K.V. George v. Secretary to GOVT., Water and Power Department, Trivandrum & Anr.
RAY, J. Special leave granted.
' _Ji:! These appeals on special leave have been filed by the contractor,_
'
K.V. GEORGE v. St.CY. TO. GOVT., WATER DEPTT. [RAY, l.] 401
K.V. George against the judgment and order passed on 10th April,
1987 by the Kerala High Court in M.F.A. No. 291 and 304 of 1982
whereby the High Court set aside the judgment of the Sub"Court,
Trivandrum in O.P. (Arb.) No. 296 of 1981 as also the award of the
Arbitrator in A.C. No. 276 of 1980 and directed that the Arbitrator
will dispose of the Arbitration case No. 132 of 1980 in the light of the
judgment of the Sub-Court in O.P. (Arb.) No. 81 of 1981 in accor
dance with law considering the claim of the contractor-appellant and
the counter-claim of the respondents. ·
The appellant who is a contractor entered into a contract with
the respondents on April 22, 1978 in connection with the construction
of an embankment across Musaliyar Padom between Cbaniage 2573.5
M to 2827 M of E.B. Main canal of Kallada Irrigation Project. The
work was require'd to be completed by 30th March, 1980 i.e. two years
from the date of selection notice which was dated 30th March, 1978.
As the appellant failed to complete the Work as per the terms of the
contract, the respondents sent a notice dated April 26, 1980 to the
appellant cancelling the contract at his risk and cost. On July 2, 1980 D
the appellant filed a claim being arbitration case No. 132 of 1980
before the named Arbitrator i.e. the Chief Engineer (Arbitration),
Vellayambalam, Trivandrum claiming enhancement of rates in respect
of the earth work involved in the contract, interest on delayed_ pay
ments and costs. The second respondent, the Superintending
Engineer, K.I.P. Circle, Karnataka filed a defence statement stating
inter alia in para 2( 1) that the time of completion of the work was fixed
as 24 months from the date of handing over site to the contractor and
he could have anticipated all such veriations before quoting rates. As
per agreement the rates once agreed will µot be enhanced. The depart
ment is not bound to pay
1
the iclaimant a, revision of schedule. In para
2(m) it bas also been pleaded that as peir agreement the contractor is
bound to carry out additional and extra items of works that arise
during execution. The additional and extra items of works done by the
contractor are guite meagre when compared to the total volume ·()f the
work. The extra and excess items were covered by supplemental agree
ment. The contractor was not able to complete even 35% of the total
work within the time of completion of the work and as such the clai
mant is not entitled to attributed delay on this account. A counter-
. claim was filed by the Superintending Engineer, K.I.P. Circle, Kot
tarakkara, the respondent No. 2 wherein a claim of a sum of
· Rs.28,84,000 was made.
The Arbitrator by his order dated January 22~ 1981 made the H
402 SUPREME COURT REPORTS [ 1989] Supp. 1 S.C.R.
award in regard to claim No. 1 directing the respondents to pay 35%
increase in the agreed rate for the item of Earth work excavating and
filling for forming the compacted embankillent with earth from barrow
area. Claim No. 1 was thus allowed. Claim Nos. 2 and 3\regarding
interest were disallowed. As regards counter-claim Nos. 1and2, it was
ordered that those issues will be considered separately and so no
award was made.
The appellant thereafter filed O.P. (Arb.) No. 81of1981 in'the
court of Sub-Judge, Trivandrum under section 14 ·of the Arbitration
Act for making the award a rule of the court. On objections being
raised by the respondents, the Court of the Sub-Judge after hearing
the parties by order dated August 18, 1981 remitted the reference to
the Arbitrator for fresh consideration on the ground that the
Arbitrator did not consider the counter claims made by the respon
dents. The appellant thereafter filed I.A. No. 3780/81 in the court of
Sub-Judge praying that the order dated August 18, 1981 may be
reviewed. In the. meantime, the appellant filed another arbitration
I) case No. 276 of 1980 before the same Arbitrator in respect of the
wrongful termination of the contract and also raised 13 items of claims
therein. The Arbitrator after going through the objections of the
respondent made an award on October 29, 1981 whereby he ordered
that the re-arrangement of the work should not be at the risk and cost
of the appellant. As regards claim No. 2, he ordered 30% increase in
E rates (as per original and supplemental agreement) for all items of
work carried out by the appellant except on items covered by Award
No. 132 of 1980 dated 22.1.1981. Claim Nos. 3 and 5 were rejected. As
regards claim No. 4 an increase of 20 per cent iu the agreed rates for
these .. items was allowed. Claim No. 11 regarding interest was dis
allowed. It was also stated in the award inter a/ia that the claimant shall
F be entitled to the refund of the security amount as well as refund of the
retention amounts, the claimant shall be entitkd to his final bill in
terms of the Award, the counter claim for recovery of costs of re
arrangement of work and also the counter claims filed by the respon
dent dated April 8, 1981 were declined. The appellant filed O.P. (Arb)
No. 296 of 1981 for making the second award a rule of the court. A
G statement of defence was filed by the respondents wherein it has been .
stated inter a/ia in para 6 that:
"The claims made in this petition under paras 6(ii), (iii),
(iv), (v), (vi) (vii) and (viii) are barred by resjudicata and
constructive resjudicata. No work was done by the clai
mant after termination o~ t\Je contract on June 24, 1980.
K.V. GEORGE v. SECY. TO. GOVT., WATER DEPTT. (RAY, J.] 403
The claim petition _in Arbitration case No. 132/80 was filed
by the claimant.before the Hon'ble Arbitrator on 2. (.1980.
It was open to him to· raise these claims,in that"Arbitration
petition. Having not done.this raising of these claims now
which are all bogus and imaginary is barred by constructive
resjudicata. He had not raised these claims before Chief
Engineer (next Superior Authority) and also before the
Hon'ble Arbitrator in his petition dated 27.10,1980. Hence
it is prayed that the above claims may not be taken up for
arbitration and they may be rejected."
It h11s also been stated in sub-para (iv) of para 6 that:
"(iv) As above. Also there had been no error i)l the rates.
The claimant. was paid at his agreed rates, and he had
received it and also no dispute lies on it. Claim may be
rejected. Work done was recorded as per item No. 7 of
Appl. of agreement and was paid as per agreement."
The Sub-Judge by order dated March 18, 1982 made the award a
rule of the court dismissing the plea of res-judicata raised by the
respondents in O.P. (Arb.} No. 296 of 1981. The respondents filed two
appeals being FMA Nos. 291 of 304 of 1982 before the High Court of
Kerala at Emakulam which held that the Arbitrator could not review
its order on the facts of the present case and so allowed F.M.A. No. E
291 and 1982 .. The High Court also allowed F.M.A. No. 304 of 1982
holding that princieles of constructive res-judicata would apply to the
arbitration case:~eeling agrieved by the aforesaid judgment and order
passed in F.M.A. Nos. 291 and 304 of 1982, the appellant-contractor
.,.. has preferred the instant appeals on special leave.
Mr .. Bliatt, learned counsel appearing on behalf of the appellant
has submitted in the first place that the High Court was wrong in
reversing the judgment and order of the trial court without considering
the provisions of Section 114 as well as Order 47, Rule 1 of the Code of
Civil Procedure in as much as Order 47, Rule 1 clearly provides that
review of an order may be made either on account of some mistake or G
error apparent on the face of the record, or for any· other sufficient
reason. lntne ms-tan! case, the first awafci was set aside by the Trial
Court on the ground that the counter claim filed on behalf of the .
respondents was not considered by the Arbitrator and so it remitted
the same for consi(leration afresh. It has been held by the High Court
that the refusal to consider the counter claims had rendered the prior H
A award liable to be set aside for mis-conduct of the Arbitrator and the
proceedings. It has been urged by the learned counsel that the counter
claim has been fully considered in the second award made by the
Arbitrator and as such the first award cannot be set aside on the
ground of non-consideration of a counter claim and it cannot be
treated as mis-conduct of the Arbitrator and the proceedings for non
consideration of the counter claim in' the first award. It has been
further contended in this connection that the finding of the High Court
to the effect that the subsequent award passed by the Arbitrator deal
ing with the counter claims did not have the effect of mitigating the
mis-conduct of the Arbitrator or of cond9ning the error.on the face of
the award, is also not sustainable in as such as the counter claim filed
c by the respondents was duly considered by the Arbitrator in the
second award made by him.
It has also been submitted by the learned counsel for the appel
lant that the principles of res-judicata and constructive res-judicata are
not applicable to the award made in Arbitration case No. 291of1981
[} in as much as the disputes that were raised were not ripe for being
referred to Arbitration in view of the terms of the contract that the
contractor had to raise the dispute before the Superintending Engineer
and thereafter before the Chief Engineer and had to wait till the end of
the stipulated period. It has been further submitted that since the
period was not over, the claims that have been raised subsequently in
H the second claim petition before the Arbitrator could not be raised in
the first claim petition before the Arbitrator and as such the second·
award made by the arbitrator cannot be said to have been barred by
res-judicata as provided in Section 11 of the Code of Civil Procedure or
by the rules of constructive res-judicata. The judgment and order of
the High Court in allowing F:M.A. No. 304 of 1982 setting aside the
F award made in Arbitration case No. 296 of 1981 is unwarrnated and as
such it is not sustainable. It has also been contended that the claim
made in the second claim petition before the Arbitrator is not barred
by order 2, rule 2 of the Code of Civil Procedure in as much as the
disputes raised in the second claim petition before the Arbitrator were
not ripe for reference as the appellant had to wait till the end of the
q stipulated period in accordance with the terms of the contract. The
judgment and order of the High Court in allowing the F.M.A. No. 304
of 1982 is not legal and valid and is liable to be set aside.
Mr. Abdul Khadir, learned counsel appearing on behalf of the
respondents on the other hand urged befote this Court that the Sub
H Judge acted fogally in directing the Arbitrator to dispose of the arbitra-
K.V. GEORGE v. SECY. TO. GOVT., WATERDEP'IT .. [RAY, LI. 405
!Ion case No. 132/80 in the light of the judgment of the Sub-Court in A
0 .. P. (Arb.) No. 81 of 1981 and in setting aside the order of review
because no case for review nor any sufficient cause has been made out
for exercising the power of review under Section 114 read with Order
47, Rule 1 of.(he Code of Civil Procedure. The High Court, it has been /,
submitted/was right in holding thaf the order of review was unwar-
ranted and in setting aside the same and directing the Arbitrator to B
dispose of the reference in accordance 'with Jaw considering the claim
of the contractor-appellant and the counter claim of the respondents.
It has been further submitted by Mr. Abdul Khadir that in view of the
provisions of Section 41 of the Arbitration Act which specifically pro
vides that the provisions of the Code of Ch;il Procedure shall apply to
arbitration proceedings, the principles of res-judicata or of construe-
. tive res-judicata will apply to arbitration proceeding. The appellant- C
. contractor having not raised all his claims in his first claim petition
made to the Arbitrator for decision and award having been made
thereon·, the second claim petition before the Arbitrator making cer
tain other claims in Arbitration Case No. 276 of 1980 is barred by the
principles of constructive res-judicata in as much as on the termination D
of the contract by order dated April 26, 1980 the contractor could have
raised all his disputes arising out of the contract at that time, but the
appellant chose to take only some of the issues arising from the said_
breach of contract before the Arbitrator. The second claim petition
raising some issues before the Arbitrator is therefore, hit by the princi
ples of constructive res-judicata and the High Court rightly allowed the E
appeal setting aside the award made in Arbitration Case No. 276 of
1980. It has also been submitted that the provisions of Order 2, Rule 2
of the Code of Civil Procedure apply to the arbitration case and the
appellant having not sought reference of all the issues, he should be
deemed to have surrendered those issues and he is debarred from
raising those issues in a subsequent claim petition made before the F
Arbitraror. In this connection, he has cited the ruling in Muhammad
, Hafiz and Anr. v. Mirza Muhammad Zakaria and Ors., AIR ·l922 (_PC)
23. The learned counsel drew our attention to para 2(i) of the objec
tions filed by the respondents in Arbitration Case No. 132 of 1980
wherein it has been stated that:
" ' .
" ........ As per agreement thlfrates once agreed will not
be enhanced. The department is not bound to pay the
claimant a revision of schedule."
It has been further submitted by the learned counsel on behalf of
the respondents that the appellant was not entitled to an increase in H
0
the rates as he claimed increase with the agreement and the claim that
has been made is untenable.
It has been lastly submitted on behalf of the respondents that the
Arbitrator has mis-conducted himself and the proceedings by not,
deciding the counter claim filed by the Government while considering
the claim filed by the appellant and making a award. The High Court
has rightly held that the Arbitrator mis-conducted himself and the
proceedings and allowed the appeal, setting aside the second award
made by the Arbitrator in Arbitration Case No. 276 of 1980.
The first question that falls for consideration in this case is
whether the finding of the High Court setting aside the ordr of review
made in I.A. No. 3780 of 1981 and setting aise the order made in O.P.
(Arb.) No. 81 of 1981 dated August 18, 1981 whereby the case was
remanded to the Arbitrator is sustainable or not. Admittedly, the
appellant filed a claim petition being Arbitration Case No. 132 of 1980
making certain claims before the Arbitrator. The respondents filed the
counter claims. The Arbitrator without considering the counter claims
kept the counter claims for subsequent consideration and made an
award. The Trial Court set aside the award and remitted the same to
the Arbitrator for making a fresh award considering the claims and
counter-claims filed by the parties. On an application for review, the
Trial Court set aside' the order and passed a decree in terms of the •
lj: award. It is not disputed that the Arbitrator did not at all consider the
countetclaims and kept the same for consideration subsequently while
making award in respect of the claims filed by the appellant.
Undoubtedly, this award made by the Arbitrator is not sustainable in
law and the Arbitrator has mis-conducted himself and in the proceed
ings by making such an award. It is the duty of the Arbitrator while
It considering the claims of the appellant to consider also the counter
claims made on behalf.q_f the respondents and to make the award after
considering both the daims and counter claims. This has not been
done and the Arbitrator did not at all consider the counter claims of
the respondents in making the award. As such the first award dated
January 22, 1981 made by th.e Arbitrator in Arbitration Case No. 132
~· of 1980 is wholly illegal and unwarranted and the High Court was right
in holding that the Arbitrator mis-conducted himself and the proceed
ings in making such an award and in setting aside the same and direct
ing the Arbitrator to dispose of the reference in accordance with law
considering the claim of the contractor and the counter claim of the
respondents. The order allowing the application for review by the
Iii Ttial Court is also bad in as much as there was no mistake or error
K.V. GEORGE v. SECY. TO. GOVT., WATllR DEPTT. (RAY, J.] 407
apparent on the face of the order dated August 18, 1981 made in O.P. A
.(Arb.) No. 81of1981 nor any sufficient reason has been made out for
review of the said order. The order dated August 18, 1981 is legal and
valid order and the order dated March 18, 1982 allowing the.applica
tion for review being I.A. No. 3780 of 1981 and setting asie the order
in O.P. (Arb.) 81of1981 dated August 18, 1981 is, therefore, bad and
unsustainable. B
With regard to the submission that the issues that have been
raised in the second claim petition before the Arbitrator is barred
under the provisions of Order 2, Rule 2 of the Code of Civil Proce
dure, it is convenient to refer to a passage in Mu/la's Code of Civil
Procedure (Volume II, Fourteenth Edition) at page 894:·
" .... This r.ule does not require that when several causes
of action arise from one transaction, the plaintiff should
sue for all of them in one suit. What the rule lays down is
that where there is one entire cause of action, the plaintiff
cannot split the cause of action into parts so as to bring D
separate suits in respect of those parts."
It is pertinent to refer in this connection to the decision in
Muhammad Hafiz and Anr. v. Mirza Muhammad Zakariya and Ors.,
AIR 1922 (PC) 23 wherein a mortgage deed provided that if the
interest was not paid for six months the creditor should be competent E
to realise either. the unpaid amount of the interest due to him or the
amount of principal and interest, by bringing a suit in court without
waiting for the expiration of the time fixed, and the Plaintiff, more
than 3 years after (i.e. time fixed), brought a suit for interest alone and
got a decree. It was held that. the second suit for principal and arrears
of interest was not maintainble as under Order 2, Rule 2, C.P.C. he F
must be deemed to have relinquished his claim for further relief, he
having exercised the option of suing for interest alone. It was further
held that the cause of action referred to in the rule is the case of action
which gives occasion to, and forms the foundation of, th'e suit, and if
that cause enables a man to seek for larger and wider relief than that to
which he limits his claim, he cannot afterwards seek to recover the G
balance by independent proceedings.
In the instant case, the contract was terminated by the respon
dents on April 26, 1980 and as such all the issues arised out of the
termination of the contract and they could have been raised in the first
claim petition filed before the Arbitrator by the appellant. This having. 1::1
408 SUPREME COURT REPORTS [ 1989] Supp. 1 S.C.R.
A not been done the second claim petition before the Arbitrator raising
the remaining disputes is clearly barred.
With regard to the submission as to the applicability of the
principles of res-judicata as provided in Section 11 of the Code of Civil
Procedure to arbitration case, it is to be noted that Section 4 t of the
B Arbitration case provides that the provisions of the Code of Civil
Procedure will apply to the Arbitration proceedings. The provisions of
res-judicata are based on the principles that there shall be no multipli
city of proceedings and there shall be finality of proceedings. This is
applicable to the arbitration proceedings as well. It is convenient to
refer to the decision in Daryao and Ors. v. The State of U.P. & Ors.,
C [ 1962] 1 SCR 574 at 582-83 wherein it has been held that the principles
of res-judicata will apply even to proceedings under Article 32 and 226
of the Constitution of India. It has been observed that:
"Now, the rule of res-judicata as indicated in s. 1l of the
Code of Civil Procedure has no doubt some technical as
pects, for instance the rule of constructive res-judicata may
he said to be technical; but the basis on which the said rule
rests is founded on considerations of public policy. It is in
the interest of the public at large that a finality should
attach to the binding decisions pronounced by Courts of
competent jurisdiction, and it is also in the public interest
that individuals should not be vexed twice over with the
same kind of litigation. If these two principles form the
foundation of the general rule of res-judicata they cannot
be treated as irrelevant or inadmissible even in dealing with
fundamental rights in petitions filed under Art. 32."
F In Satish Kumar and Ors. v. Surinder Kumar and Ors., AIR 1970
(SC) 833 it has been observed that:
"The true legal posi!ion in regard to the effect of an award
is not in dispute. It is well settled that as a general rule, all
claims which are the subject-matter of a reference to arbit-
G ration merge in the award which is pronounced in the pro
ceedings before the arbitrator and that after an award has
been pronounced, the rights and liabilities of the parties in
respect of the said claims can be determined only ·on the
basis of the said award. After an award is pronounced, no
action can be started on the original claim which had been
H the subject-matter of the reference ........... This con-
K.V. GEORGE v. SECY. TO. GOVT., WATER DEPTI. l~AY, J.J 409
clusion, according to the learned Judge, is b.ased upon the
elementary principle that, as between the parties and their
privies, an award is entitled to that respect which is due to
judgment of a court of last resort. Therefore, if the award
which has been pronounced between the parties has in fact,
or can, in law, be deemed to have dealt with the present
dispute, the second reference would be incompetent. This
position also has not been and .cannot be se•fously
disputed."
Considering the above observations of this Court in tl\e'-aforesaid
cases we hold that the principle of res judicata or for tl\at the principles
of constructive res judicata apply to a~bitration proceedings and as
such the award made in the second arbitration proceeding being Arbit
ration Case No. 276 of 1980 cannot be sustained and is therefore, set
aside. The High Court has rightly allowed the F.M.A. No.304 of 1982
holding that the appellant-contractor was precluded from seeking· the
second reference. No other points have raised before us by the
appellant.
In the premises aforesaid, we dismiss these appeals with costs
quantified at Rs.5,000 and affirm the judgment and order dated April
10, 1987 made by the High Court.
Y. Lal Appeals dismissed. E