Delhi Development Authority v. Batti & Ors
RAJESH BINDAL, J.
1. Leave granted.
2. This order will dispose of two appeals arising out of order dated
30.11.2017 passed by the Division Bench of the High Court of Delhi in
W.P(C) No. 12135/2015. One appeal is preferred by Delhi Development
Authority whereas the another has been filed by Government of NCT
of Delhi.
3. The service on respondent is complete. However, no o ne
appeared when the appeal was taken up for hearing.
4. The facts of the cases are available on record. Vide notification
dated 23.06.1989 issued under Section 4 of the Land Acquisition Act,
1894 (For short, ‘the Act’) large chunk of the land measuring a bout
3,500 Hectares was sought to be acquired for planned development of
part of Delhi. It was followed by notification issued on June 20, 1990
under Section 6 of the Act. The Award bearing No. 13/92-93 was
announced by the Land Acquisition Collector (DS), Delhi on 19.06.1992.
5. It is evident from the facts noticed by the High Court in the
impugned order that husband of the respondent late Mange Ram w as
son of late Harkesh. He was father-in-law of the respondent no.1- writ
petitioner. He was claimed to be the recorded owner of 1/12th share [01
bigha and 19 biswas and 03 biswansi] in land bearing Khasra Nos. 281/
DELHI DEVELOPMENT AUTHORITY v. BATTI & ORS.
4(10-11), 282/4 (10-3) and 80(2-8) total area measuring 23 bighas and 2
biswas, situated in the revenue estate of Village Ghari Mandu, Shahdara,
Delhi.
6. There is nothing on record to suggest the acquisition in question
was ever challenged by the predecessor-in-interest of respondent no.1.
The writ petition came to be filed in the year 2015 referring to Section
24(2) of the Right to Fair Compensation and Transparency in L and
Acquisition, Rehabilitation and Resettlement Act, 2013 (for short “the
2013 Act”) claiming that the possession of land having not been taken
and the compensation not paid, the acquisition has lapsed.
7. The High Court noticed the fact that the possession of the land
had been taken by the State and handed over to the Forest Departme nt
for development as green belt, agriculture and water body as the land
falls in ‘O’ Zone. It was further pleaded that respondent no. 1 was not
entitled to receive any compensation as the land, in fact, vested in Gaon
Sabha.
8. After considering the arguments raised by learned counse l
appearing for the parties, the High Court, while relying upon the judgment
of this Court in Pune Municipal Corporation & Anr. vs. Harakchand
Misirimal Solanki & Ors. (2014) 3 SCC 183 held that the acquisition
in question has lapsed qua the land of the respondent no.1 as the
compensation therefor had not been tendered. The issu e regarding
entitlement of compensation to the respondent as there was dispute
regarding the title of the land, was kept open.
9. The arguments raised by learned counsel appearing for the
appellant are that in view of the Constitution Bench judgment of this
Court in Indore Development Authority vs. Manoharlal and Others
(2020) 8 SCC 129 whereby earlier judgment of this Court in Pune
Municipal Corporation & Anr.’s case (supra) was overruled the order
passed by the High Court is to be set aside. It was o pined by the
Constitution Bench that compliance to either of the two conditions i.e.
taking over of possession of the land or payment of compe nsation, is
good enough to sustain the acquisition. In the case in hand, from the
facts admitted on record it is evident that the possession of the land was
taken after the acquisition was complete. There was no quest ion of
payment of compensation to predecessor in interest of th e respondent
no.1 as admittedly there was dispute regarding title of t he land. The
635
land is recorded in the name of Gaon Sabha. Even the High Court in
the impugned order had kept the question of title open.
10. Heard learned counsel for the appellant.
11. There is no dispute on the fact that the judgment of this Court
in Pune Municipal Corporation and Another’s case (supra), was relied
upon by the High Court to hold that the acquisition in question ha d
lapsed. It was overruled by the Constitution Bench judgment of this
Court in the Indore Development Authority’s case (supra). Para 362
thereof is extracted below:
“362. Resultantly, the decision rendered in Pune Mun icipal
Corporation & Anr. (supra) is hereby overruled and all othe r
decisions in which Pune Municipal Corporation (supra) has been
followed, are also overruled.”
12. Various questions required to be considered by the Constitution
Bench were answered in para 366 of the judgment. The same r ead as
under:
“366. In view of the aforesaid discussion, we answe r the
questions as under:
366.1. Under the provisions of Section 24(1)(a) in cas e the
award is not made as on 1-1-2014, the date of commencement
of the 2013 Act, there is no lapse of proceedings.
Compensation has to be determined under the provisions of
the 2013 Act.
366.2. In case the award has been passed within the window
period of five years excluding the period covered by an interim
order of the court, then proceedings shall continue as provide d
under Section 24(1)(b) of the 2013 Act under the 1894 Ac t
as if it has not been repealed.
366.3. The word “or” used in Section 24(2) between
possession and compensation has to be read as “nor” or as
“and”. The deemed lapse of land acquisition proceed ings
under Section 24(2) of the 2013 Act takes place where due t o
inaction of authorities for five years or more prio r to
commencement of the said Act, the possession of land has not
been taken nor compensation has been paid. In other words,
in case possession has been taken, compensation has not be en
DELHI DEVELOPMENT AUTHORITY v. BATTI & ORS.
[RAJESH BINDAL, J.]
paid then there is no lapse. Similarly, if compensation has
been paid, possession has not been taken then there is no
lapse.
366.4. The expression “paid” in the main part of Section 24(2)
of the 2013 Act does not include a deposit of compensat ion
in court. The consequence of non-deposit is provided in the
proviso to Section 24(2) in case it has not been de posited
with respect to majority of landholdings then all beneficiaries
(landowners) as on the date of notification for lan d
acquisition under Section 4 of the 1894 Act shall be entitled
to compensation in accordance with the provisions of the 2013
Act. In case the obligation under Section 31 of the Land
Acquisition Act, 1894 has not been fulfilled, inter est under
Section 34 of the said Act can be granted. Non-depo sit of
compensation (in court) does not result in the lapse of land
acquisition proceedings. In case of non-deposit with re spect
to the majority of holdings for five years or more,
compensation under the 2013 Act has to be paid to t he
“landowners” as on the date of notification for lan d
acquisition under Section 4 of the 1894 Act.
366.5. In case a person has been tendered the compensation
as provided under Section 31(1) of the 1894 Act, it is not
open to him to claim that acquisition has lapsed under Sectio n
24(2) due to non-payment or non-deposit of compensation in
court. The obligation to pay is complete by tenderi ng the
amount under Section 31(1). The landowners who had refused
to accept compensation or who sought reference for hi gher
compensation, cannot claim that the acquisition proceedin gs
had lapsed under Section 24(2) of the 2013 Act.
366.6. The proviso to Section 24(2) of the 2013 Act is to be
treated as part of Section 24(2), not part of Section 24(1)(b ).
366.7. The mode of taking possession under the 1894 Act
and as contemplated under Section 24(2) is by drawi ng of
inquest report/memorandum. Once award has been passed on
taking possession under Section 16 of the 1894 Act, the land
vests in State there is no divesting provided under Section
24(2) of the 2013 Act, as once possession has been taken
there is no lapse under Section 24(2).
637
366.8. The provisions of Section 24(2) providing for a deemed
lapse of proceedings are applicable in case authorities hav e
failed due to their inaction to take possession and pay
compensation for five years or more before the 2013 Act cam e
into force, in a proceeding for land acquisition pending wit h
the authority concerned as on 1-1-2014. The period of
subsistence of interim orders passed by court has t o be
excluded in the computation of five years.
366.9. Section 24(2) of the 2013 Act does not give rise to new
cause of action to question the legality of conclud ed
proceedings of land acquisition. Section 24 applies to a
proceeding pending on the date of enforcement of th e 2013
Act i.e. 1-1-2014. It does not revive stale and tim e-barred
claims and does not reopen concluded proceedings nor allow
landowners to question the legality of mode of taki ng
possession to reopen proceedings or mode of deposit of
compensation in the treasury instead of court to in validate
acquisition.”
13. A perusal of the impugned order passed by the High Court
shows that the Writ Petition was allowed relying upon the judgement of
this Court in Pune Municipal Corporation and Another’s case (supra).
The case set by the writ petitioner was that late Harkesh was the recorded
owner of the land as noticed in para 2 of the judgment. The writ petitioner
is his daughter-in-law. Even the husband of the writ petitioner had expired
when the writ petition was filed. It was claimed that late H arkesh was
having bhoomidari rights, however in terms of the stand taken by the
appellant, no surviving membership was placed on record. Definite and
undisputed stand taken by the respondent before the High Court w as
that the possession of the land was taken after the award was announced
and the same was handed over to the Forest Department for development
as green belt, agriculture and water body as the land fall s in ‘O’ Zone.
14. Initially, the stand sought to be taken by the writ pe titioner
before the High Court was that the physical possession of the land had
not been taken, however, the same was given up. The only argum ent
pressed was that the compensation be paid as per the provisions of the
2013 Act. The Writ Petition was allowed relying upon the judgment of
this Court in Pune Municipal Corporation and Another’s case (supra).
The High Court had also noticed the fact that there was disp ute about
DELHI DEVELOPMENT AUTHORITY v. BATTI & ORS.
[RAJESH BINDAL, J.]
title of the property which as per the stand taken by both the parties was
kept open. Meaning thereby, even the compensation could not have been
paid to the predecessor interest of the respondent/ writ petitioner. There
is nothing on record to suggest as to what action was taken by the person
who claimed interest in the property to seek compensation, in case land
owned by him was acquired more than two decades back a nd no
compensation paid. The litigation started only with enactment of Act of
2013
15. For the reasons recorded above, the present appeal deserve s
to be allowed as the ingredients of Section 24(2) of 2013 Act as interpreted
by this Court in Indore Development Authority vs. Manoharlal and
Others’s case (supra) are not satisfied in the case in hand. There cannot
be lapsing of acquisition of land.
16. The appeals are, accordingly, allowed and the impugned order
passed by the High Court is set aside. The writ petiti on filed by the
respondents in the High Court stands dismissed.
Ankit Gyan Appeals allowed.
(Assisted by : Mahendra Yadav, LCRA)