The State of Uttar Pradesh and Anr. v. Keshav Prasad Singh
This appeal by special leave arises from the Judgment of the Division
Bench of the Allahabad High Court in Writ Petition No. 1179/73 dated the
July 19, 1977. The facts lie in a short compass. The land comprising 205
links situated in plot No. 702 which comprises a total area of 580 links was
acquired in the year 1963 for the construction of PWD office building in D
Sharjuddinpur in Azamgarh city. While making construction, it was indeed,
as found by the Civil Court, at a suit of the respondent that the State had
encroached upon 140 links of the land in the said plot No. 702 which was
subsequently demarcated as plot No. 702/A and described as plot nos.
702/4 (68 links) and 702/5 (72 links). The Civil Court issued a mandatory E
injunction directing the PWD Department to remove the encroachment.
The State while carrying the matter in appeal, simultaneously invoked its
power of eminent domain and issued notification under Section 4(1) of the
Land Acquisition Act, 1894 (for short, 'the Act') which was published on
October 26, 1972. The said notification came to be questioned in the High
Court in this Writ Petition on two grounds and the High Court found,
firstly, that the power exercised under s.17(1) was not justified since the
land is neither waste nor arrable land and that, therefore, the notification
dispensing with the inquiry under s.S(A) was clearly illegal. The Govern
ment without admitting that the respondent was the owner and having filed
the appeal to the District Judge on the basis of the finding that the G
appellants had encroached upon the respondent's land and a mandatory
injunction for demolition of the compound wall having been issued, the
exercise of the power section 4(1) of the Act was colourable. Accordingly,
the notification under s.4(1) and the declaration under s.6 came to be
quashed. Thus, this appeal by special leave. H
It is contended for the State that the view taken by the High Court
is clearly unsustainable. When the State found that there is mandatory
injunction issued by the Court holding that the respondent is owner of the
land and that the construction was made on a land which is not part of the
land acquired in 1963, the Government exercised the power of eminent
domain and that, therefore, the State is entitled to issue the notification
under s.4(1). It is also contended that since the compound wall was already
constructed and as mandatory injunction was operating against the appel
lant for its demolition, the Government was justified to exercise its power
under s.17(1) read with s.17(4) dispensing with the inquiry under Section
SA of the Act.
Sri Manoj Swarup, the learned counsel appearing for the respondent
in his usual vehemence contends that this is a clear case of mala fide and
colourable exercise of the power. In view cif the fact that the Government
had not admitted the right of the respondent and the State had taken a
D different stand that it was a mistaken identity of the property and since the
Civil Court recorded a finding that the respondent is the owner of the land
the Government, without surrendering possession or demolition of the
compound wall, cannot justify its unlawful action by exercising the power
of eminent domain. It cannot issue the notification under s.4(1) to nullify
E the decree of injunction of the Civil Court. Thus, it ·would constitute
colourable exercise of power and this Court would be reluctant to justify
such action under Article 136 to support such high-handed and illegal
action on the part of the State. It is also contended that since land is not
an arrable land, the exercise of power under s.17(1) read with s.17(4) is
F clearly illegal.
Having considered the respective contentions, we are of the con
sidered view that the conclusion of the High Court was clearly illegal. It is
· seen that the land acquired was for a public purpose. Admittedly, the same
land was acquired in the year 1963 for building a PWD office and after
G construction compound wall was also constructed to protect the building.
As found by the Civil Court, on adducing evidence in a suit, that the
Department had encroached into respondent's land which was directed to
be demolished and delivery of possession to be given. It is seen that when
that land was needed for a public purpose, i.e. as part of public office, the
H State is entitled to exercise its power of eminent domain and would be
...-.-
'
STATE OF U.P. v. K.P. SINGH 333
justified to acquire the land according to law. Section 4(1) was, therefore, A
correctly invoked to acquire the land in dispute. It is true that the State
had not admitted that its officers had encroached upon the respondent's
land and had carried the matter in appeal. The finding of the Civil Court
was that the property belongs to the respondent. The factum of the action
under the Act implies admission of the title of the respondent to the extent B
of land found by the civil court to be an encroachment. Though the State
chose to file the appeal which was pending, better Judgment appears to
have prevailed on the State to resort to the power of eminent domain
instead of taking a decision on merits from a Court of Law. In view of the
fact that the PWD Office building was already constructed and a com
pound wall was needed to make the building safe and secure and construc
tion was already made, which is a public purpose, the exercise of power of
eminent domain is perfectly warranted under law. It can neither be said to
be colourable exercise of power nor an arbitrary exercise of power.
The next question is whether the Government would be justified in D
exercising its power under s.17(4) and dispense with the inquiry under s.5A
of the Act. Mandatory injunction issued by the Civil Court to demolish the
compound wall and to restitute possession to the respondent had to be
complied with. There is thus urgency. The public purpose was obvious as
the compound was required to be retained to protect the safety of the E
office. The object of s.5A enquiry was to show whether there was no public
purpose or the land was not suitable or some other lands may be acquired.
All these relevant and related facts are redundant due to the facts of the
case.
So, on the facts and in the circumstances, the Government was
justified in exercising their power under s.17(4) invoking urgency clause
and dispense with the inquiry under s.5A. By no stretch of imagination it
could be said that there was no public purpose, for which inquiry under
s.5A. could be made and decision taken. In that view of the matter, the
High Court was clearly in error in allowing the Writ Petition and com- G
mitted a manifest error of law in quashing the notification under s.4(1) and
declaration under s.6 of the Act.
In view of the fact that the matter is pending for a long time, the
Land Acquisition Officer is directed to pass an award within six months H
334 SUPREME COURT REPORTS [1995) SUPP. 2S.C.R.
A from the date of the receipt of the order of this Court. It is open to the
respondent to put forth his claim for compensation according to law and
it would be decided by the Land_ Acquisition Officer according to law. The
Appeal is allowed and the W.P. stands dismissed. No costs.
T.NA. Appeals allowed
'.·