The State of Jharkhand v. the Indian Builders Jamshedpur
Judgment
1. In view of our opinion that Bharat Drilling & Foundation Treatment
Pvt. Ltd. v. State of Jharkhand and Ors 1 is not an authority for the
proposition that an excepted clause or a prohibited claim in a contract
applies only to the employer and not to the Arbitral Tribunal, for
the reasons to follow, in order to obviate uncertainty and for clear
declaration of law, we are referring Bharat Drilling (supra) to a larger
bench for reconsideration and authoritative decision. The context in
which we have referred the matter to a larger bench is as follows.
2. State of Jharkhand is in appeal against the judgment of the High
Court of Jharkhand allowing Section 37 2 appeal under Arbitration
and Conciliation Act, 19963. The appeal was filed by the respondent-
claimant against the judgment of the Civil Court 4 setting aside the
arbitral award allowing the objections filed by State under Section 34.
By its award dated 19.04.2007, the Arbitral Tribunal allowed certain
claims but the Civil Court set aside the claims 3, 4 and 6 on the
ground that they were specifically prohibited under the contract
between the parties.
3. Mr. Rajiv Shankar Dwivedi, learned counsel appearing for the State
of Jharkhand has made a short submission that the High Court
committed a serious error in allowing the appeal on the ground that
the issue arising for consideration is covered by decision of this
Court in Bharat Drilling (supra). Mr. Dwivedi has expressed a serious
1 (2009) 16 SCC 705.
2 In Arbitration Appeal No. 17 of 2007 dated 11.05.2012.
3 Hereinafter referred to as the ‘Act’.
4 Sub-Judge-1, Jamshedpur in Misc. Arbitration Case No. 01/2004 dated 19.04.2007.
420 [2025] 12 S.C.R.
Supreme Court Reports
concern that the decision in Bharat Drilling (supra) is being applied,
regularly and wrongly, to interpret prohibitory claim clauses in all
Government contracts. He would therefore submit that even if the
Court may not interfere in the facts of this case, there is a compelling
necessity to clarify the position of law. On the other hand, Mr. Manoj
C. Mishra, learned counsel appearing for the respondent, supported
the decision of the High Court.
4. In view of the concern expressed by Mr. Dwivedi, we agreed to
examine the question of law and the principle in Bharat Drilling
(supra). Before we proceed any further, it is necessary to examine
the relevant clauses under the agreement, which are extracted
hereinbelow for ready reference;
“4.20.0 CLAIMS:
4.20.2: No claim for idle labour, idle machinery, etc. on
any account will be entertained…
4.20.4: No claim shall be entertained for business loss or
any such loss.”
5. It is submitted that the Arbitral Tribunal committed a serious error
in allowing claim no. 3 (relating to underutilised overheads) when
that claim is barred under clause 4.20.2, claim no. 4 (relating to loss
due to underutilised tools, plants and machinery) when such claim
is clearly barred under contractual clause 4.20.2. Further, it is also
contended that claim no. 6 (relating to loss of profit) could not have
been granted in the teeth of clause 4.20.4, which specifically declares
that “no claim shall be entertained for business loss or any such loss”.
6. This submission, however, found favour with the Civil Court accepting
Section 34 objections of the State and setting aside the award on
claim nos. 3, 4 and 6. When we peruse the judgment of the High Court
under Section 37, we find that there is no discussion whatsoever as
regards to claim nos. 3, 4 and 6, except for reference and reliance
on the order of this Court in Bharat Drilling (supra). Placing reliance
upon Bharat Drilling (supra), without any other discussion or analysis,
the High Court proceeded to restore the award as regards claim
nos.3, 4 and 6.
7. As we examined the decision of this Court in Bharat Drilling
(supra), we find that it was argued therein that, the contractual “bar
against such claims is applied only to the department and not to
The State of Jharkhand v. The Indian Builders Jamshedpur
the Arbitral Tribunal”. Without examining the contention in detail,
the Court proceeded further and referred to the decision of Board
of Trustees For The Port of Calcutta v. Engineers-De-Space-Age 5
and set aside the order passed by the High Court and restored the
award. Mr. Dwivedi therefore contends that Bharat Drilling (supra)
does not lay down any law and that it is an order in the facts and
circumstances of the case.
8. It is quite evident from the order impugned before us that the High
Court has not examined the contractual clauses extracted hereinabove
and has proceeded to dispose of the appeal under the impression
that the issue is conclusively covered by the decision of this Court
in Bharat Drilling (supra). As has been already indicated, in Bharat
Drilling (supra), the Court has not examined the contractual clauses
that have fallen for our consideration herein. Contractual clauses
that limit claims are founded on freedom to contract. They are
agreements that crystalise informed choices of parties. Explaining
the incorporation of party autonomy in the statutory scheme of the
Act, this Court in Central Organisation for Railway Electrification
(CORE),6 explained this position:
“22. The basis of any arbitration is the freedom of the
parties to agree to submit their disputes to an individual
or to a panel of individuals whose judgment they are
prepared to trust and obey. Party autonomy is fundamental
to international commercial arbitration because it allows the
parties to design the arbitration proceedings to suit their
needs and commercial reality. Party autonomy has been
described by this Court as the “brooding and guiding spirit”
and “backbone” of arbitrations. The principle of minimum
judicial interference supplements the autonomy of parties
by prohibiting courts from interfering in arbitral proceedings
unless mandated by the law. This principle respects the
autonomy of the parties to mutually chart the course of
the arbitral proceedings.
23.The Arbitration Act has given pre-eminence to party
autonomy throughout the arbitral process. The Arbitration
5 (1996) 1 SCC 516.
6 2024 INSC 857 : 2024 SCC OnLine SC 3219.
422 [2025] 12 S.C.R.
Supreme Court Reports
Act has used phrases such as “unless otherwise agreed
by the parties”, “failing any agreement”, “the parties are
free to agree”, “failing such agreement”, and “unless the
agreement on the appointment procedure provides other
means” to recognize the autonomy of parties to determine
the arbitral proceedings. The use of the above phrases
also indicates that an arbitrator is bound by the procedures
agreed upon between the parties.”
(emphasis supplied)
9. Applicability of excepted or prohibitory clauses would primarily depend
upon the agreement between the parties, which alone is the guiding
principle for the Arbitral Tribunal. In similar circumstances, interpreting
the contractual clauses, this Court in Pam Developments Private
Limited v. State of West Bengal 7 held as follows;
“12. This submission is persuasive, but the contract clauses
speak for themselves. In fact, the High Court did what the
arbitrator should have done. Examine what the contract
provides. This is not even a matter of interpretation. It
is the duty of every Arbitral Tribunal and court alike and
without exception, for contract is the foundation of the legal
relationship. Having considered the above referred clauses
in the contract the High Court came to the conclusion
that awarding any amount towards idle, machinery, etc. is
prohibited under the “Special Terms and Conditions” of the
contract. The arbitrator did not even refer to the contractual
provisions and the District Court dismissed the objections
under Section 34 with a standard phrase as extracted
hereinabove. The High Court exercising jurisdiction under
Section 37 did its duty and we are of the opinion that the
conclusions of the High Court are correct and cannot be
interfered with.”
(emphasis supplied)
10. Returning to Bharat Drilling (supra), we also notice that the Court
referred to Port of Calcutta (supra) concerning payment of interest,
7 (2024) 10 SCC 715.
The State of Jharkhand v. The Indian Builders Jamshedpur
which stands on a completely different footing. This is because,
jurisdiction relating to grant of interest is sourced from Section 31(7)
of the Act. Pam Developments (supra) articulates this principle in
the following manner;
“23. The power of the arbitrator to grant pre-reference
interest, pendente lite interest, and post-award interest
under Section 31(7) of the Act is fairly well-settled. The
judicial determinations also highlight the difference in
the position of law under the Arbitration Act, 1940. The
following propositions can be summarised from a survey
of these cases:
23.1. Under the Arbitration Act, 1940, there was no specific
provision that empowered an arbitrator to grant interest.
However, through judicial pronouncements, this Court has
affirmed the power of the arbitrator to grant pre-reference,
pendente lite, and post-award interest on the rationale that a
person who has been deprived of the use of money to which
he is legitimately entitled has a right to be compensated for
the same.8 When the agreement does not prohibit the grant
of interest and a party claims interest, it is presumed that
interest is an implied term of the agreement, and therefore,
the arbitrator has the power to decide the same. 9
23.2. Under the 1940 Act, this Court has adopted a strict
construction of contractual clauses that prohibit the grant
of interest and has held that the arbitrator has the power
to award interest unless there is an express, specific
provision that excludes the jurisdiction of the arbitrator 10
from awarding interest for the dispute in question 11.
8 State of Orissa v. G.C. Roy, (1992) 1 SCC 508, para 43(i). Also see State of Orissa v. N.C. Budharaj,
(2001) 2 SCC 721; Union of India v. Krafters Engg. & Leasing (P) Ltd., (2011) 7 SCC 279 : (2011) 3 SCC
(Civ) 533
9 State of Orissa v. G.C. Roy, (1992) 1 SCC 508, paras 43 (iv) & 44.
10 Port of Calcutta v. Engineers-De-Space-Age, (1996) 1 SCC 516, paras 4 and 5; Madnani Construction
Corpn. (P) Ltd. v. Union of India, (2010) 1 SCC 549 : (2010) 1 SCC (Civ) 168; Tehri Hydro Development
Corpn. Ltd. v. Jai Prakash Associates Ltd., (2012) 12 SCC 10 : (2013) 2 SCC (Civ) 122, paras 18-20;
Union of India v. Ambica Construction, (2016) 6 SCC 36 : (2016) 3 SCC (Civ) 36 (First Ambica Construction
Case); Ambica Construction v. Union of India, (2017) 14 SCC 323 : (2018) 1 SCC (Civ) 257 (Second
Ambica Construction Case); Raveechee & Co. v. Union of India, (2018) 7 SCC 664 : (2018) 3 SCC (Civ)
711; Reliance Cellulose Products Ltd. v. ONGC Ltd., (2018) 9 SCC 266 : (2018) 4 SCC (Civ) 351.
11 State of U.P. v. Harish Chandra, (1999) 1 SCC 63.
424 [2025] 12 S.C.R.
Supreme Court Reports
23.3. Under the 1996 Act, the power of the arbitrator to grant
interest is governed by the statutory provision in Section
31(7). This provision has two parts. Under clause (a), the
arbitrator can award interest for the period between the
date of cause of action to the date of the award, unless
otherwise agreed by the parties. Clause (b) provides that
unless the award directs otherwise, the sum directed to
be paid by an arbitral award shall carry interest @ 2%
higher than the current rate of interest, from the date of
the award to the date of payment.
23.4. The wording of Section 31(7)(a) marks a departure
from the Arbitration Act, 1940 in two ways : first, it does
not make an explicit distinction between pre-reference
and pendente lite interest as both of them are provided
for under this sub-section; second, it sanctifies party
autonomy and restricts the power to grant pre-reference
and pendente lite interest the moment the agreement bars
payment of interest, even if it is not a specific bar against
the arbitrator.12
23.5. The power of the arbitrator to award pre-reference and
pendente lite interest is not restricted when the agreement
is silent on whether interest can be awarded13 or does not
contain a specific term that prohibits the same 14.
23.6. While pendente lite interest is a matter of procedural
law, pre-reference interest is governed by substantive law.15
Therefore, the grant of pre-reference interest cannot be
sourced solely in Section 31(7)(a) (which is a procedural
12 Sayeed Ahmed & Co. v. State of U.P., (2009) 12 SCC 26, paras 14, 23, 24 : (2009) 4 SCC (Civ) 629;
Union of India v. Saraswat Trading Agency, (2009) 16 SCC 504 : (2011) 3 SCC (Civ) 499; Sree Kamatchi
Amman Constructions v. Railways, (2010) 8 SCC 767, para 19 : (2010) 3 SCC (Civ) 575; Union of
India v. Bright Power Projects (India) (P) Ltd., (2015) 9 SCC 695, para 13 : (2015) 4 SCC (Civ) 702;
Reliance Cellulose Products Ltd. v. ONGC Ltd., (2018) 9 SCC 266, para 24 : (2018) 4 SCC (Civ) 351;
Jaiprakash Associates Ltd. v. Tehri Hydro Development Corpn. (India) Ltd., (2019) 17 SCC 786, paras
13-15 : (2020) 3 SCC (Civ) 605; Delhi Airport Metro Express (P) Ltd. v. DMRC, (2022) 9 SCC 286, paras
16-20, 24 : (2022) 4 SCC (Civ) 623.
13 Jaiprakash Associates Ltd. v. Tehri Hydro Development Corpn. (India) Ltd., (2019) 17 SCC 786, para
13.2.
14 Oriental Structural Engineers (P) Ltd. v. State of Kerala, (2021) 6 SCC 150, paras 15-18 : (2021) 3 SCC
(Civ) 548.
15 Central Bank of India v. Ravindra, (2002) 1 SCC 367, para 39 following State of Orissa v. G.C. Roy,
(1992) 1 SCC 508, para 43(v).
The State of Jharkhand v. The Indian Builders Jamshedpur
law), but must be based on an agreement between the
parties (express or implied), statutory provision (such as
Section 3 of the Interest Act, 1978), or proof of mercantile
usage16.
(emphasis supplied)
11. As issues relating to payment of interest arising under Section 31(7)
of the Act stand on a different footing from that of contractual clauses
excepting or prohibiting certain claims, we are of the opinion that the
judgment in Bharat Drilling (supra), relying on the judgment of this
Court in Port of Calcutta (supra), dealing with the principle of grant
of interest pendente lite, is not appropriate. Further, we are also of
the opinion that the approach adopted in Bharat Drilling (supra) is
not in tune with the principles laid down by this Court in the recent
decisions of Cox and Kings Ltd. v. SAP India Private Ltd. 17, CORE
(supra) and In Re: Interplay Between Arbitration Agreements Under
Arbitration and Conciliation Act, 1996 and Stamp Act, 189918.
12. In view of the above discussion and in order to ensure clarity and
consistency, we are of the opinion that the ratio of Bharat Drilling
requires to be reconsidered. In this view of the matter, we direct the
registry to place our judgment and order before the Hon’ble Chief
Justice for appropriate orders for placing the matter before a larger
bench of appropriate strength.
Result of the case: Registry to place the judgment and order before
the Hon’ble Chief Justice for appropriate orders
for placing the matter before a larger bench of
appropriate strength.
†