State of Karnataka Represented Through Chief Secretary to Government of Karnataka v. Shri T.R. Dhananjaya and Anr.
This Court by order dated August 25, 1995 found, Mr. J. Vasudevan,
Principal Secretary, Housing and Urban Development Department,
Government of Karnataka guilty of wilful disobedience of the order of this
Court and sentenced him to undergo simple imprisonment for one month.
Thereon, Vasudevan filed I. As. 4 and 5 of 1995 praying for remission of
the sentenc~ and explaining the circumstances in which he sought the
remission. It was also stated that the order in question has since been
implemented. By our order dated September 8, 1995, the applications were
rejectoo.
The State of Karnataka filed this I.A. on September 11, 1995 for
reviewing the order dated September 8, 1995. It has been stated in the
application that primarily the State is responsible to implement this Court's
order through their Secretaries and the State has highest regards for the
G orders of this Court. After the afoi;esaid ordt?r was passed by this Court
against Vasudevan, the judgment of this Court has been implemented and
therefore sentence of imprisonment is requested to be remitted.
It is now settled law that an appeal or application like the one at
hand can be initiated only by the person found guilty. No other person has
H any right to intervene on his behalf, as he alone is the person aggrieved.
....
STATE v. T.R.DHANANJAYA 641.
Since Vasudevan had filed aforesaid applications and his prayer for remis
sion was rejected on merits, the application filed by the State seeking
review of a review order, is not maintainable. It is submitted on behalf of
the State that in view of the extensive power of this Court under Article
142 of the Constitution, this Court may consider the matter and remiMhe
sentence. We do not find any circumstance warranting further review of
our review order and that too on self-same grounds. The contention of the
State is that since the action is taken at different levels, the officer is not
personally liable for the violation of the order of the Court. It is their
internal management and the Court or any other party would not know as
to who was actually responsible for the disobedience. It would be open to
the Government to frame appropriate rules fastening the responsibility and
accountability for implementation of the order of the courts and to inform
the courts in that behalf. Till this is done, officers like Vasudevan shall have
to be held responsible for disobedience of courts' order relating to their
Department.
The application is accordingly dismissed.
R.P. Application dismissed.