decision was
found to be arbitrary. The court directed the respondent to file necessary
application for statutory sanction for operation of the unit and the appellant
was to decide on the application. To complete the narrative a review
petition, was filed by the appellant. The appellant sought to project the
aspect of fraud. The fraud consisted of the act of the respondent relying
on unique/distinctive serial numbers of the invertors in regard to a number
of invertors which were found to be common/duplicate. In other words,
the case of the appellant was that the project for 50 MV w as divided
into 10 blocks of 5 megawatt. Each block had 116/117 invertors. A fraud
was committed on the CEIG. In other words, it was the appellants case
that the respondent had not complied with the PPA in regard to t he
installing of the required number of invertors. The first respondent took
the stand that the all the serial number of the invertors were quite legible
though the contrary was contended. The CEIG reported the physi cal
readiness of the project for commissioning. The respondent also dr ew
upon the inspection report of the appellant itself. The High Court bearing
in mind the limited jurisdiction dismissed the review.
103. In the impugned Termination Notice dated 07.07.2018, after
referring to the delay of 54 days in fulfilling condition subsequent, it is
mentioned that the commercial operation date, as per Arti cle 2.6, was
14.04.2017. It was indicated that there was no indication regardi ng
commissioning against the column ‘readiness of plant’ as on 11.08.2017.
The last date for commencement of supply was shown as 18.09.2017.
The expiry date of three months period for commencement of supply
from the last due date was 18.12.2017. It is further provided that t he
expiry date of seven days of PPA Termination Notice p eriod was
25.12.2017. The status of the project as on 19.04.2018 was indicated as
‘not ready for commissioning’. Thereafter, it is pointed out that there is
no justification for delay in achieving condition subsequent. Still further,
reference is made to the Order passed by the High Court in t he earlier
Writ Petition. Physical verification was carried out o n 19.04.2018,
whereupon, it was found that installation work of plant and equipment
81
was incomplete in Blocks 9 and 10. It was further pointed out tha t the
copy of the Inspection Report was enclosed, where ins tallation of
invertors, installation of solar EV panels, cabelling and earthing work,
was yet to be completed. It was further pointed out that even after more
than six months, after deadline of commissioning of project, the plant is
not ready for commissioning. Thus, there was not only failure to achieve
condition subsequent but also failure to commission the project within
time. In comparison with the case of Renew Clean Energy, it is pointed
out that apart from failure to comply with condition subsequent, even the
outer timeline has not been observed, whereas, in the cas e of Renew
Clean Energy, they were ready to commission by the scheduled
commissioning date. The timeline under Article 9.1 was not conformed
to. After referring to the Order of the High Court, it was found that, with
reference to Article 2.5.1(d) and Article 9.1 of the PPA, the PPA was
terminated.
104. Let us demystify the case for termination. Apart from non-
fulfilment of the condition subsequent, apparently, in tune with the liberty
granted by the High Court, the appellant has set out a case that the last
date of commencement of supply was 18.09.2017, and even a s on
19.04.2018, the respondent was not ready for commissioning of the
project. With reference to Articles 5.1, 5.2 and 5.3 of the PPA, which
consisted of the commercial operation date, pre-commercial operation
and notice of commercial operation, it is stated that the respondent has
not intimated regarding the schedule of commissioning, till the date of
the Termination Notice. A distinction is sought to be drawn between
Renew Clean Energy and the respondent, in that the case of the first
respondent, even the first respondent was not ready to commission the
project within the stipulated time.
105. The case that the first respondent has projected in the Wr it
Petition, on the other hand, is, inter alia, as follows:
On 04.07.2017, while issuing letter to respondent no.4, it
issued notice for commissioning by 31.07.2017, in terms of Article
5.1(c) of the PPA. Site inspection by the appellant was solicited
through its EPC. The respondent obtained approval from the CEIG
for commissioning on 09.08.2017. The CEIG certified that all
infrastructure and installation pertaining to the project were ready
and the respondent may proceed with the commissioning activities.
CEIG approval is requirement under Article 5.3(a). However, the
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
appellant proceeded to terminate the PPA by Order d ated
07.07.2018. Thus, it is stated that the appellant, for reasons best
known to it, chose to ignore the first respondent’s request for
proceeding with the commissioning of the project. The respondent
also obtained in principle connectivity for the project from the
appellant. It is the specific case of the respondent that p rior to
11.08.2017, first respondent had received intimation from its EPC
Contractor that the project was ready for commissioning barring
minor works pending completion such as construction of shed/
cubical for the Guard which would have no bearing on the project
commissioning. The respondent pointed out that the appellant was
obliged to issue default notice under Article 9.1 of the PPA. The
respondent was entitled for a period of three months. No such
notice was issued. As far as the Report of the Inquiry Committee
dated 19.04.2018, relied on by the appellant, it is pointed out that
the challenge to the earlier termination notice was pending and
the respondent was constrained to demobilise its staff/s ecurity
guards. Thefts took place. It is pointed out that these thefts took
place after the certification by the CEIG. In other wor ds, the
respondent would blame the appellant for not conducting an inquiry
immediately after the certification by the CEIG. It is also the case
of the first respondent that, through its EPC Contractor, it had
procured, inter alia , 1163 string invertors. Some of the string
invertors were stolen, as stated earlier. That the ca se of the
respondent is not that the project had been commissioned but that
the appellant prevented it from commissioning the project before
the last date. It is also seen stated that the project was complete
in all respects from the side of the respondent but on account of
theft of a very small number of equipment, highlighted by t he
appellant in its Inspection Report, the first respondent had, in the
meanwhile ensured to get these miscellaneous equipments a nd
parts reinstalled and the project was complete in all respects as
on that date. As far as the theft is concerned, the first respondent
had lodged two FIRs through its EPC Contractor well before the
inspection carried out on 19.04.2018.
THE ASPECT OF DISPUTED QUESTIONS OF FACTS
106. What are the disputed questions of facts? The most important
disputed question of fact is as to whether the first respo ndent was, in
83
fact, ready to commission the project by the end of the peremptory date,
which was fixed as a period of twenty-four months from the date of the
agreement. On the one hand, the appellant would contend that fir st
respondent was not ready to commission the project. This is for t he
reason that in the 9 th and the 10 th Blocks, certain string invertors were
found missing. On the other hand, the case of the respondent is based on
the Report of the CEIG, which would show that the respondent was
ready to commission the project. As far as the CEIG Report is concerned,
the case of the appellant appears to be that the respondent had played a
fraud in obtaining the CEIG Report. This was unsuccessfully canvassed
before the High Court in the Review Petition. In other words, the case
sought to be set up by the appellant is that as many as 272 string invertors
were bearing duplicate numbers and, therefore, it was being held out by
the first respondent that it had performed its contractual obligation, when
it was not the case. As far as the delay of 53 days in fulfilling the conditions
subsequent is concerned, there is no dispute that there was such a delay.
Though, an attempt was made by the first respondent to contend that in
view of the amendment substituting one of the conditions subsequen t,
viz ., the condition relating to land and, therefore, there would be further
extension of time. We do not think that we can allow the first respondent
to set up such a plea. However, we have already concluded that the
issue as to the right or power of the appellant to terminate the PPA on
account of the delay of 53 days, may not be open to the appellant, in
view of the Judgment of the High Court.
107. The learned Senior Counsel for the first respondent, Dr. A.M.
Singhvi, would, in fact, contend that this Court may proceed on the basis
that actually there is a disputed question of fact. This is on the reasoning
that even if this Court proceeds on the basis of the Inspe ction Report
dated 19.04.2018, a miniscule percentage of Rs. 350 crores would be
the subject matter of the lacunae that was pointed out by the Inspecting
Team in its Report dated 19.04.2018. It is pointed out that the f irst
respondent should not be visited with the highly arbitrary decisi on to
terminate the PPA when nearly Rs. 350 crores have been sunk into the
project. The project itself is an environment friendly project. An unusually
large number of competitors had bid in the bidding process and the first
respondent had emerged as a lowest bidder, which, at that time was
hailed.
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
THE CASE UNDER ARTICLE 9.1 READ WITH
ARTICLE 9.4(a)
108. One of the grounds taken by the first respondent against the
termination notices is that it is issued without complying with Article 9.1
of the PPA. We have already adverted to the said Article. We have also
referred to Article 9.4.(a). Let us divine what is contemplated under the
PPA. The PPA contemplates Article 9 with its sub-divisions to provide
for events of default and remedies. Under Article 9, the sub -Articles
provide for seller’s event of default and the appellant’s Event of default.
Reading Article 9.1 with Article 9.4 and, more particularly, Article 9.4.(a),
which alone is relevant, we understand the following to be wha t is
contemplated by the parties. Article 9.1 begins with the words ‘in case
of default’. The default in the case of seller’s event of default would be
the default, which is the subject matter of the termination. Here, we can
safely conclude that the seller’s event of default, which is apposite, is
the failure to commence the supply of power to the appell ant at the
contracted capacity, relevant to the scheduled commissioning date by
the end of twenty-four months. The words ‘scheduled commissioning
date’, have been defined in the PPA itself, to mean, for solar project of
capacity 50MW as per the quantum indicated in LOI, the commissioning
period allowed shall be nineteen months from the date of signing of the
PPA. The period of twenty-four months must be reckoned from t he
date of the PPA and, so understood, since the date of the PPA is
18.09.2015, twenty-four months therefrom would expire on 18.09.2017.
We, therefore, proceed on the basis that such an event, constituting default
on the part of the first respondent, had taken place. Continuing with the
analysis of Article 9.1, what was expected of the appellant was, as the
non-defaulting party, to issue a default notice to the defaulting party, viz.,
the seller, which in this case is the first respondent. Article 9.1 further
clearly contemplates that if the default is not fully set right within three
months from the date of issue of the default notice, then, in the case of
default by the seller, the appellant was to serve a seven days’ notice of
termination. The notice was, undoubtedly, to be in writing. It is by the
second notice, which is to be of the duration of seven days that the
appellant could validly terminate the agreement. Thus, PPA cle arly
indicates the issuance of a default notice when seller commits an act of
default. Without issuing the first default notice, giving three months’ time
from the date of issue of the notice, the second notice, which would be
a notice of termination, cannot be issued.
85
109. Now, let us find whether the appellant has followed this
procedure. In the impugned termination notice dated 07.07.2018, what
is indicated in a Table in paragraph-9 is that there was a delay of 54 days
in the matter of fulfilment of conditions subsequent and the scheduled
commercial operation date, as per Article 2.6 was 14.04.2017. 11.08.2017
is noted as the date of notice of termination. 18.09.2017, being the end
of twenty-four months from the date of signing of the PPA is shown as
the last date of commencement of supply of the contracted capacity and
Article 9.4 is referred to. 18.12.2017 is shown as the expiry date of
three months, apparently, from 18.09.2017, for commencement of supply
from the last due date. Thereafter, 25.12.2017 is shown as the expiry
date of seven days of the PPA termination notice period. In paragraphs-
21, 22 and 23 of the impugned notices, the appellant takes the following
stand:
“21. As per table-I, time line for commissioning of project has
been indicated. You were required to adhere to st1p ulated
provisions of the PPA. Whereas this has not been achieved by
you, within the time line even considering provisions of Article 9.1
of the PPA i.e., 24 months (supply to power to. contracted capacity
from date of PPA) + 3 months (default notice period) + 7 day s
(termination notice period), from the signing of the PPA have
already being exhausted.
22. Whereas, in light of showcause notice issued vide this office
letter no. 108 dated 22.02.2017 and liberty granted “ by Hon’ble
Court to MPPMCL, in its order dated 20.06.2018 for issuing fresh
order in terms of PPA dated 18.09.2015 to you, in accordance
with law, it is evident that you have failed to fulfil your contractual
obligation as per PPA executed with you on 18.09.2015. Thus,
the PPA qualifies for termination.
23. Therefore, in line and in compliance to the Hon’ble High Court
judgment dated 20.06.2018 and pursuant to the provision under
Article-2.5.1 (d) along with the consideration of the timel ine
stipulated in Article 9 .1 of the PPA and showcause notice dated
22.02.2017, the PPA signed on 18 Sept. 2015, between Mis Sky
Power Southeast Solar India Pvt. Ltd. New -Delhi, (SPV of
Parent Company Sky power Southeast Asia Holding 2 Ltd.) and
MPPMCL, for supply of Power from the proposed, 50MW. Solar
PY plant located at Village-Bedhaya District - Khan dwa and
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
subsequently location changed to Village Chhibel, Teb-Khalliiwa,
Distt- Khandwa at a rate of Rs. 5.091 per unit, is hereby
terminated.”
110. Thus, we find the twenty-four months period from the date
of the PPA, plus three months default notice period, plus sev en days
termination notice period, had been already exhausted. In paragraph-22,
support is sought to be drawn from the show-cause n otice dated
‘22.02.2017’ and the liberty granted by the High Court in the first Writ
Petition, for issuing a fresh Order. The PPA, it was found by the appellant,
qualified for termination. In paragraph-23, it is explicitly stated that based
on Article 2.1.1(d) along with the timeline stipulated in Article 9.1 and
the show-cause notice dated 22.02.2017, the PPA was terminated.
111. Therefore, the show-cause notice dated 22.02.2017 is what
the appellant lays store by to conclude that it was acting in compliance
with the requirement of issuance of the default notice under Article 9.1.
It, therefore, becomes necessary to advert to the notice dated 22.02.2017.
We may extract the following:
“MP POWER MANAGEMENT COMPANY LIMITED
CIN: U4010MP2006SGC018637
(A Govt. of M.P. UNDERTAKING)
Regd. Office: Shakti Bhawan, Rampur, Jabalpur, Madhya Pradesh,
india-482008, Tel: 0761-2661111;-2660500, Fax: 0761- 261696,
website:-www.mppmcl.com, email: md@mppmcl.com,
No. 05-01/Solar Bidding-III/PP A/108
‘Jabalpur Date 22.02.2017
To,
M/s Sky Power Southeast Solar Pvt. Ltd.
16A/20 W.E.A. Main Ajmal Khan Road,
Karol Bagh,
New Delhi-110005.
Subject: submission of documents for fulfilment of condition
subsequent in respect of your 50MW Solar Power project proposed
at Village Chhirbel, Tallika Dist Khandwa under Phase-III solar
competitive bidding.
87
Ref: 1. Power purchase Agreement executed on 18.09.2015.
2. Your letter No. SKP/MP/SOLAR/MPPMCL/2015-116/06,
dated 12.01.2017
Dear Sir,
With reference to your latter cited above, this is to intimate that
on scrutiny of the documents submitted by you for fulfilment of
condition subsequent after 210 days from signing of PPA. In
respect of your 50 MW solar power project proposed at vil lage
Chhirbel, Taluka & dist Khandwa, status of the documents found
as under:
D.G.M. (Commercial-3)
R.0., MPPMCL, Bhopal
Chief General Manager (Commercial): Block No. 11, Shakti
Bhawan, Rampur, Jabalpur (MP) 482008
Tel: 0761-2661245, 2702404, Fax: 0761-2661245,
email: makarand.chincholkar@mppmcl.com
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
It needs to be mentioned here that as per provisions of amended
clause 2.1 (f) of the PPA pertaining to acquisition of land for the
project, Seller shall be required to furnish the fo llowing ~
documentary evidence:-
• Ownership or lease hold right (for at least 30 years) or right to
use permission (for revenue land in Madhya Pradesh) in the name
of seller and possession of 100% of the area of the land required
for the allotted project.
• Requisite documents from the concerned and compe tent
revenue registered authority for the acquisition ownership vesting
of the land in the name of the seller and in case of priva te land
clear title for ownership and/ or registered lease deed for land
taken on lease.
As can be seen from the above table you have submitted cle ar
title for ownership for only 64.94 hectare land. whereas for 34.12
hectare land you have submitted unregistered lease deed for only
12 months, which cannot be considered for fulfilment of condition
subsequent as per provisions of the PPA as mentioned above.
Further, as per provision of clause 2.5.l (dO of the PPA, referred
PPA is liable for termination. Therefore, you are requested to
submit your explanation/ justifications, if any, within 10 days from
the issue of this letter, for further - necessary action in the matter.
Chief General Manager Commercial
MPPMCL, Jabalpur”
112. A perusal of this notice, would reveal the following:
The subject matter of the said notice appears to be the fulfilment
of condition subsequent. It is clearly mentioned that as pe r
Article 2.5.1, the PPA was liable for termination. The fi rst
respondent was asked for the explanation within ten days from
the date of the letter for further necessary action in the matter.
We are of the view that the said notice cannot qualify as one
which was issued as a default notice under Article 9.1. We
have already found that Article 9.1, dealing with default, which
in this case, is the default by the seller, and, furthermore, the
default being non-observance of the time limit of twenty-four
89
months from the date of agreement dated 18.09.2015, the notice
dated 22.02.2017, could not have been issued, even before the
expiry of the period of twenty-four months from 18.09.2015.
In other words, the seller’s event of default under Article 9.4(a)
could have become the subject matter of a notice under Article
9.1 only if there was failure on the part of the first respondent
to supply power, as provided in Article 9.4(a), within twenty-
four months. That point of time, viz., the expiry of twenty-four
months from 18.09.2015, would arrive, at the earliest, only on
18.09.2017. Therefore, it is only after 18.09.2017 that the first
notice or, what is described as the default notice, could have
been issued by the respondent under Article 9.1. Apparently,
what has happened is the appellant has combined the default
alleged with reference to Article 2.5.1(d), to which, undoubtedly,
notice dated 22.02.2017, could be said to be related and has
projected the said show-cause notice as the default notice within
the meaning of Article 9.1 read with Article 9.4. Article 9.1
contemplates a default, the issuance of default notice and, most
importantly, giving a period of three months for the seller (first
respondent) to set right things. It is if the seller does not remedy
the matter within three months, that the second notice, which
is essentially an Order of termination of the PPA, can be issued.
A perusal of the notice dated 22.02.2017 does not make any
reference to the seller’s event of default contemplated in Article
9.4.(a). The reasons are not far to seek. For the reasons, which
we have indicated hereinbefore, the notice could not have been
issued based on there being a seller’s default within the meaning
of Article 9.4.(a) on 22.02.2017. We reiterate that as on
22.02.2017, the seller’s event of default under Article 9.4.(a),
could not exist in law or in facts. Still further, we notice from
the tenor of the notice dated 22.02.2017 that the first respondent
was, in fact, asked to give its justification within ten days from
the date of issue of the notice for necessary action in the matter.
This is totally incompatible with the notice contemplated as a
default notice within the meaning of Article 9.1. Article 9.1
contemplates the existence of a default by the seller and the
giving of a period of three months to the seller to remove the
defect. We are unable to understand how notice date d
22.02.2017 could be understood as affording any suc h
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
opportunity as is contemplated under Article 9.1. Therefore,
we have no hesitation in holding that the appellant cannot seek
shelter under notice dated 22.02.2017 to justify the notice of
termination dated 07.07.2018, if reliance is to be placed on
Article 9.1 read with Article 9.4.(a). We have already found
that the appellant cannot be permitted to reopen the issue relating
to the non-fulfilment of the conditions subsequent, as the issue
has attained finality by virtue of the Judgment of the High Court
dated 20.06.2018.
113. Appellant has attempted to justify the notice dated 22.02.2017
as the show-cause notice within the meaning of Article 9.1 based on the
Judgment of the High Court in the first round of litigation. We are of the
view that appellant would not be justified in drawing support from the
said Judgment to contend that the issuance of notice dated 22.02.2017,
would suffice and it absolves the appellant from complying with Article
9.1. From a perusal of the said Judgment in Writ Petition No. 12880 of
2017, we find that the High Court found that an attempt was made by
the appellant to justify the earlier termination dated 11.08.2017 on the
ground that respondent had not commissioned the power project within
the time fixed in the agreement. The High Court was not impressed as it
found that the lack of commissioning of the power project was not the
reason for terminating the contract and the appellant could not supplement
the reason in view of Judgment of this Court in Mohinder Singh Gill
and another v. Chief Election Commissioner, New Delhi and ot hers 35 .
It is thereafter, after setting aside the Order dated 11.08.2017, that liberty
was granted to the appellants to pass fresh Order in terms of the PPA,
in accordance with law. High Court, therefore, only pe rmitted the
appellants to invoke the PPA with respect to the lack of commissioning,
and moreover, in accordance with law. It becomes clear as day light that
since by the date of the Judgment, i.e., 20.06.2018, the period of twenty-
four months from the date of the agreement, had expired, and if, in
terms of the liberty granted by the High Court, the appe llant was to
lawfully terminate the contract, it could not have acted in breach of the
mandate of the PPA, which, in fact, the High Court had specifica lly
directed appellant to comply with. In other words, though nearly ni ne
months had gone by from 18.09.2017, when the High Court pronounced
Judgment on 20.06.2018, if the appellant wanted to te rminate the
agreement, at least under the contract, the appellant was obliged to issue
35 (1978) 1 SCC 405
91
the default notice. As we have noticed, the appella nt was perhaps
persuaded to issue the impugned termination notice on the basis of the
earlier notice dated 22.02.2017 as it felt that it was entitl ed to ask the
Court to revisit the issue relating to the non-fulfilment of the condition
subsequent as well. The appellant has, in fact, proceeded in the notice of
termination that the three months period, contemplated in Article 9.1,
came to an end automatically, on 18.12.2017 and things had not changed
on the ground, entitling it to issue the notice dated 07.07.2018, after the
further expiry of seven days on 25.12.2017. The appellant, in this regard,
appears to have laboured under the apprehension that the mere expiry
of the period of three months, after the occurring of the event of seller
default, within the meaning of Article 9.4.(a) and the further expiry of
another seven days, entitled it to issue the notice of termination. What,
on the other hand, Article 9.1 read with Article 9.4.(a) contempl ated
was not the mere running of time for a period of three months, after the
occurrence of the seller’s event of default but an opportunity to the
seller by the giving of a notice of default and waiting for three months. It
is only after the seller was put on notice of the default, which it had
committed and an opportunity was granted to remove fully the default
and it persevered in breach, that a valid Order of termination could be
passed. On this reasoning, there can be no dispute that the appellant has
clearly failed to act in terms of the clear mandate of Article 9.1 read
with Article 9.4.(a).
114. There is another vital aspect to be borne in m ind. The
impugned notice dated 11.08.2017, brought about the termination of the
contract. This is while notice dated 04.07.2017 was issued by the first
respondent, as noticed. Therein, the appellant was specifically asked to
inspect the premises. The CEIG also issued the certificate on 09.08.2017.
Now the really significant fact is that after the appellant terminated the
contract on 11.08.2017, it is wholly inconceivable and arbitrary to predicate
that the first respondent should have commenced the project and complied
with Article 9.4(a) by 18.09.2017. Even more unfair it would be to find
that the first respondent had three months period from 18.09.2017 t o
cure the defect which period came to an end on 18.12.2017. Yet, t his
very premise is reflected in the impugned notice dated 07.07.2018. There
is no case at all for the appellant that immediately on the expiry of 24
months contemplated in Article 9.4(a), a notice was given under Article
9.1. This could not be, also for the reason that the appellant had well
before 18.09.2017, on 11.08.2017, terminated the contra ct. This is
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
indisputable. Equally significantly, termination of the contrac t dated
11.08.2017 clearly was illegal though it was found later and set aside by
judgment dated 20.06.2018. Thus, we cannot also brush aside the
complaint of the first respondent that this is a case where it stood prevented
from commencing supply within the meaning of Article 9.4(a). The fact
of termination by order dated 11.08.2017 and its invalidation by the High
court on 20.06.2018 are again not matters of dispute.
115. There is another aspect to the matter. The termination of a
contract, undoubtedly, results in the intrusion into and depriv ation of
valuable rights, which are vouchsafed to the awardee of the contract. It
could be argued that dehors a contractual provision, unless it be that the
contract peremptorily provides for the termination of the contract
expressly without service of the notice on the occurrence of c ertain
stipulated events, principles of natural justice may not be out of place
and under the Theory of Fair State Action, in consonance with Article
14, an opportunity to the awardee as to why the contract should not be
terminated, may be just. In this regard, we may recapit ulate what this
Court in State of U.P. v. Sudhir Kumar Singh and Others 36 has, inter
alia , held:
“23. It may be added that every case in which a citizen/p erson
knocks at the doors of the writ court for breach of his o r its
fundamental rights is a matter which contains a “publi c law
element”, as opposed to a case which is concerned only with
breach of contract and damages flowing therefrom. Whenever a
plea of breach of natural justice is made against the St ate, the
said plea, if found sustainable, sounds in constitutional law as
arbitrary State action, which attracts the provisions of Article 14
of the Constitution of India - see Nawabkhan Abbaskhan v. State
of Gujarat (1974) 2 SCC 121 at paragraph 7. The present case
is, therefore, a case which involves a “public law element” in that
the petitioner (Respondent No. 1 before us) who knocked at the
doors of the writ court alleged breach of the audi alteram
partem rule, as the entire proceedings leading to cancellation of
the tender, together with the cancellation itself, were done on an ex
parte appraisal of the facts behind his back.”
No doubt, it related to a case of cancellation of the tende r after
the tenderer had worked thereunder for over a year and based on two
36 (2020) SCConline SC 847
93
ex parte enquiries. We may bear in mind that Article 9.1 captures not
really the principles of natural justice as such but an opportunity to set
right a default by the seller.
116. Having found that the impugned termination Order dated
07.07.2018 ill squares with the requirement of Article 9.1, the question
may arise, whether this is a matter which should be t he basis for
interference in powers of judicial review under Article 226. This is not
the basis on which the impugned Judgment is based. Could it be said that
this is a matter, which should have formed the subject matter of a
proceeding in a civil court. In this regard, we may notice the following
aspects:
The object behind giving the default notice under Article 9.1 is to
provide an opportunity to the seller under the PPA to comply with the
PPA and remove the default within the period of three months. If it is a
case where it is demonstrated that removal of the de fault was an
impossibility, then, it would, indeed, be a futile exercise and perhaps, at
least, in a writ proceeding based on infraction of Article 14 or that the
action is arbitrary, the Court may have refused to exercise the
extraordinary jurisdiction and relegate the party to other forum to seek
whatever relief it may be entitled to. If on the other hand, complying
with Article 9.1 was, indeed, meaningful and the default (Article 9.4.(a)
could have been removed as contemplated under Article 9.1, then,
undoubtedly, it may constitute arbitrariness to deprive the first respondent
of the benefit of a default notice.
We cannot be totally unmindful of the fact that such a Clause like
Article 9.1 was inserted with the understanding, that, in such large
complex projects, involving large sums of money being invested, and
furthermore, the successful completion of the project being intended to
augment the production of energy, in this case solar energy, there was
an element of public interest also involved in not allowing the curtains to
be rung down by an abrupt termination without affording an opportunity
to the seller to remove the default. Therefore, we would also examine
whether there is a case where, it could be said that the case of the first
respondent is totally bereft of bonafides or merit.
117. In this case, on 04.07.2017, the first respondent addressed
what it purports to be the notice of commercial operatio ns within the
meaning of Article 5.3. It reads as follows:
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
“Ref No. SKP-2/MP/SOLAR/COMM/2017-18/026
Date: 04-07-2017
To
The Chief Engineer (Planning & Design)
M P Power Transmission Company Limited,
Shakti Bhawan, Rampur,
Jabalpur – 482008, Madhya Pradesh.
Subject: Notice to Commission on the 50 MW Solar Power Project
of SkyPower Southeast Solar India Private Limited located at
Village Chirbel, District Khandwa (“Project”), and Evacuation of
Power from the Project to the 400 KV Chhagaon Sostation.
Reference: Power Purchase Agreement dated September 18, 2015
between Southeast Solar India Private Limited and MP Powe r
Management Company Limited (“PPA”).
Dear Sir,
As per above cited subject matter and reference, we hereby
intimate you of our intention to commission the project by 31 st
July, 2017 (“Proposed Commissioning Date”). By the Proposed
Commissioning Date, we are likely to procure and obtain a ll
permissions and approvals required for the Plant and fulfil and
obligations specified in Article 5.3 read with Annexure XII of the
PPA.
In relating to the commissioning of the Project by the Proposed
Commissioning Date, we would like to apprise you of the progress
made by use in relation to completion of some of the critical path
items for the Project-
• Transmission Line – 95% work has been completed as on
28 th June, 2017 for the 132KV DCDS (double circuit double
string) transmission line from location of the Project to the
400KV substation Chhegaon. Balance 5% is expected to
be completed by 15 th July, 2017 in all respect.
• Bay construction- 90% work on the 132 KV bay is
completed (post receipt of connectivity approval from MP
95
Power Transmission Company Limited (“MPPTCL”) for
the Project along with installation of specified equipment
as required by MPPTCL. Balance 10% of the work,
including testing, meter and CRP panel, is expected to be
completed by 20 th July, 2017.
• Connecting Agreement-Connection agreements have
already been signed on 18 th May, 2017 between Madhya
Pradesh Power Transmission Company Limited, Jabalpur
and M/s SkyPower Solar India Private Limited.
• SLDC connectivity- Connectivity from plant to the SLDC-
Indore is already established through dedicated 2nox2mbps
point to point lease lines from BSNL (as per approved
scheme of SLDC on 23 rd March, 2017 through letter no.
SE./LD. E&T/880, data can be transferred immediately on
charging of plant). Specified equipment as per approved
scheme of SLDC has been installed at SLDC-Indore and
at the Project. Even, IP scheme for both the routers has
been allocated by the SLDC, Jabalpur (through letter no.
SE/LD.E&T/06, dated 3 rd April, 2017).
• CEIG Certification-We have initiated the process to obtain
the CEIG certification, and the CEIG certification is expected
by 20 th July, 2017. The CEIG certificate shall be produced
to MPPTCL as an annexure to obtain the commissioning
certificate, as required under the PPA.
Considering above facts on project progress we hereby reque st
your kind needful and depute necessary officials and personnels
to our site to undertake necessary inspection and testing and help
us in the target commissioning dated of 31 st July, 2017.
In the event, you require any further information from us, we will
be happy to provide the same upon your request.”
(Emphasis supplied)
118. No doubt, Article 5.3 contemplates a notice whereunder the
seller specifies that the plant was constructed as per the agreement and
it was ready to deliver the solar power in accordance wit h its terms.
Secondly, it must be indicated that all permissions and approvals required
for the plant to sell solar power at the rates and terms had been obtained.
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
Still further, all interconnection facilities were available to receive solar
power. Notice is to take effect, however, only when the TRA NSCO/
DISCOM declares that all the conditions in Article 5.3 stood satisfied
(or waived by it), inter alia , i.e., that the seller had successfully completed
the testing of the plant in accordance with the man ufacturer’s
recommendations and the seller had obtained and provided from the
Electrical Inspectorate of the Government of Madhya Pradesh or other
authorised agency, a certificate and the seller had delivered a list of the
equipments with details. The further condition is that the plant had achieved
initial synchronisation with the appellant and had demonstrated reliability
of its communication system, inter alia , that the seller had operated the
plant without experiencing any abnormal or any unsafe operating condition
on any interconnected system. The seller was also to notify the appellant
within no later than 30 days prior to the commercial operations date, that
the conditions, as laid down in Article 1.01 have been met.
119. However, the first respondent in the letter dated 04.07.2017
has intimated about the intention to commission the project by 31.07.2017,
which is on the 27 th day after the notice. As far as transmission line was
concerned, 95 per cent of the work was claimed to have been completed
as on the 28.06.2017. Balance 5 per cent, it is stated, would be completed
by the 15.07.2017 in all respects. In regard to bay construction, 90 per
cent of work was stated to be completed along with installation of certified
equipment. Here also, it is stated that the balance 10 per cent of the
work including, testing, meter and CRP panel would be completed by
20.07.2017. Connection agreement is stated to have been signed on
18.05.2017. As far as SLDC connectivity is concerned, it is stated that
connectivity to SLDC indoor was already established through dedicated
2nox2mbps point to point lease lines from BSNL. As far as the
certification by the CEIG, it is stated that the process to obtain the CEIG
certification would be initiated and it is expected by 20.07.2017. Inspection
was prayed for so as to achieve the target commissioning da te by
31.07.2017. No doubt, the appellant has proceeded on the basis that the
notice dated 04.07.2017 cannot be treated under Article 5.3 of the PPA.
As far as the CEIG Report is concerned, it appears to be dated
09.08.2017. It could no doubt be found that what Article 5.3 notice
contemplates is a state of accomplishment of conditions when the notice
is sent. However, the notice dated 04.07.2017 promised completion by
31.07.2017. Article 5.3 provides for waiver. If a default notice under
Article 9.1, was given on 07.07.2018, in place of the termination notice,
97
then, with the state of completion attained and, if anything further remained,
doing that also, and issuing the notice, if insisted, the defect could have
been removed.
120. In this regard, we may notice a significant distinction between
Article 2.5.1 (d) which was used as the sheet anchor by the appellant to
contend that in the event of non-achievement of condition subsequent
termination was mandatory. Article 2.5.1(d) is as follows:
“d) In case of delay of more than 9 months, MPPMCL shall
terminate PPA and release balance amount of CPG.”
(Emphasis supplied)
121. When it comes to Article 9.1, we have noticed that it
contemplates the giving of default notice when an event of default takes
place. The seller is given three months’ time to set right things fully.
Thereafter, Article 9.1 provides that in case of the default by the seller
not being removed fully, apparently, the appellant by giving seven days
termination notice ‘may’ terminate the agreement. The choic e of the
word ‘may’ importing discretion in Article 9.1 is in stark contrast with
Article 2.5.1 (d).
122. Apparently, it was so drafted so that in an event like in a
seller event of default under Article 9.4.(a), i.e., failure by the seller to
supply power within 24 months, bearing in mind the nature of project
and the stakes involved for both the appellant and the seller, there may
be cases where the seller may wish to grant more time so that a project
which has progressed to a state of near completion may not be aborted
by the termination and grant of time would, on the other hand, witness
the full blossoming of the project.
123. It would appear that the appellant did not carry out any
inspection. The inspection carried out by the CEIG in first week of August,
2017 was an inspection conducted by the five-member team and it is
further claimed that this inspection lasted for 3-4 days beginning from
01.08.2017. The CEIG has certified that the project was ready and that
the first respondent can proceed with the commissioning act ivity. We
bear in mind that the period of twenty-four months contemplated in Article
9.4(a), would expire only on 18.09.2017. The CEIG has given its Report
on 09.08.2017 that the project was ready for commissioning. The factum
of the Report cannot be treated as a disputed question of fac t as it is
covered by a document. In fact, we find that, the appella nt proceeded
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
on the basis admittedly that it was reliable, but, however, on 11.08.2017
issued the termination notice solely based on non-fulfilment of conditions
subsequent. This notice stood set aside on 20.06.2018. Maybe the manner
in which the inspection was carried out and the pitfalls in the same may
be characterised as the disputed questions of facts. Also, thou gh the
appellant was invited to carry out the inspection on 04.07.2017, t he
appellant carried out the inspection only on 19.04.2018 and the Report
was dated 21.04.2018.
124. If we go by the Report of the CEIG, the project o f the
respondent would appear to have been completed for the purpose s of
effecting commissioning. It may be another matter that other formalities
had to be completed. When the team of the appellant carri ed out the
physical inspection, (it was done on 19.04.2018), the appellant’s team
also substantially endorsed the Report of the CEIG. However, it was
found that a certain number of string inverters inter alia, were not found
at many locations in Block Nos. 9 and 10. It was found as follows:
“4. Any other specified observation in respect of installation of
solar P.V plant
In block 9 and 10, string inverters were not found at many location
but those location had solar panels installed interconnections of
PV panel (cabling) string work at there location are not f ound
connected with each other Further, at some location the ca ble
and earthing work is observed incomplieto & suspended.”
125. It is here that we must notice the case of the first respondent
to be that though the equipment was installed as certified in the Report
of the CEIG and what remained was formal connectivity to th e grid
upon which commissioning certificate would be issued, the final event
remained on account of non-issuance of connectivity code for connection
to the grid. It is while so, when the challenge against the first termination
notice was under consideration and there was demobi lisation of
manpower, certain string inverters were stolen, the cost of which is stated
to be Rs.172000 per string inverter. Based on safety con cerns, the
equipment was, according to the first respondent, removed and kept in
safe custody. The first respondent has laid store by two first information
reports lodged. The first FIR was lodged on 12.09.2017 and another
FIR was lodged on 04.03.2018 relating to the theft of certain equipments.
This is a case where the first respondent has alleged that it has already
invested Rs.331 crores.
99
126. We will proceed on the basis that there was a CEIG Report
dated 09.08.2017 certifying that the project of the first respondent was
complete. This is well before 18.09.2017, which was the date by which
the commissioning had to be done. It is also clear that the commissioning,
as such, was not completed. Still further, if we go by the CEIG Report,
the case of the first respondent of it being on the verge of commissioning
could not be brushed aside as wanting in bonafides or merit. Still further,
there is a case of the appellant that the inspection carried out on
19.04.2018, resulting in Report dated 21.04.2018, reveale d certain
deficiencies in the form of missing inverters inter alia from Block Nos.
9 and 10 inter alia . First respondent has a case of thefts occurring. In
fact, the first respondent has a definite case that about 39 inverters
involved were also replaced in June, 2018 based on Purchase Order of
May 2018 [See Annexure R12 produced before the High Court in Review
Petition No.682 of 2020]. This is even before 07.07.2018. No doubt, the
appellant has a case that the FIRs relied on by the first respondent did
not refer to inverters. As to whether, it was a result o f thefts that the
inverters etc. which were already there as on the date of the CEIG
inspection went subsequently missing or as to whether it was as a result
of the Report of the CEIG being flawed and, therefore, the i nverters
etc. were not there in the first place, even as on the dat e of the CEIG
Report, appears to us to be a disputed question of fact. We proceed on
the basis that the inverters in question were not there. Bu t as noticed,
about 39 stolen invertors were already replaced in June 2018. At any
rate, if a default notice had been given pointing out this aspect, the matter
could possibly be put right within three months of such a notice. W e
recall here the few complaints (essentially two in number) which remained
of Respondent No.5. It could have been pointed out as part of aspect of
default if it was so understood. We have also found that the joint inspection
of the respondent No.4 had found on 24.08.2017 that the line may be
charged. What we can find is only that this is not a case where the first
respondent could be said to be in a position where it could be said that it
would be unable to comply with the terms of the default notice if it was
warranted. In other words, if as on 07.07.2018, instead of issuing a
termination notice, if notice had been given within the meaning of Article
9.1, it is quite possible that the first respondent would have remedied the
defect as alleged. We have also noted that even in 2017, no notice was
given under Article 9.1 and even the contract was terminated illegally as
found by the High Court by notice dated 11.08.2017. The whole id ea
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
behind the default notice under Article 9.1 was lost sight of by the
appellant. We have unravelled also, the impact of the use of the word
‘may’ in Article 9.1. The action of the appellant in dep arting from
unambiguous regime of the PPA without any justification would make
its actions arbitrary.
127. The other aspect projected by the appellant is what wa s
projected in the Review Petition filed before the High C ourt. It was
contended essentially as follows:
The first respondent had committed a fraud on the Office
of the Chief Electrical Inspector, the appellant and on the Court.
It was alleged that the project was divided into 10 blocks of 5MW
each and each Block of 5MW would have 116/117 Inverters
approximately. Each of the Inverter was to have a u nique
distinctive serial number. Each inverter was to have 43KV rating,
as indicated in the CEIG Report. The fraud consiste d of a
discovery by the appellant on an alleged ‘detailed’ analysis of the
serial numbers of the inverters, that in each Block, there were
several Inverters having numbers which were common/duplicate
and interchangeably used in the same or other blocks. It was
alleged that for about 186 Invertors serial numbers were
commonly, duplicably and interchangeably used. Some of the
inverter numbers were not legible. Therefore, it was alleged that
there was lack of due diligence by the authorised personnel of the
CEIG.
128. In this regard, the first respondent has countered the case of
the appellant not only by producing invoices supplied by the overseas
supplier and the bill of entry issued by the Customs Department but the
Lorry Receipts, to establish the procurement of 1175 Inverters required
for the first respondent Unit in 2017. It is also their case that the inverter
serial numbers themselves carry no significance. They w ere mere
identifiers for the purpose of record keeping, warranty claims, etc. All
the 1163 Inverters installed by the first respondent had identical mechanical
specification and the mere mention of incorrect serial num bers in the
Report of the CEIG did not establish that the first responde nt was not
ready to commission the project. The first respondent also has pointed
out that on learning of the duplication of the few inverters serial numbers
in the Report of the CEIG, it promptly approached the CEIG on 16.09.2020
with details of the correct unique serial numbers and the corresponding
101
location of the inverters. It requested the CEIG to inspect and verify the
inverters and to issue a corrigendum to the first Report dated 09.08.2017.
In fact, there is reference to first respondent in compliance with the first
impugned Judgment writing to the CEIG earlier on 15.04.2020, to visit
the project site for reissuing/revalidating the approval for commissioning
the project, since the validity of the first report dated 09 .08.2017 had
lapsed. It is specifically contended in the reply to the Review Petition
that due to non-cooperation of the appellant on the excuse of Covid-19,
the CEIG inspection could not be undertaken. This stand is reiterated, in
fact, in the counter affidavit in this Court also. It would appear that the
first respondent had deposited the inspection fee of Rs.66,14,000/- which
is said to be equipment based meaning thereby that it was paid reckoning
all the inverters. It would appear that no inspection has been carried by
the CEIG based on the request for revisit. As far as this aspect is
concerned, apart from the fact that the CEIG has conducted an inspection
and given a Report on 09.08.2017, certifying the readiness of the Unit of
the first respondent, the first respondent has produced documents like
invoices from overseas sellers, bill of entry with the Customs Department
and certain lorry receipts. The alleged fraud is the common numb er
found in 186 inverters in the Report of the CEIG. A physical inspection
by the CEIG, which was necessitated in terms of the original Judgement,
at any rate, for revalidation of the Report was and is necess ary and
inevitable even if the appeals fail. The first respondent had alerted the
CEIG for the need for a reinspection for ascertaining the aspect relating
to duplication in numbers. It would appear that such inspection has not
been carried out. In this regard, it is important to notice that the appellant
carried out an inspection on 19.04.2018 and it had not found out any
such discrepancy as it has not projected in regard to the aspect of common
numbers or illegibility of numbers, in the inverters, in its Report dated
21.04.2018. At any rate, the PPA clearly provided for the issuance of a
default notice, providing an opportunity to remove the defect. This
obligation has been observed in its breach.
129. Therefore, we would find that an inspection by the CEIG
would necessarily have to be carried out in which the appellant would
have to be involved to facilitate the exercise. In the facts of this case, on
being satisfied, the CEIG would necessarily have to grant the re-validation
of the earlier Report. It would also involve an opportunity to the CEIG to
look into the aspects which have been projected by the fist respondent
itself in its letter dated 16.09.2020. The report would indeed indicate the
M. P. POWER MANAGEMENT COMPANY LTD., JABALPUR v. M/S. SKY
POWER SOUTHEAST SOLAR INDIA PVT. LTD. [K. M. JOSEPH, J.]
state of affairs about all the facets. As already noticed, even under the
impugned Judgement dated 27.02.2020, the first respondent would have
to submit necessary applications. We only clarify that i t may involve
removing any remaining deficiencies with the fifth respondent.
130. It may not be wholly irrelevant to notice the following aspect
which is reflected in the counter affidavit filed by the respondent No.1
before this Court.
“It is of utmost importance to mention here that while the challenge
to the 2018 Termination Notice was pending, the Petitioner had
proposed a so-called amicable resolution of the dispute with the
Respondent No.1 and convened a meeting for this purpose on
February 6, 2020. Occurrence of this meeting and the discussions
held are recorded at paragraphs 7 and 8 of the Impugned Order
1. During this meeting, the Petitioner had attempted to impr ess
upon the Respondent No.1 to explore ‘Third Party Sale’ from the
project or, agree to a reduction in tariff in line with the re cent
auctions conducted by SECI for other solar power proj ects.
Respondent No.1 had rejected both the option of ‘third Party Sale’
or, the attempts to reduce tariff specified in Article 9.7 of the
PPA, which was discovered through a transparent competitiv e
bidding process. The very fact that the Petitioner had proposed to
the respondent No.1 to explore sale of power from the Project to
third parties is proof enough that the Project was complete and
ready for commissioning.”
In this regard, we may notice paragraph 4 of the minutes of the
meeting dated 06.02.2020 which reads as follows: -
“4. MPPMCL further stated that, as the commissioning of t he
project has been substantially delayed and, in the meantime solar
binding tariffs have been considerable reduced up to Rs. 2.61/
Unit for which MPPMCL has already entered into PPAs, therefore
MPPMCL offered M/s Sky Power to supply power at reduced
tariff of the project was the lowest in the bid and their investment
was made during the FY 2016-2017 therefore, supplying power
to MPPMCL at reduced tariff will not be viable henc e not
possible.”
We would think that essentially the appellant’s attempt was to
secure a reduction in the rate. The rate of the first re spondent was
103
found to be the lowest after a clearly keenly competitive international
bidding, involving a large number of bidders.
131. In the totality of facts, we would, therefore, think that though
for reasons, which may not be the same as in the impugned judgment,
we need not interfere with the view taken by the High Court. The appeals
fail and are dismissed. Parties to bear their own costs.