Mahanadi Coalfields Ltd & Anr v. M/S Ivrcl Amr Joint Venture
DR DHANANJAYA Y CHANDRACHUD, J.
1. Leave granted.
2. The appellant, Mahanadi Coalfields Ltd., is a subsidiary of Coal
India Limited1. The respondent, IVRCL AMR Joint Venture, is a joint
venture of engineering contractors engaged in the b usiness of
infrastructure development. On 11 October 2010, the appellant floated
an e-tender for the work of strengthening and widenin g of a coal
transportation road at the Talcher Coalfields in the State of Orissa. The
respondent was the successful bidder and was awarded a work ord er
on 14 December 2011. A ‘Contract Agreement’ was ent ered into
between the parties on 30 January 2012, in terms of which the wor k
order was to be executed between 16 January 2012 and 14 January
2015.
3. In a meeting held on 28 June 2012, the appellant advised the
respondent to expedite the mobilization of resources to start the work
immediately. Later, the appellant sent a series of letters to the respondent
requesting it to expedite the work as per the work schedule. In 2013 and
2014, the appellant served several notices to the respondent whe n the
1 “CIL’’
MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR
JOINT VENTURE
latter failed to adhere to the work schedule. Ultimately, the appellant
terminated the work order on 15 May 2014 allegedly on account of
delay in completing the work and the inability of the respondent to meet
the work schedule.
4. Thereafter, on 12 October 2017 the respondent raised a claim
of Rs. 128,65,12,688 enumerating the latches and delays on the part of
the appellant. The claim was rejected by the appellant on 18 December
2017. Subsequently, the respondent issued a notice of arbitration to the
appellant by a letter dated 9 April 2018 in terms of clause 15 of the
Contract Agreement. Through the said arbitration notice, the respondent
called upon the appellant to give its consent to the appointment of Justice
Asok Kumar Ganguly as the sole arbitrator. Having received no response
from the appellant to the arbitration notice within 15 days, the respondent
filed an application under Section 11(6) of the Arbitration and Conciliation
Act, 19962 before the High Court of Orissa.
5. On 29 November 2019, a Single Judge of the High Court of
Orissa allowed the application under Section 11 of the 1996 Act by
appointing a sole arbitrator. The relevant extracts of the Hi gh Court’s
decision read as follows:
“3. Learned counsel for both the sides do not dispute the fact that
Clause 15 of the contract agreement provides for “Settlement of
dispute/Arbitration” in case there is any dispute or diff erence
between the parties.
4. Mr. R Sharma, learned counsel for the opposite party has taken
different contentions on merit. He has also brought to the notice
of this Court clause 19 of the letter dated 14.12.2011 (Annexure-
3), which reads as under:
“19. That matters relating to any dispute or difference ari sing
out of the tender, work order and subsequent contra ct
agreement entered into, based on this tender and work order
shall be subject to the jurisdiction of District Cou rt, Angul
only.”
5. However, in view of the decisions of the Hon’ble Suprem e
Court in the case of Mayavati Trading Private Limited vs. Pradyuat
Deb Burman, reported in (2019) 8 SCC 714, the Court has to look
2 “1996 Act’’
527
into the arbitration clause. In that view of the matter, the matter is
required to be referred to the arbitrator.”
6. Mr K K Venugopal, learned Attorney General for India, appears
on behalf of the appellants, while Mr S Niranjan Reddy, learned Senior
Counsel, appears on behalf of the respondent.
7. The submission which has been urged on behalf of the appellants
by the learned Attorney General is that clause 15 of the Contract
Agreement dated 30 January 2012 does not constitute an arbitrati on
agreement. Hence, it has been urged that in the absence of an arbitration
agreement within the meaning of Sections 2(b) and 7 of the 1996 Act,
the very invocation of the jurisdiction under Section 11(6) was not valid.
In order to appreciate the submission, it would be necessary to extrac t
clause 15 of the Contract Agreement. The provision reads as follows:
“15. Settlement of Disputes/Arbitration:
15.1 It is incumbent upon the contractor to avoid litigation and
disputes during the course of execution. However, if such
disputes take place between the contractor and the
department, effort shall be made first to settle the disputes
at the company level. The contractor should make request
in writing to the Engineer-in-Charge for settlement of such
disputes/claims within 30 (thirty) days of arising of the case
of dispute/claim failing which no disputes/claims of the
contractor shall be entertained by the company.
15.2 If differences still persist, the settlement of the dispute with
Govt. Agencies shall be dealt with as per the Guideline s
issued by the Ministry of Finance, Govt. of India in this
regard. In case of parties other than Govt. Agencies, the
redressal of the disputes may be sought in the Court of
Law.”
8. Section 2(b) of the 1996 Act defines an arbitration agreement
to mean an agreement as referred to in Section 7. In terms of Section 7,
an arbitration agreement is an agreement by the parties to submit to
arbitration all or certain disputes which have arisen or which may arise
between them in respect of a defined legal relation ship, whether
contractual or not. Sub-section (2) of Section 7 stipulates that an arbitration
agreement may be in the form of an arbitration clause in a contract or in
the form of a separate agreement. In terms of sub-section (3) of Section
MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR
JOINT VENTURE [DR DHANANJAYA Y CHANDRACHUD, J.]
7, the arbitration agreement has to be in writing. Sub-section (4) of Section
7 then stipulates that:
“(4) An arbitration agreement is in writing if it is cont ained in-
(a) a document signed by the parties;
(b) an exchange of letters, telex, telegrams or other means of
telecommunication including communication through
electronic means which provide a record of the agreement;
or
(c) an exchange of statements of claim and defence in which
the existence of the agreement is alleged by one party and
not denied by the other.”
9. In Jagdish Chander v. Ramesh Chander,3 a two-judge bench
of this Court, while relying upon the earlier decisions in K. K. Modi v.
K. N. Modi ,4 Bharat Bhushan Bansal v. U.P. Small Industries
Corpn. Ltd ,5 Bihar State Mineral Development Corpn v. Encon
Builders (I) (P) Ltd .,6 and State of Orissa v. Damodar Das ,7
enumerated the principles governing what constitutes an a rbitration
agreement. Justice R V Raveendran, speaking on behalf of the bench,
held that the words used in an arbitration agreement should disclose a
determination and obligation on behalf of parties to r efer disputes to
arbitration. This court held:
“8 (i) The intention of the parties to enter into an arbitrat ion
agreement shall have to be gathered from the terms o f the
agreement. If the terms of the agreement clearly indica te an
intention on the part of the parties to the agreement to refer their
disputes to a private tribunal for adjudication and a willingness to
be bound by the decision of such tribunal on such disputes, it is
arbitration agreement. While there is no specific form of an
arbitration agreement, the words used should disclo se a
determination and obligation to go to arbitration and not
merely contemplate the possibility of going for arbitrati on.
Where there is merely a possibility of the parties agree ing
3 (2007) 5 SCC 719
4 (1998) 3 SCC 573
5 (1999) 2 SCC 166
6 (2003) 7 SCC 418
7 (1996) 2 SCC 216
529
to arbitration in future, as contrasted from an obligation t o
refer disputes to arbitration, there is no valid and bind ing
arbitration agreement.
(ii) Even if the words “arbitration” and “Arbitral Trib unal (or
arbitrator)” are not used with reference to the process of settlement
or with reference to the private tribunal which has to adjudicate
upon the disputes, in a clause relating to settlement of disputes, it
does not detract from the clause being an arbitration agreement if
it has the attributes or elements of an arbitration agreement. They
are: (a) The agreement should be in writing. (b) The parties should
have agreed to refer any disputes (present or future) bet ween
them to the decision of a private tribunal. (c) The private tribunal
should be empowered to adjudicate upon the disputes in an
impartial manner, giving due opportunity to the parties to put forth
their case before it. (d) The parties should have agreed th at the
decision of the private tribunal in respect of the disputes wi ll be
binding on them.
(iii) Where the clause provides that in the event of disputes arising
between the parties, the disputes shall be referred to arbitration, it
is an arbitration agreement. Where there is a specific and dire ct
expression of intent to have the disputes settled by arbitration, it is
not necessary to set out the attributes of an arbitration agreement
to make it an arbitration agreement. But where the clause
relating to settlement of disputes, contains words which
specifically exclude any of the attributes of an arbitrat ion
agreement or contains anything that detracts from a n
arbitration agreement, it will not be arbitration agreement .
For example, where an agreement requires or permits an
authority to decide a claim or dispute without hearing, or
requires the authority to act in the interests of only on e of
the parties, or provides that the decision of the aut hority
will not be final and binding on the parties, or that if e ither
party is not satisfied with the decision of the authority, h e
may file a civil suit seeking relief, it cannot be terme d as an
arbitration agreement .
(iv) But mere use of the word “arbitration” or “arbitrator”
in a clause will not make it an arbitration agreement, if i t
requires or contemplates a further or fresh consent of th e
MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR
JOINT VENTURE [DR DHANANJAYA Y CHANDRACHUD, J.]
parties for reference to arbitration. For example, use of words
such as “parties can, if they so desire, refer their dis putes to
arbitration” or “in the event of any dispute, the parties may a lso
agree to refer the same to arbitration” or “if any disp utes arise
between the parties, they should consider settlement by arbitration”
in a clause relating to settlement of disputes, indicate tha t the
clause is not intended to be an arbitration agreement. Similarly, a
clause which states that “if the parties so decide, the dis putes
shall be referred to arbitration” or “any disputes between parties,
if they so agree, shall be referred to arbitration” is not an arbitration
agreement. Such clauses merely indicate a desire or hope to
have the disputes settled by arbitration, or a tent ative
arrangement to explore arbitration as a mode of settlement
if and when a dispute arises. Such clauses require the
parties to arrive at a further agreement to go to arbitration,
as and when the disputes arise. Any agreement or cla use
in an agreement requiring or contemplating a furthe r
consent or consensus before a reference to arbitratio n, is
not an arbitration agreement, but an agreement to en ter
into an arbitration agreement in future .”
(emphasis supplied)
10. In the present case, clause 15 of the Contract Agreement is
titled “Settlement of Disputes/Arbitration”. However, the substantive
part of the provision makes it abundantly clear that there is no arbitration
agreement between the parties agreeing to refer either present or future
disputes to arbitration.
11. Clause 15.1 contains a reference to the steps to be take n for
settlement of disputes between the parties. Clause 15.2 stipulates that if
differences still persist, the settlement of the disputes with government
agencies shall be dealt with in accordance with the guidelin es of the
Ministry of Finance. In the case of parties other than government
agencies, the redressal of disputes has to be sought in a court of law.
12. A clause similar to clause 15 of the Contract Agreement in the
present case was considered by a bench of this Court in IB Valley
Transport, Vijay Laxmi (P) Ltd . v. Mahanadi Coalfields Ltd
consisting of J Chelameswar and A. K. Sikri, JJ. 8 In the said case, the
8 (2014) 10 SCC 630.
531
clause was interpreted as an alternative remedy at the company level to
be exhausted before taking recourse to other suitable legal remedies. It
was observed:
“10. From the aforesaid narration of facts, it becomes clear that
Clause 12 of the general terms and conditions provides for
a mechanism of dispute resolution before resorting to the
legal remedies. This clause specifically states that it is incumbent
upon the contractor to avoid litigation and disputes during the course
of execution. If any dispute takes place between the
contractor and the department, effort shall be made first t o
settle the disputes at the company level. Further, this clause
states that the contractors should make request in writing
to the Engineer Incharge for settlement of such dis pute/
claim within 30 days of arising of cause of dispute/claim. ”
(emphasis supplied)
13. The above extract makes it abundantly clear that clause 15 of
the Contract Agreement is a dispute resolution mechanism at the company
level, rather than an arbitration agreement. Consequently, in c ase of a
dispute, the respondent was supposed to write to the Engineer-in-charge
for resolving the dispute. Clause 15 does not comport with the essential
attributes of an arbitration agreement in terms of section 7 of t he 1996
Act as well as the principles laid down under Jagdish Chander (supra).
A plain reading of the above clause leaves no manner of doubt about its
import. There is no written agreement to refer either pres ent or future
disputes to arbitration. Neither does the substantive part of the clause
refer to arbitration as the mode of settlement, nor does it provide for a
reference of disputes between the parties to arbitratio n. It does not
disclose any intention of either party to make the Engineer-in-Charge, or
any other person for that matter, an arbitrator in respect of disputes that
may arise between the parties. Further, the said clause does not make
the decision of the Engineer-in-Charge, or any other arbitrator, final or
binding on the parties. Therefore, it was wrong on the part of the High
Court to construe clause 15 of the Contract Agreement as an arbitration
agreement.
14. However, it has been urged on behalf of the respondent by
Mr S Niranjan Reddy that the first appellant is a subsi diary of CIL. It
has been submitted that on 7 April 2017, CIL issued a policy document
MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR
JOINT VENTURE [DR DHANANJAYA Y CHANDRACHUD, J.]
to its General Managers for the settlement of disputes or di fferences
arising out of works and services contracts through arbitration. Clause 5
of the above communication provides as follows:
“Past/existing work order/contract:
5. With regards to dispute/differences cropping up in existing
work order/contract, employer (department) shall adopt
procedure for settlement of the same, through arbitration
process. As you are aware that neither the CIL Manuals
nor contract document at present contains any claus e
regarding arbitration, therefore, dispute/differences cannot
be referred to arbitration straight away. Hence, befo re
referring the matter to arbitration, consent of the other party
(contractor) is necessary for redressal of dispute/
differences through arbitration. Once, the contractor agrees
for settlement of dispute/differences arising out of contracts
through arbitration, an agreement may be signed between
employer and contractor for referring the dispute/
differences to Sole Arbitration by a person appointed by
Competent Authority of CIL/CMD of Subsidiaries (as the
case may be). The rest of the procedure shall be as per the
Arbitration and Conciliation Act, 1996 as amended by
Amendment Act of 2015 and also as per instruction
incorporated in clause “Settlement of Disputes through
Arbitration”.”
15. Hence, it is urged that the first appellant being a subsidiary of
CIL and being a public sector undertaking may well consider as to whether
the disputes which have arisen between the appellants and the respondent
should be referred to arbitration. In this context, the appellants and the
respondent placed reliance on an order dated 20 July 2018 of the Chief
Justice of the High Court of Orissa in Arbitration Petition No 59 of 2016.
16. We are unable to subscribe to the submission which has been
urged on behalf of the respondent based on the policy letter dat ed 7
April 2017. The communication which has been issued by CIL refers to
the possibility of a consensual resolution of disputes or differences through
arbitration as neither the CIL manuals nor the contract document, at the
time, contained a clause regarding arbitration. However, it has b een
submitted that once the contractor has agreed to settle a dispute through
533
arbitration, the agreement may be signed between the employer and the
contractor for reference to arbitration, by a person to be a ppointed by
the competent authority of CIL or, as the case may be, the Chairman
and Managing Director of the subsidiaries.
17. The communication dated 7 April 2017 merely indicates a
desire on behalf of CIL to have disputes related to work contracts settled
by arbitration. It requires both the parties to arrive at a further agreement
to proceed to arbitration when the dispute arises. Therefore, in view of
the principles laid down in Jagdish Chander (supra), following a line of
precedent, clause 5 in the aforesaid communication cannot be construed
as an arbitration agreement between the appellants and the respo ndent
in terms of section 7 of the 1996 Act so as to compel the appella nts to
appoint an arbitrator.
18. The order of the Chief Justice of the High Court of Orissa
dated 20 July 2018 proceeds on an understanding that the learned counsel
for both the sides did not dispute the fact that clause 15 of the Contract
Agreement and clause 5 of the policy decision 7 April 2017 ta ken by
CIL provide for appointment of an arbitrator in case there is any dispute
or difference between the parties. The order has, therefore, proceeded
on an understanding of counsel, which in any event cannot be regarded
as a binding statement of law on the existence of a n arbitration
agreement.
19. For the above reasons, we have come to the conclusion t hat
the invocation of the jurisdiction of the High Court under Section 11(6)
of the 1996 Act was not valid and there being no arbitration agreement
between the appellants and the respondent, no reference to arbit ration
could have been made. We accordingly allow the appeal and set aside
the impugned judgment and order of the High Court dated 29 November
2019. The respondent would, however, be at liberty to seek recourse to
the remedy available in law to pursue the redressal of its grievances.
20. Pending application, if any, stands disposed of.
Bibhuti Bhushan Bose Appeal allowed.
(Assisted by : Rakhi, LCRA)
MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR
JOINT VENTURE [DR DHANANJAYA Y CHANDRACHUD, J.]