Experion Developers Private Limited v. Himanshu Dewan and Sonali Dewan and Others
JUDGMENT
SANJIV KHANNA, J.
The instant appeal fi led by M/s. Experion Developers Private Limited1
under Section 67 of the Consumer Protection Act, 20192, is directed against
the order and judgment dated 16.01.2023 passed by the National Consumer
Disputes Redressal Commission 3, in the Consumer Case No. 34/2022,
whereby the appellant has been directed to refund to Himanshu Dewan &
Sonali Dewan & Others 4, the amount collected towards excess sale area,
and to execute supplementary correction deeds within six weeks from the
date of the order.
2. The appellant in the instant case had developed and constructed the
apartments in a housing project, namely “Windchants”, situated in Gurgaon,
Haryana. The respondents are the allottees or the subseque nt purchasers/
buyers of their apartments. The contractual terms inter-se are governed by
the “Apartment Buyer Agreement”5.
3. Clause 8 of the agreement pertains to the “CHANGES AND
VARIATIONS IN THE SALE AREA”. The relevant part of Clause 8.6(ii)
and Clause 8.7 read: -
1 For short, “the appellant”.
2 For short, “the Act”.
3 For short, “National Commission”.
4 For short, “the respondents”.
5 For short, “the agreement”.
1123
“8.6 While every attempt shall be made to adhere to the Sale Area, in
case any changes result in any revision in the Sale Area, the Company
shall advise the Buyer in writing along with the co mmensurate
increase/decrease in Total Sale Consideration based, however, upon the
BSP as agreed herein. Subject otherwise to the terms and conditions
of this Agreement, a maximum of 10% variation in the Sale Area and
the commensurate variation in the Total Sale Consideration is agreed
to be acceptable to the Buyer and the Buyer undertakes to be bound
by such increase/decrease in the Sale Area and the commensurat e
increase/decrease in the Total Sale Consideration. For any increase/
decrease in the Sale Area, the payment for the same shall be required
to be adjusted at the time of Notice of Possession or immediately in
case of any transfer of the apartment before the Notice of Possession
or as otherwise advised by the Company.
8.7 If any of the Changes leads to any change in sale area of the
apartment in excess of Ten Percent (10%) of the Sale Area mentioned
herein at any time prior to the execution of the Conveyance Deed for
the Apartment and such variation is unacceptable to Buyer, all attempts
shall be made by the Company to off er an alternate apartment of a
sale area similar to the Sale Area of the Apartment within a maximum
of 10% variation in the Sale area within the Group Housing Colony
subject to availability. If such alternate apartment is available, the
applicable Total Sale Consideration for such alternate apartment shall
be payable/refundable, as the case may be, for the sale a rea of the
alternate apartment at the BSP mentioned herein and there sha ll be
no claim against the Company in respect of the Apartment nor shall
otherwise be raised by the Buyer in this regard at any time.”
4. The expression “Sale Area” as defi ned in Clause 1(xlviii), reads: -
“1. (xlviii) - ‘Sale Area’ shall include the covered area, inclusive of
areas enclosed by the periphery walls, balconies/ decks, area under
the columns and wails, half of the area of walls common wit h other
premises, cupboads, projections/ledges, area utilized for the common
services and facilities provided viz. areas in/under staircases, circulation
areas, walls atriums, stilts, lift shafts and lobbies, lift machine rooms,
service shafts, passages/ corridors, refuge areas, common washrooms/
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
toilets, mails rooms, all electrical plumbing and fi re shafts, community
facilities, common service rooms, security rooms, sewage treatment
plants, underground and overhead water storage tanks, DG/panel room,
terrace gardens, air handling units, pantries and any other areas which
have been paid for or are constructed by the Company for com mon
use, but shall exclude the areas under the following:-
a) Sites for retail shops and other commercial areas in the Project.
b) Amenities such as schools, medical centre/dispens ary,
creche, other health centers and the like.
c) Dwelling units for the economically weaker sections as
prescribed under Applicable Laws.
d) Car Parking Spaces”
5. According to the appellant, there was an increase in the sale
area, earlier provisionally allotted to the respondents, and the refore vide
communication/letter dated 27.04.2017, the respective allottees were
informed about the increase and revision in the sale area of their apartments.
Accordingly, the diff erential demand letters on account of such increase
were issued by the appellant to the allottees of the apar tments, including
the respondents. The respondents/their respective previous allottees made
payments towards the diff erential demand without any demur or protest
between the period December 2017 to August 2018, and the a ppellant
executed the conveyance deeds in their favour between the peri od April
2018 to September 2019.
6. Subsequently, the respondents on 25.02.2022 fi led a complaint being
Consumer Case No. 34/2022 before the National Commission seek ing a
refund of the amounts paid by them towards the increased sale area alleging,
inter alia, that there was neither increase in the carpet area nor in the built-
up area, and that the demand towards increase in the sale area made by
the appellant was illegal. The respondents relied upon the d ecision dated
26.08.2020 rendered by the National Commission in the case of Pawan
Gupta v. Experion Developers Private Limited.6
6 2020 SCC OnLine NCDRC 788.
1125
7. The case was resisted by the appellant by fi ling a reply challenging
the very maintainability of the consumer case and contending, inter alia,
that no ‘cause of action’ had arisen. According to the appellant, respondent
nos. 1, 2 and 5 were the subsequent allottees, who came into picture much
after the increase in the sale area and raising of demand therefor. Even the
payments for the same were made by their concerned predecessor allottees
without any protest. In case of respondent no. 6, the predecessor allottee was
already intimated about the increase in the sale area and had not objected
to the increase. Respondent no. 6 was, thus, well aware of the i ncrease in
the sale area and had made payments towards the same without any protest.
Other respondents also had made payments towards the increase in the
sale area without any protest. It was further contended that as per Section
69 of the Act, a consumer complaint could be fi led within two years from
the date when the ‘cause of action’ arises. In the instant case, the ‘cause of
action’ had arisen on 27.04.2017, when the demand for the increased area
was raised by the appellant. The complaint was fi led before the National
Commission on 25.02.2022, that is, about fi ve years after the ‘cause of action’
had arisen and three years after the lapse of limitation period. Relying upon
the certifi cates, reports and affi davits of the architects, it was contended that
there was an actual increase in the sale area of the apartments as mentioned
therein and therefore, the charges demanded were valid and legal, in terms
of Clause 8 of the agreement.
8. The respondents in the rejoinder had contended that due to the Covid
pandemic, the period of limitation was suspended during the period from
15.03.2020 to 28.02.2022 by this Court in terms of the directions issued
in Suo Moto Writ Petition (Civil) No. 3 of 2020, and hence, the claim of
the respondents was within the period of limitation. In the communication/
letter dated 27.04.2017, intimating the purported increase in the sale area,
the appellant had not placed any material or evidence to justify the increase
in the area. They allege that the reports and certifi cates of the architects are
all post-dated records, which cannot be taken as the basis for justifying the
increase in the sale area.
9. The National Commission, as stated herein above, by the impugned
judgment has directed the appellant to refund the amount and execute
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
supplementary/correction deeds. The appellant being aggrieved by the same,
has preferred the present appeal.
10. Heard the learned Senior Advocates Dr. Abhishek Manu Singhvi
and Mr. Amit Sibal appearing for the appellant, and the learned Senior
Advocate Mr. Bishwajit Bhattacharyya appearing for the respondents.
11. At the outset, we must record our disagreement with the fi nding
recorded by the National Commission as to the ‘continuing cause of action’
till 26.08.2020, which is the date when the question of the excess sale area
was decided by the National Commission in CC Nos. 285/2018 and 286/2018
titled Pawan Gupta v. Experion Developers Private Limited. The issue of
limitation has to be decided as per the provisions in the en actment, in the
instant case Section 697 of the Act, which prescribes a two years limitation
to fi le a complaint from the date on which the ‘cause of action’ has arisen.
The ‘cause of action’ means every fact, which, if traversed, is necessary to
prove in order to support the claimant’s right to judgment, is not dependant
on a decision in another case by an allottee raising a similar issue.
12. As per the respondents, the ‘cause of action’ arose when the
payments towards the increase in the sale area were made, and thereupon,
the conveyance deeds were executed between April 2018 to Septem ber
2019. They also submit, on account of the Covid pandemic, the period
from 15.03.2020 to 28.02.2022 has to be excluded in terms of the directions
issued by this Court in Suo Moto Writ Petition (Civil) No. 3 of 2020. Since
the complaints were made on 25.02.2022, and on exclusion of the period
between 15.03.2020 to 28.02.2022, the complaints would be well within
the limitation of two years from the date on which the ‘cause of action’ had
arisen as prescribed in Section 69 of the Act.
7 69. Limitation period.—(1) The District Commissio n, the State Commission or the
National Commission shall not admit a complaint unl ess it is fi led within two years
from the date on which the cause of action has arisen.
(2) Notwithstanding anything contained in sub-secti on (1), a complaint may be
entertained after the period specifi ed in sub-section (1), if the complainant satisfi es the
District Commission, the State Commission or the National Commission, as the case
may be, that he had suffi cient cause for not fi ling the complaint within such period:
Provided that no such complaint shall be entertained unless the District Commission
or the State Commission or the National Commission, as the case may be, records its
reasons for condoning such delay.
1127
13. The appellant, relying upon Section 98 of the Limitation Act, 1963,
which provides that once limitation starts running no subsequent disability
or inability to institute a suit or make an application would stop it, have
argued that the ‘cause of action’ arose and commenced on 27.04.2017,
which is when the appellant had intimated the increase in the sale area and,
consequently, the enhancement of price. Accordingly, in terms of Section
69 of the Act, which prescribes the limitation of two years from the date on
which the ‘cause of action’ has arisen, the limitation had come to an end on
26.04.2019. Therefore, the respondents would not be entitled to the benefi t
of exclusion of the period from 15.03.2020 to 28.02.2022.
14. Having gone through the wording of the communication/ letter
dated 27.04.2017, we do not fi nd any merit in the subm ission of the
appellant. The communication/letter dated 27.04.2017 by th e appellant
states that the construction work was in progress and that the appellant
would soon be starting the occupation certifi cate process. Further, with
the project reaching the handover stage, the appella nt had got clarity
on the overall areas and subsequent impact on the respec tive units. As
per the calculation, the sale area of the apartment had increased by the
square feet as indicated in the communication dated 27.04.20 17. We do
not read the communication/letter as the starting point of the ‘cause of
action’. ‘Cause of action’ being the foundation of the cla im refers to the
entire set or bundle of facts necessary and material to prove in order to
get a judgment. It refers to a defi nite point of time wh en the requisite
ingredients constituting that ‘cause of action’ are complete. The ‘cause of
action’ is complete when they provide the aggrieved party with the right
to invoke jurisdiction of the court/forum. The test is to determine when
the aggrieved person could have fi rst maintained action for a successful
result. In our opinion, the communication/letter dated 27. 04.2017 was an
assertion, albeit without any specifi c details or particulars. The appellant,
as per the contractual terms, is well within their right to ask for enhanced
8 9. Continuous running of time.—Where once time ha s begun to run, no subsequent
disability or inability to institute a suit or make an application stop it:
Provided that, where letters of administration to the estate of a creditor have been
granted to his debtor, the running of the period of limitation for a suit to recover the
debt shall be suspended while the administration continues.
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
sale consideration on increase in the sale area as defi ned. The respondents
have not questioned and challenged this right of the appellant. They have
challenged the computation and calculations. The respondents have the
right to ask for calculations and details, when the appell ant had stated
that the sale area had increased. On being satisfi ed with the calculation,
the respondents could have accepted the increase in th e sale area, if the
same was in accordance with the agreement. The ‘caus e of action’ arose
when the appellant insisted and compelled the respondents /allottees to
make payment, but did not furnish the details and par ticulars to enable
the respondents/allottees to ascertain the actual allo cated sale area. One
would not expect the allottee or the consumer to challe nge the demand,
which is in terms of the contract between the partie s, and is therefore not
questionable. In such cases, no ‘cause of action’ arises. Furth er, the onus
to justify and substantiate the claim and calculations of increased sale area
was, and is on the appellant. In the context of the pre sent case, it is an
accepted position that the sale deeds were executed wit h the respondents
between the period from 13.04.2018 to as late as 09.01.2020 . In view of
the aforesaid, the complaints fi led by the respondents cannot be dismissed
on the ground of being barred by limitation under Section 69 of the Act.
We also observe that the consumer forums have the power to condone the
delay when suffi cient cause is shown, even after two years of the ‘cause of
action’ having arisen. While no application for condonation of delay was
fi led, the National Commission could have always granted an opportunity
to the respondents.
15. At the same time, we should notice the argument raised by t he
appellant on acquiescence and estoppel, as the respondents are s eeking a
refund of the amount paid without any demur or protest about four years
after the payments were made. Therefore, it is submit ted that the plea
of defi ciency of service is hit by the legal bar of acceptanc e and ones’
previous action and conduct. It is highlighted that the conveyance deeds
were executed by the appellant on the respondents/allottees upon making
full payment, including the payments with regard to the increased area, and
such payment, it is submitted, was voluntary and without reservation. It is
also argued by the appellant that it is not even the case of the respondents
that they/original allottees had made payments under some threat, coercion
or duress. Therefore, it does not lie in the mouth of the respondents to say,
1129
rather, they were estopped from saying four years after the execution of
the conveyance deeds in their favour that there was no actual incre ase in
the sale area and the demand raised by the appellant in that regard was not
justifi ed or was illegal.
16. Similar issues had arisen before this Court in Wing Commander
Arifur Rahman Khan and Aleya Sultana and Others v. DLF Southern
Homes Private Limited and Others9. This Court accepted the argument by
the consumers that execution of a deed of conveyance by a fl at buyer would
not preclude a consumer claim for compensation for delayed possession in
a case where the allottees were not given an option, but were rather told
that the possession would not be given and the conveyance deed would
not be executed without the acceptance of the off er of possession terms. In
the said case, the builder/developer had stated that it would not handover
the possession and execute the conveyance deed without a cceptance of
the off er of possession terms. Any request to take over possession and
execute the documents under protest was untenable. The consumers were,
in fact, asked to fi le an unconditional affi davit/undertaking to that eff ect,
as execution of documents under protest or claim of co ercion was not to
be entertained. In this background, this Court in Arifur Rahman Khan
(supra) held that the fl at buyers/consumers were essentially presented with
an unfair choice of either retaining their right to pursue their claims, in
which event they would not get possession or title in the mea ntime, or to
forsake the claims in order to perfect their title to t he fl ats for which they
had paid valuable consideration. Accordingly, the question ne eded to be
addressed was whether a fl at buyer who seeks to espouse a claim against
the developer for delayed possession can, as a conseque nce of doing so,
be compelled to defer the right to obtain a conveyance to perfect their title.
This Court held that it would be manifestly unreason able to expect that
in order to pursue a claim for compensation for delayed han ding over of
possession, the purchaser must indefi nitely defer obtaining a conveyance
of the premises purchased or, if they seek to obtain a deed of conveyance
to forsake the right to claim compensation. The contra ry position which
the National Commission had espoused, this Court was of the view cannot
9 (2020) 16 SCC 512.
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
be countenanced and accepted. This Court thus rejected the argument
that on the execution of the conveyance deed, the transa ction ceases to
be a transaction in the nature of “supply of services” c overed under the
Consumer Protection Act, 1986 and becomes a mere sale of immovable
property and, therefore, it is not amenable to the jurisdiction of the
consumer fora. At the same time, this Court had refused t o interfere and
grant relief in cases of purchasers who had entered into specifi c settlement
deeds with the developers observing that it would only be a ppropriate
and proper if the parties were held down by the terms of the bargain. The
contention that the settlement deeds were executed under coercion or under
undue infl uence was also not accepted since no specifi c material had been
produced on record to demonstrate the same. This Court also held that
subsequent purchasers cannot benefi t from the order of this Court therein.
However, this view in re. the subsequent purchasers stands overruled
by a bench of three judges’ in Laureate Buildwell Private Limited v.
Charanjeet Singh10. In Laureate Buildwell Private Limited (supra) the
larger bench over-ruled the ratio laid down in Arifur Rahman Khan
(supra) to the extent that a subsequent purchaser woul d not be entitled
to the benefi t of the order passed in case of the original allottee. On the
other hand, it has been held that the nature and extent of relief, to which
the subsequent purchaser can be entitled, is fact and s ituation dependent.
It cannot be argued that a subsequent purchaser, who steps into the shoes
of the original allottee of a housing project in which the builder has not
honoured its commitment to deliver the fl at within the s tipulated time,
should not expect even reasonable time for the performanc e of builder’s
obligation. Such an argument, if accepted, would lead to a situation where a
large number, possibly thousands of fl at buyers, waiting for their promised
fl ats or residences would be left without any relief. Such a conclusion
would be arbitrary. In these cases, it would be fair to assume that the
subsequent purchaser had knowledge of the delay, but such knowledge
cannot be extended to accept the submission that such delay shall continue
indefi nitely based upon an a priori assumption. The equities have to be
properly moulded.
10 2021 SCC OnLine SC 479.
1131
17. As these aspects and questions are essentially factual, albeit have
not been ascertained and addressed in the present case, we would pass an
order of remand to the National Commission to examine the issue in light
of the dictum laid down by this Court. Upon the facts being fi rst ascertained,
the legal principles have to be applied.
18. There is yet another and a stronger reason why we are inclined to
pass an order of remand. For this purpose and for the sake of convenience,
we would reproduce the observations by the National Comm ission in
Pawan Gupta (supra) on the merits for rejecting the claim made by the
builder/developer (the appellant) for the increase of the sale area. These
are as under:
“The complaints have been fi led mainly for two reasons. The fi rst is
that the opposite party has demanded extra money for exc ess area
and second is the delay in handing over the possession. In r espect
of excess area, the complainant has made a point that wi thout any
basis the opposite party sent the demand for excess area and the
certifi cate of the architect was sent to the complainant, which is of
a later date. The justifi cation given by the opposite party that on the
basis of the internal report of the architect the demand was made for
excess area is not acceptable because no such report or any other
document has been fi led by the opposite party to prove the excess
area. Once the original plan is approved by the competent authority,
the areas of residential unit as well as of the com mon spaces and
common buildings are specifi ed and super area cannot change until
there is change in either the area of the fl at or in the area of any of
the common buildings or the total area of the project (plot area) is
changed. The real test for excess area would be that the opposite party
should provide a comparison of the areas of the original approved
common spaces and the fl ats with fi nally approved common spaces/
buildings and the fl ats. This has not been done. In fac t, this is a
common practice adopted by majority of builders/developers which is
basically an unfair trade practice. This has become a means to extract
extra money from the allottees at the time when allottee cannot leave
the project as his substantial amount is locked in the p roject and he
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
is about to take possession. There is no prevailing system w hen the
competent authority which approves the plan issues some kind of
certifi cate in respect of the extra super area at the fi nal stage. There
is no harm in communicating and charging for the extra ar ea at the
fi nal stage but for the sake of transparency the opposite party must
share the actual reason for increase in the super area based on the
comparison of the originally approved buildings and fi nally approved
buildings. Basically the idea is that the allottee must know the change
in the fi nally approved lay-out and areas of common spaces and the
originally approved lay-out and areas. In my view, until this is done,
the opposite party is not entitled to payment of any e xcess area.
Though the Real Estate Regulation Act (RERA) 2016 has made it
compulsory for the builders/developers to indicate the carpet area
of the fl at, however the problem of super area is not yet fully solved
and further reforms are required.”
19. The appellant had challenged the said decision of the National
Commission by fi ling the appeals being Civil Appeal Nos. 3703-3704 of
2020 before this Court. However, they were dismissed vide the order dated
12.01.2021. The order reads as under:
“1. We are not inclined to interfere with the order of the Nati onal
Consumer Disputes Redressal Commission dated 26 August 2020 in
Consumer Complaint Nos. 285 and 286 of 2018.
2. The appeals are accordingly dismissed.
3. Pending application, if any, stands disposed of.”
20. The review petitions, being R.P. (C) Nos. 1357-1358 of 2021, in
the said civil appeals fi led by the appellant, were also dismissed by this
Court on 11.01.2022 by passing the following order:
“1. Application for oral hearing is dismissed.
2. We have carefully gone through the review petitions and the
connected papers. We fi nd no merit in the review petitions and the
same are accordingly dismissed.
3. Pending applications, if any, stand disposed of.”
1133
21. The order dated 12.01.2021 of this Court dismissing the civil
appeals and the order dated 11.01.2022 dismissing the subsequent review
petitions fi led in the case of Pawan Gupta (supra) are non-reasoned orders
that do not state what has weighed with the court while dismissing the appeals
and the review petitions. However, the result is that the orde r passed by
the National Commission in the case of Pawan Gupta (supra) has attained
fi nality and binds the parties to the decision.
22. Learned counsel for the parties have made elaborate submissions
on the issue of whether the orders passed by this Court in the case of Pawan
Gupta (supra) by applying the doctrine of merger, principle of res judicata
and in view of the rule of precedential value, would foreclose the submissions
raised by the appellant in the present case. Learned Senior Advocate, Mr.
Bhattacharyya, appearing on behalf of the respondents, has submitted
that the fi ndings recorded in the judgment by the National Commission in
Pawan Gupta’s (supra), which is a case related to the same housing project,
has merged with the order passed by this Court in the appeals preferred by
the appellant and it will be binding on the appellant on s ubsequent cases,
including the cases fi led by the respondents.
23. On the other hand, it is submitted by learned Senior Advocates, Dr.
Abhishek Manu Singhvi and Mr. Amit Sibal, that the complaint preferred
by Pawan Gupta was in his individual capacity and not in a representative
capacity. Pawan Gupta had made specifi c prayer for handing over possession
of his unit, for awarding interest on the amount paid by him for th e delay
that occurred in handing over possession and also for a refund of the amount
charged by the appellant towards service tax, car parking and increase in the
common area. Hence, upon the dismissal of the statutory appeals fi led by
the appellant in case of Pawan Gupta (supra), the judgment of the National
Commission would merge into the order of this Court through a non-speaking
order. The result would be that the litigation inter se the parties in case of
Pawan Gupta (supra) had attained fi nality in the said case. Nonetheless,
it could not be construed by any stretch of imagination that th e National
Commission was barred from examining or deciding the issues involved in
the instant case as the appellant had placed on record details and evidence
in the form of the architect’s certifi cate dated 23.09.2020 and a report of
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
the same date with calculations to show and justify the increase in the sale
area. The architect’s certifi cate and the report dated 23.09.2020 were not
placed before the National Commission in the case of Pawan Gupta (supra).
No doubt, the same were fi led before this Court as additional documents,
but the appeal itself was dismissed in limine without taking the additional
documents on record, and that too by a non-reasoned order. In the present
case, the architect’s certifi cate and the report dated 23.09.2020 were placed
before the National Commission, but they were not examined and considered
in the reasons set out by the National Commission. Decision in Pawan
Gupta (supra) was simply applied.
24. Specifi cally on the question of additional documents, it is submitted
by Learned Senior Advocate, Mr. Bhattacharyya, appearing on behalf of the
respondents, that once an application for additional documents was fi led in
this Court, the doctrine of merger would apply and, therefore, the present
appeal merits dismissal on this short ground.
25. This Court has examined doctrine of merger in several decisions,
but we would, for the purpose of this case, refer to only two decisions in
Kunhayammed and Others v. State of Kerala and Another11 and Khoday
Distilleries Limited and Others v. Sri Mahadeshwara Sahakara Sakkare
Karkhane Limited.12, which approves of the ratio in Kunhayammed (supra).
26. Kunhayammed (supra) refers to several other decisions of this
Court and has crystallised the legal position as under:
“44. To sum up, our conclusions are:
(i) Where an appeal or revision is provided against an order passe d
by a court, tribunal or any other authority before superior forum and
such superior forum modifi es, reverses or affi rms the decision put
in issue before it, the decision by the subordinate forum merges in
the decision by the superior forum and it is the latter which subsists,
remains operative and is capable of enforcement in the eye of law.
11 (2000) 6 SCC 359.
12 (2019) 4 SCC 376.
1135
(ii) The jurisdiction conferred by Article 136 of the Constitution is
divisible into two stages. The fi rst stage is upto the disposal of prayer
for special leave to fi le an appeal. The second stage commences if and
when the leave to appeal is granted and the special leave petit ion is
converted into an appeal.
(iii) The doctrine of merger is not a doctrine of universal or unlimited
application. It will depend on the nature of jurisdiction exercised by
the superior forum and the content or subject-matter of challenge laid
or capable of being laid shall be determinative of the appl icability
of merger. The superior jurisdiction should be capable of r eversing,
modifying or affi rming the order put in issue before it. Under Article
136 of the Constitution the Supreme Court may reverse, modify or
affi rm the judgment-decree or order appealed against while exercising
its appellate jurisdiction and not while exercising the discret ionary
jurisdiction disposing of petition for special leave to appeal. The
doctrine of merger can therefore be applied to the former and not to
the latter.
(iv) An order refusing special leave to appeal may be a non-speaking
order or a speaking one. In either case it does not attract the doctrine
of merger. An order refusing special leave to appeal does not stand
substituted in place of the order under challenge. All that it means is
that the Court was not inclined to exercise its discretion so as to allow
the appeal being fi led.
(v) If the order refusing leave to appeal is a speaking or der, i.e.,
gives reasons for refusing the grant of leave, then the order has two
implications. Firstly, the statement of law contained in th e order is
a declaration of law by the Supreme Court within the meani ng of
Article 141 of the Constitution. Secondly, other than the declaration
of law, whatever is stated in the order are the fi ndings recorded by
the Supreme Court which would bind the parties thereto and also the
court, tribunal or authority in any proceedings subsequent thereto by
way of judicial discipline, the Supreme Court being the Apex Court
of the country. But, this does not amount to saying that the order of
the court, tribunal or authority below has stood merged in the order
of the Supreme Court rejecting the special leave petition or that the
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
order of the Supreme Court is the only order binding as res j udicata
in subsequent proceedings between the parties.
(vi) Once leave to appeal has been granted and appellate jurisdiction
of Supreme Court has been invoked the order passed i n appeal
would attract the doctrine of merger; the order may be of revers al,
modifi cation or merely affi rmation.
(vii) On an appeal having been preferred or a petition seeking leave
to appeal having been converted into an appeal befo re the Supreme
Court the jurisdiction of High Court to entertain a re view petition
is lost thereafter as provided by sub-rule (1) of Rul e 1 of Order 47
CPC.”
27. The aforesaid decision no doubt draws the distinction between
a simple non-speaking order passed by this Court reje cting the special
leave to appeal fi led under Article 136 of the Consti tution of India, in
which case the doctrine of merger has no application, and cases where
this Court exercises its appellate power in terms of the statute or the
Constitution. In the former set of cases, the grant of special leave to
appeal is discretionary. The eff ect of a non-speaking order of dismissal of
the special leave petition without anything more indic ating the grounds
or reasons for dismissal by a necessary implication cannot be taken as
acceptance of the reasons or the ratio of the judgment under challenge.
It is not correct to assume that the Court has impli citly decided all the
questions. There could be multiple reasons why in a par ticular case a
special leave to appeal can be refused. It would be incorrect to attempt to
embark on such reasons when they have not been so stated. Such reasons
can be varied and diff erent, and may not completely and directly relate to
the merits of the case as to be construed as an imprimatur of this Court
on the correctness of the decision appealed against. A case may not raise
a question of general principle but turn on its own facts. Facts of the
particular case may not be suitable as a foundation f or determining some
question of a general principle. Due to heavy backlog of work, this Court
has to restrict the intake of fresh cases. Thus, ther e can be a variety of
reasons why the court dismisses a special leave petition , and that too by
a non-speaking order.
1137
28. Approving this aforesaid ratio, in Khoday Distilleries Ltd. (supra)
it is observed:
“20. The Court thereafter analysed number of cases where orders
of diff erent nature were passed and dealt with these judgments by
classifying them in the following categories:
(i) Dismissal at the stage of special leave petition — without reasons
— no res judicata, no merger.
(ii) Dismissal of the special leave petition by speaking or rea soned
order — no merger, but rule of discipline and Article 141 attracted.
(iii) Leave granted — dismissal without reasons — merger results.”
29. On the question whether there was any confl ict in the legal ratios in
Kunhayammed (supra) and earlier judgment of this Court in Abbai Maligai
Partnership Firm and Another v. K. Santhakumaran and Others13, the
three judges’ Bench in Khoday Distilleries Ltd. (supra) has held:
“24. Having noted the aforesaid two judgments and particularly the
fact that the earlier judgment in Abbai Maligai Partnership Firm is
duly taken cognizance of and explained in the latter judgment, we are
of the view that there is no confl ict insofar as ratio of the two cases is
concerned. Moreover, Abbai Maligai Partnership Firm was decided on
its peculiar facts, with no discussion on any principle of law, whereas
Kunhayammed is an elaborate discourse based on well-accepted
propositions of law which are applicable for such an issue. We are,
therefore, of the view that detailed judgment in Kunhayammed lays
down the correct law and there is no need to refer the cases to larger
Bench, as was contended by the counsel for the appellant.
25. While taking this view, we may also point out that even in K.
Rajamouli this Court took note of both these judgments and explained
the principle of res judicata in the following manner: (SCC p. 41,
para 4)
13 (1998) 7 SCC 386.
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
“4. Following the decision in Kunhayammed we are of the view
that the dismissal of the special leave petition against the main
judgment of the High Court would not constitute res judicata
when a special leave petition is fi led against the order passed in
the review petition provided the review petition was fi led prior to
fi ling of special leave petition against the main judgment of the
High Court. The position would be diff erent where after dismissal
of the special leave petition against the main judgment a part y
fi les a review petition after a long delay on the ground that the
party was prosecuting remedy by way of special leave petition.
In such a situation the fi ling of review would be an abuse of the
process of the law. We are in agreement with the view taken in
Abbai Maligai Partnership Firm that if the High Court allows
the review petition fi led after the special leave petit ion was
dismissed after condoning the delay, it would be treated as an
aff ront to the order of the Supreme Court. But this is not the case
here. In the present case, the review petition was fi led well within
time and since the review petition was not being decided by the
High Court, the appellant fi led the special leave petition against
the main judgment of the High Court. We, therefore, overrule
the preliminary objection of the counsel for the respondent and
hold that this appeal arising out of the special leave petit ion is
maintainable.””
30. Reiterating the conclusions in Kunhayammed (supra), Khoday
Distilleries Ltd. (supra), states:
“26. From a cumulative reading of the various judgments, we sum up
the legal position as under:
26.1. The conclusions rendered by the three-Judge Bench of this Court
in Kunhayammed and summed up in para 44 are affi rmed and reiterated.
26.2. We reiterate the conclusions relevant for these cases as under :
(Kunhayammed case, SCC p. 384)
“(iv) An order refusing special leave to appeal may be a non-speaking
order or a speaking one. In either case it does not attract the doctrine
of merger. An order refusing special leave to appeal does not stand
1139
substituted in place of the order under challenge. All that it means is
that the Court was not inclined to exercise its discretion so as to allow
the appeal being fi led.
(v) If the order refusing leave to appeal is a speaki ng order i.e.
gives reasons for refusing the grant of leave, then the order has two
implications. Firstly, the statement of law contained in th e order is
a declaration of law by the Supreme Court within the meani ng of
Article 141 of the Constitution. Secondly, other than the declaration
of law, whatever is stated in the order are the fi ndings recorded by
the Supreme Court which would bind the parties thereto and also the
court, tribunal or authority in any proceedings subsequent thereto by
way of judicial discipline, the Supreme Court being the Apex Court
of the country. But, this does not amount to saying that the order of
the court, tribunal or authority below has stood merged in the order
of the Supreme Court rejecting the special leave petition or that the
order of the Supreme Court is the only order binding as res j udicata
in subsequent proceedings between the parties.
(vi) Once leave to appeal has been granted and appellate jurisdiction
of the Supreme Court has been invoked the order passed in appeal
would attract the doctrine of merger; the order may be of revers al,
modifi cation or merely affi rmation.
(vii) On an appeal having been preferred or a petition seeking lea ve
to appeal having been converted into an appeal before the Supre me
Court the jurisdiction of the High Court to entertain a review petition
is lost thereafter as provided by sub-rule (1) of Order 47 Rule 1 CPC.”
26.3. Once we hold that the law laid down in Kunhayammed is to be
followed, it will not make any diff erence whether the review petition
was fi led before the fi ling of special leave petition or was fi led after
the dismissal of special leave petition. Such a situation is covered in
para 37 of Kunhayammed case.”
31. No doubt, in Pawan Gupta’s case (supra), this Court had not
exercised the power or jurisdiction conferred by Ar ticle 136 of the
Constitution of India, but had exercised its appellate power, which would, in
terms of the ratio in Kunhayammed (supra), becomes the fi nal order which
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
is executable. Thus, the dismissal of the appeal by this Court in the case of
Pawan Gupta (supra), had put a fi nality and an end to the litigation in the
said case. To this extent, therefore, the application of the general principle
of res judicata would bar the party from raising the plea once again. The
order passed by this Court, on the application of the principl e of judicial
discipline, bars and prevents any tribunal or parties from c anvassing or
taking a view which would have the eff ect of re-examination of the issues
and points determined in the case of Pawan Gupta (supra) inter-se the parties
to the decision. However, dismissal of the appeal would not operate as res
judicata in the case of the respondents against the appellant as they we re
not parties to the said case, and the proceedings initiated by Pawan Gupta
were fact specifi c and not in a representative capacity.
32. The dismissal of the appeal in the case of Pawan Gupta(supra)
without any reasons being recorded would not attract Article 141 of the
Constitution of India as no law was declared by the Supreme Court, which
will have a binding eff ect on all courts and tribunals in India. There is a
clear distinction between the binding law of precedents in terms of Article
141 of the Constitution of India and the doctrine of merger and res judicata.
To merge, as held in Kunhayammed (supra), and Khoday Distilleries Ltd.
(supra) means to sink or disappear in something else, to become absorbed or
extinguished. The logic behind the doctrine of merger is that there cannot be
more than one decree or operative orders governing the same subject matter
at a given point of time. When a decree or order passed by an inferior court,
tribunal or authority is subjected to a remedy available u nder law before
a superior forum, then the decree or order under challenge continue s to
be eff ective and binding; nevertheless, its fi nality is put in jeopardy. Once
the superior court disposes the dispute before it in any manne r, either by
affi rming the decree or order, by setting aside or modifying the same, it is the
decree of the superior court, tribunal or authority, which is the fi nal binding
and operative decree. The decree and order of the inferior court, tribunal or
authority gets merged into the order passed by the superior forum. However,
as has been clarifi ed in both decisions, this doctrine is not of universal or
unlimited application. The nature of jurisdiction exercised by the superior
court and the content or subject matter of challenge laid or could have been
laid will have to be kept in view.
1141
33. What is important is the distinction drawn by this Court between
the law of precedents and res judicata. In State of Rajasthan v. Nemi Chand
Mahela and Others14, it is held:
“11. The learned counsel for the petitioners had drawn our attention to
para 22 of the decision in Manmohan Sharma case, (2014) 5 SCC 782
which refers to the case of one Danveer Singh whose writ petition had
been allowed and the order had attained fi nality as it was not challenged
before the Division Bench or before the Supreme Court. Termination
of services in the case of Danveer Singh, it was accordingly held, was
not justifi ed and in accordance with law. The reasoning given in paras
22 and 23 in Manmohan Sharma case relating to the case of Danveer
Singh would refl ect the diff erence between the doctrine of res judicata
and law of precedent. Res judicata operates in personam i.e. the matter
in issue between the same parties in the former litigation, while law
of precedent operates in rem i.e. the law once settled is binding on all
under the jurisdiction of the High Court and the Supreme Court. Res
judicata binds the parties to the proceedings for the reason that there
should be an end to the litigation and therefore, subsequent proceeding
inter se parties to the litigation is barred. Therefore, law of res judicata
concerns the same matter, while law of precedent concerns application
of law in a similar issue. In res judicata, the correctness of the decision
is normally immaterial and it does not matter whether the p revious
decision was right or wrong, unless the erroneous determination relates
to the jurisdictional matter of that body.”
This ratio was followed and approved by a three judges’ Bench in
Malook Singh and Others v. State of Punjab and Others15.
34. In Makhija Construction & Engg. (P) Ltd. v. Indore Development
Authority and Others 16, after referring to several earlier decisions, this
Court has observed that a precedent operates to bind in similar situations in
a distinct case, whereas res judicata operates to bind parties to proceedings
for no other reason, but that there should be end to litigation. Principle of
14 (2019) 14 SCC 179.
15 (2021) SCC OnLine SC 876.
16 (2005) 6 SCC 304.
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
res judicata should apply where the lis was inter-parties and has attained
fi nality on the issues involved. The principle of res judicata will have no
application in cases where the judgment or order has been pas sed by the
Court having no jurisdiction thereof or involving a pure question of law.17
Law of binding precedents, in terms of Article 141 of the Constit ution
of India, has a larger connotation as it settles the princ iples of law which
emanates from the judgment, which are then treated as binding precedents.
35. In the context of factual background of the present case, and o n
examining the judgment in the case of Pawan Gupta (supra) passed by the
National Commission, we are clearly of the view that the order passed by
this Court dismissing the appeal in the case of Pawan Gupta (supra) would
operate as res judicata in the said case but does not lay down a binding
precedent which would be applicable to other cases. As it transpires from
the judgment in the case of Pawan Gupta (supra), the National Commission
itself had specifi cally observed inter alia that “there was no harm in
communicating and charging for the extra area at the fi nal stage, but for
the sake of transparency opposite party must share the actual reason for the
increase in the super area based on comparison of the originally approved
buildings and fi nally approved buildings. Basically, the idea is t hat the
allottee must know the change in the fi nally approved layout and areas of
common spaces and the originally approved layout and areas”. It is true
that there was no material on record placed by the appellant in t he said
case of Pawan Gupta (supra) showing the actual increase in the sale area.
Nonetheless, the appellant in the instant case, along with its detailed reply,
had produced the documents, i.e. the certifi cate dated 23.09.2020 given by
the Architects D-idea, the Report dated 23.09.2020 given by Knight Frank
(India) Private Limited, the affi davit dated 31.08.2021 by Mr. Muninder Pal
Singh, and the affi davit dated 26.04.2022 by Mr. Anurag Mahajan, to show
that there was an actual increase in the sale area, justifying its demand for
the extra payment. The respondents, in rejoinder, had neither pla ced any
material to contradict the said Architect’s certifi cates and reports nor had
they disputed the contents thereof. The only contention raised by them was
that the said documents were produced as an afterthought and, theref ore,
17 See Fida Hussain and Others v. Moradabad Development Au thority and Another,
(2011) 12 SCC 615.
1143
could not be taken into consideration. At this juncture, it is a lso pertinent
to note that clause 8.6 of the agreement, provided for an increase/decrease
in the sale area as defi ned and also the corresponding sale price increase
of upto 10%. The appellant, by producing the said documents, had sought
to justify that the variance, i.e. increase in the built up area of the project,
which was less than 5% and such variance was within the permissible limits.
36. Thus, we are clearly of the view that the order of thi s Court
dismissing the appeal in the case of Pawan Gupta (supra) cannot be read
as a precedent and applied to the cases in hand. In fact, precedents cannot
decide questions of fact. The decision in the case of Pawan Gupta (supra)
was based on evidence adduced by the appellant/builder/developer, which
in the said case was not found to be suffi cient and cogent to justify and
substantiate the demand raised in view of the increased sale area. No doubt,
the architect’s certifi cate and report dated 23.09.2020 was fi led before this
Court as additional documents, but a non-reasoned order passed by t his
Court dismissing the case cannot be read as accepting and considering the
additional evidence, or as rejecting justifi cation and reasons given therein for
claiming additional/increased sale area. Any additional evidence sought to be
produced at the appellate stage can only be introduced when an appropriate
application under Rule 27 to Order XLI of the Code of Civil Procedure,1908
is moved and an order is passed taking them on record. Therefore, the order
passed by this Court dismissing the appeal in the case of Pawan Gupta
(supra) is confi ned to the facts of the said case, including the evidence led
by the parties before the National Commission. The National Commission
was therefore required to consider and examine the contentions of the
appellant and not overrule the same on the grounds of the principle of res
judicata and on the rule of binding precedent, which do not apply. An order
of remand on the question of merits as to the stipulation and increase in the
sale area is therefore required.
37. However, we wish to clarify that the observations made in this
order, insofar as limitation is concerned, would be binding and has attained
fi nality. Observations made in this order on the question of acquiescence/
estoppel and merits/justifi cation of the increase in the sale area would be
aspects which would have to be considered by the National Comm ission
afresh in terms of the observations contained in the present judgment. We
EXPERION DEVELOPERS PVT. LTD. v. HIMANSHU
DEWAN AND SONALI DEWAN [SANJIV KHANNA, J.]
have not specifi cally commented on whether or not, in the facts of the
present case, principles of acquiescence/estoppel will apply or whether or
not the appellant has been able to justify and substantiate the claim for the
increase in the sale area. These aspects would be examined by the National
Commission by ascertaining the facts and on merits.
38. Accordingly, for the reasons stated above, the impugned order and
judgment passed by the National Commission is set aside and the a ppeal
is disposed of with a direction of remand in terms of the observations and
directions given herein. There would be no order as to costs.