Smt. Mukul Rani v. Arshnei and Ors. v. Delhi Development Authority and Anr.
. The appellants let out the property in question to M/s. Tufted
Carpets and Woolen industries Limited (subsequently the name of the
tenants was changed to M/s. Trans Asia Carpets Ltd.) in July, 1978. The
H tenants applied for permission to respondent No. 1, for using the said
"'
.....
....
..
M.R. V ARSHNEI v. D.D.A 805
property for commercial purposes, known as non- conforming purpose, A
Permission was granted and extended from time to time by respondent No.
1 till September 1981, though the tenants kept representing to the
authorities for extension of time to stop the use of the premises for
commercial purposes. In January, 1983 the appellants received a show
cause notice dated 3rd December, 1982 from respondent No. 1 asking them B
to show cause as to why they should not be prosecuted for violating Section
14 of the Delhi Development Act, 1957 (hereinafter referred to as the Act)
on the ground that the appellants had pemiitted the tenant-company to use
the said property in contravention of the provisions of the Master Plan and
the Zonal Development Plan of Delhi. The appellants replied to the show
cause notice stating that they had no information that the tenant was using C
the property in contravention of the plan without pennission of respondent
No. 1 and asserted that they had not given any permission to the tenants
to use the property for non- conforming purposes. The appellants were,
thereafter, asked by respondent No.1 that the tenants should be stopped
from misusing the property within 15 days from the date of the communica- D
tion, failing which prosecution under Section 29(2) of the Act would be
launched against the appellants. This communication from respondent
No.1 is dated 24th March, 1983. The appellants once against through their
letter dated 12th April 1993, controvered the allegations contained in the
communication and reiterated what they had stated in the reply to the show
cause notice. They also, on the same date, through their counsel sent a E
notice to the tenant calling upon it to immediately stop the commercial use
of the property. While the matter rested thus, prosecution was launched
against the appellants for violation of Section 14 of the Act punishable
under Section 29(2) of the Act. The learned Trial Magistrate convicted the
appellants vide judgment dated 1st April 1985 and imposed a fine of Rs. F
1500 on each of the four appellants. The appellants preferred an appeal
against their conviction and sentence before the Additional Sessions Judge,
New Delhi but without any success and their appeals were dismissed on
17th July 1989. The revision petitions filed by the appellants before the
. High Court were dismissed in limine. By special leave granted by this
Court, the appellants are before us. G
We have heard learned counsel for the parties and perused the
record. Section 14 of the Act provides. :
"14. User of land and buildings in contravention of plans - After H
806
SUPREME COURT REPORTS [1995) SUPP. 3 S.C.R.
the coming into operation of any of the plans in a zone no person
shall use or permit to be used any land or building in that zone
otherwise than in conformity with such plan:
Provided that it shall be lawful to continue to use upon such
terms and conditions as may be prescribed by regulations made in
this behalf any and or building for the purpose and to the extent
for and to which it is being used upon the date on which such plan
comes into force."
From a bare reading of the Section, it is obvious that a person can
C be said to violate the plan, if he uses or pennits to be used the property
otherwise than in conformity with the Master/Zonal Plan. The allegations
against the appellants is that they had pennitted the tenant to use the
property for commercial purposes in violation of the Master Plan.
There is no legal evidence led by the prosecution to show that the
D appellants had pemiitted the property to be used by the tenant in violation
of the Master Plan for non-conforming purposes. The only witness who·
appeared on behalf of the respondent before the Trial Court in support of
their case, Shri Shamimudeen, Junior Engineer, DDA, PW2, deposed that
the tenant had told him that he had been permitted by the appellants to
E use the property for commercial purposes. This is hear-say evidence and
clearly not admissible. The tenant was not examination as a witness in the
case, PW2 expressed total ignorance as to whether the tenant was actually
using the property as commercial property with the pennission of the
.,
landlord or not. No other oral or documentary evidence was led in support ~
of the allegation against the appellant. Thus, in the absence of any legal
· F evidence to show that permission had been granted by the appellants to
the tenant to use the property in contravention of the Master Plan, no
conviction of the appellants could have been recorded. by the Trial Court.
The courts below thus fell in error in convicting the appellants
G without any legal evidence on the record.
The appeal consequently succeeds. The conviction and sentence of
the appellant is set aside and they are hereby acquitted. The fine which
had been paid by the appellant shall be refunded to them.
G.N. Appeal allowed.