Tamil Nadu Electricity Board and Anr. v. N. Raju Reddiar and Anr.
PATIANAIK, J. Leave granted.
This appeal by special leave is directed against the Judgment of the
F Division Bench of the Madras High Court dated 6.9.1995 in O.S.A. No. 112
of 1987. The palintiffs who are the respondents in this appeal filed the suit
on the original side of the High Court for recovery of a sum of Rs. 46,08,820
together with interest at 18% per annum. It was alleged in the plaint that
the defendants who are appellants in this appeal invited tenders for
transportation of iron and steel materials including unloading, weighment
G and stocking from various stockyards of the suppliers to the destination
stores during the period 1.9.1978 to 31.8.1979. In pursuance of the aforesaid
advertisement the Plaintiff No. 1 submitted his tender on 12.7.1978 and
along with tender submitted, a letter was also enclosed. This offer of the
plaintiff was accepted and an agreement was entered into. In accordance
H with the agreement the plaintiff furnished a bank guarantee and deposited
T.N. ELECTRICITY BD. v. N.R. REDDIAR [PATTANAIK,J.] 743
the necessary earnest money and commenced the work of transport of A
materials. It was further alleged that the palintiffs carried the material and
di;livered the same at various destinations as per the direction given from
time to time by the defendants. In all a total quantity of 1, 73, 78, 821 metric
tonnes of iron and steel were transported and the necessary bills were
submitted in November, 1979. But the defendant instead of making the B
payments in accordance with the terms of the contract postponed the
payment of the bills. It was averred in the plaint that the defendant agreed
to pay no on multi slab basis which is apparent from letter of the plaintiff
attached to the tender submitted by him and that was also the trade
practice. The plaintiff finally issued a notice on 28.3.1980 calling upon the
defendants to settle the bills but the defendants replied on 7.5.1980 making C
several misleading averments. As the plaintiffs' bills were not settled, the
suit was filed for recovery of the amount as already stated.
The defendants in their written statement denied the allegations
made in the plaint. The specific stand taken in the written statement was D
that the plainiffs are not entitled to claim multi slab basis and on the other
hand they are entitled to single slab basis. It was stated that the multi slab
rates had never been accepted and not covered by the agreement executed
by the parties. It was also stated that on the basis of instructions from
headquarters the Superintending Engineer5 have been passing the bills on
single slab basis and the plaintiffs remained silent during the entire tenure
of the contract period but raised this issue after the contract period was
over. The defendant further averred that the plaintiffs have not delivered
the materials correctly at some destinations. In reply to the aforesaid
written statement the plaintiffs also filed a reply statement denying the
allegations made in the written statement and reiterated the stand taken in
the plaint. On these pleadings the learned Single Judge framed three issues
and on Issue No. 1 came to hold that the rates mentioned in Exhibit D-8 ,,
will have to be calculated on single slab basis and not on multi slab basis
as contended by the plaintiffs. So far as the letter Exhibit P-1 dated
11.7.1978 which was enclosed to the tender from Exhibit P-2, the learned G
Single Judge negatived the contention of the defendant and came to hold
that the words written in ink in Exhibit P-1 were ai the time of submission
of the tender. The words were "! have quoted my rates for each slab and
add for every extra one and part thereof'. The plaintiffs' case is essentially
based on the aforesaid expression in the letter which was enclosed to the H
744 SUPREME COURT REPORTS [1996\ SUPP.1 S.C.R.
A tender and which according to the plaintif!S was ultimately accepted. The
learned Single Judge, however, construed the expression "for each slab"
mentioned in Exhibit D-6 and came to hold that the tender was not on
multi slab basis. The learned Judge also held that merely because the
tender conditions are not clear one cannot accept the contention of the
B plaintiff that the rates agreed upon is on multi slab basis. Further taking
into account the terms and conditions of Exhibit D-1 the learned Judge
came to hold that the irresistible conclusion is that what was intended is
only a single slab basis. The learned Judge also examined several other
tenders and then negatived the plaintifrs contention that the agreement
was on multi slab basis. On an analysis of the pattern of the working of the
C rates in several tenders the learned Judge rejected the plaintiffs' contention
that the contract was on multi slab basis. Though the plaintiffs relied upon
several recommendations of the Superintending Engineer but the learned
Judge on consideration of the same came to hold that those recommenda
tions will have to be rejected. It was also held that the terms and conditions
D of a contract have to be decided on its own and production of other
contracts will not be of any help in deciding what are the terms of the
present contract. He also held that the defendants failed to produce any
other contemporarious contract which has been granted on multi slab basis.
On issue No. 2 the learned Single Judge on consideration of entire evidence r .
on record came to hold that the shortages alleged by the defendants had
not been established. On Issue No. 3 the learned Single Judge came to hold
that there is considerable delay in the matter of payment of bills though
such delay had occasioned on account of difference in the interpretation
of the terms of the contract and the delay is on the part of the defendants
in settling the bills. With these conclusions and on calculating on single slab
basis the learr.ed Single Jugde passed a decree for Rs. 9,31,157.63 witb
interest at 12% per annum from 1.1.1980 till the date of decree and
thereafter at 6% per annum. The suit was thus decreed in part. The
plaintiffs challenged the decree by filing an appeal and the defendants also
filed a cross-objection challenging that part of the decree in favour of the
G plaintiffs. The Division Bench of the High Court relying upon the hand
written portion of Exhibit P-1 and the conduct of the Superintending
Engineer in passing the palintiffs' bills on multi slab basis as well as relying
upon some other contracts came to hold that the plaintiffs are entitled to
freight charges on multi slab basis. The Division Bench also held that the
H interpretation of the learned Single Judge of the expression 'for each slab'
T.N. ELECTRICITYBD. v. N.R. REDDIAR [PATTANAIK,J.] 745
is wholly erroneous and it could only mean that the rate was on multi slab A
basis. With these conclusions the Division Bench allowed the plaintiffs'
appeal and dismissed the defendant's cross-objection and hence the
present appeal by the special leave.
Mr. V.R. Reddy, the learned Additional Solicitor General appearing
for the appellants contended that the hand written portion in the plaintiffs
letter Exhibit P-1 dated 11.7.1978 which was enclosed to the tender form
Exhibit P-2 is nothing but a subsequent interpolation inasmuch as neither
there is any signature either of the plaintiff or of the receiving officer on
the same and further it was really astonishing that though the tender was
submitted on 12.7.1978 but according to the plaintiff an attested copy of C
the letter could be obtained from the departmental officer on 11.7.1978.
Mr. Reddy further argued that the acceptance of the tender by the con
tractor clearly indicates that it was on single slab basis as the nute to the
same states "only one rate should be quoted for various lengths and sizes
and not different rates for different lengths". Mr. Reddy further urged that D
the very fact that the plaintiffs did not submit any bills till the end of the
contract period and started .to submit the bills during the extended period
of the contract would indicate that with an obvious illegal design the bills
were not being submitted in time. Repelling the reasonings advanced by
the Division Bench of the High Court Mr. Reddy urged that passing of
some bills by some of the Superintending Engineers on multi slab basis is E
not determinative of the terms and conditions of the contract particularly
when the contract is a written one and consequently the Division Bench
erred in law that the contract was on multi slab basis.
We find sufficient force in each of the contentions advanced by th.e F
learned counsel for the appellants.
Mr. Sivasubramanaim, the learned senior counsel appearing for the
respondents, repelling the contentions advanced by Mr. Reddy urged that
there was no issue at all on the question as to whether hand written portion
was subsequently inserted with the connivance of the officers of the Board G
·and therefore it would not be appropriate for this Court to interfere with
the same at this stage. The learned counsel also contended that the very
admission of DW-1, one of the witnesses of the defendants to the effect
that after submission of the tender, discussions were made with the con
tractor and the contractor eXplicitely expressed to have the work done on H
746 SUPREME COURT REPORTS {l996J SUPP. 1 S.C.R.
multi slab basis, clinches the matter and it is not open for the defendants
to give a go bye to the said admission of the witness. The learned counsel
also urged that the defendants in fact accepted and acted on multi slab
basis as is apparent from the letter Exhibit P-39 dated 18.4.80 from the
Superintending Engineer, General Construction Circle/South. Tirunelvalli
to the Chief Engineer, Materials Management, whereunder not only the
Superintending Engineer has candidly admitted that the system of payment
of multi slab basis has been in vogue in several circles but also stated that
the single slab system will not give a workable practical solution. Learned
counsel lastly urged that the single slab system is on the face of it wholly
unreasonable and to SU$lain the said argument placed before us certain
calculations made in different documents. We arc unable to persuade
ourselves to agree with the contentions advanced by the learned counsel
for the respondents.
At the outset it must be borne in mind that the agreement between
the parties was written agreement and therefore the parties are bound by
the terms and conditions of the agreement. Once a contract is reduced to
writing, by operation of Section 91 of the Evidence Act it is not open to
any of the parties to seek to prove the terms of the contract with reference
to some oral or other documentary evidence to find out the intention of
the parties. Under Section 92 of the Evidence Act where the written
instrument appears to contain the whole terms of the contract then parties
to the contract are not entitled to lead any oral evidence to ascertain the
terms of the contract. It is only when the written contract does not contain
the whole of the agreement between the parties and there is any ambiguity
then oral evidence is permissible to prove the other conditions which also
must not be inconsistent with the written contract. The case in hand has to
be adjudged bearing in mind the aforesaid principles and the plaintiffs
being conscious of this position along with the tender appended a letter
and in that letter inserted terms bv writing in ink to establish the case that
the acceptance of the plaintiffs' tender would tantamount to lhe acceptance
to the terms contained in the letter in which there was insersion is writing
G to the effect that it was on multi slab basis. It is in this context the question
whether such hand written portion was originally there or was subseqnently
inserted assumes great significance. We are unable to accept the stand
taken by the learned counsel for the respondents that there was not such
issue on this question inasmuch as this question was considered by the
learned Trial Judge while discnssing Issue No. 1 on the basis of evidence
T.N.ELECTRICITYBD.v. N.R. REDDIAR [PATTANAIK,J.] 747
laid and the Trial Judge had given a finding in favour of the plaintiffs. The A
said finding, however, on the face of it appears to us to be wholly unsus
tainable. As has been stated earlier there was no signature either by the
persons submitting the tender or by the persons receiving the same on the
h•nd written portion of the letter. The learned Trial Judge had noticed that
the certified copy which was issued by the Board on 11. 7.1978 of the
aforesaid letter clearly contains the hand written portion and therefore he
came to the conclusion that the hand written portion was there at the time
of submission of the tender. The tender itself was submitted on 12.7.1978
and we fail to understand how the Board could grant a certified copy of
the letter on 11.7.1978 when the plaintiffs' case itself is that along with the
tender he had appended the letter in question. On this ground alone it can C
be safely held that hand written portion in Exhibit P-1 was not there at the
time of submission of the tender but was subsequently inserted obviously
with the connivaces of the officers of the Board. The Board in its rejoinder
affidavit filed in this Court has stated that the attested copy was actually
received on 28.12.1978, much later than the finalisation of the tenders and D
agreement and in order to build up a case the aforesaid interpolation has
been made. In the facts and circumstances of the present case the aforesaid
stand of the Board appears to us to be wholly justified and at any rate we
have no hesitation to come to the conclusion that the hand written portion
in Exhibit P-1 was not there initially and has been inserted subsequently.
The main basis of the plaintiffs' case on which a multi slab rate was claimed E
therefore fails. The written agreement between the parties nowhere indi
cates that the rate to be paid to the plaintiffs was on multi slab basis. and
the terms and conditions of the written contract is not susceptible of such
a construction.
It is no doubt true that DW-1 a witness of the defendants in his
evidence had admitted that after submission of tender there was certain
discussions between the contractor and the authorities and in that discus-
sion contractor had expressed to charge for the job on multi slab basis and
same was accepted by the authorities. We are afraid a decree cannot be
granted in favour of the plaintiffs on the aforesaid statement since the G
·contract in hand was a written one. There is no document whatsoever in
support of the aforesaid. so called after tender discussion and the accep
tance of the terms in the said discussion to the effect that rate would be
charged on multi slab basis. Then again if the plaintiff had appended the
letter to the tender indicating that he would be charging on mnlti slab basis H
748 SUPREME COURT REPORTS [1996[ SUPP.1 S.C.R.
there was no occasion to have any after tender discussion or to raise the
issue of rate being accepted on multi slab basis. The so called statement
of DW-1 therefore is wholly unacceptable and in the eye of law also cannot
be taken into account to vary the terms of the written contract. The
Division Bench of the High Court committed obvious error in allowing
variance of the terms of written contract relying upon such statement of
DW-1 and granted the decree on multi slab basis.
The only other question which survives for consideration is whether
the conduct of some of Superintending Engineers in passing some of the
bills on multi slab basis can be pleaded as an estoppcl against the defen
dants and can form the basis of plaintiffs' case. The answer to this question
must be in the negative. It transpires that some of the Superintending
Engineers passed some of the bills on multi slab basis and further when
complaints were received and the matter was investigated into by vigilance
to absolve the concerned officers from liability, a recommendation has
D been made to grant the rate on multi slab basis. But such a recommenda
tion or such passing of bills on one count or multi slab basis cannot be
construed to have conferred a right on the plaintiffs to get the payments
on multi slab basis, until and unless it is provided by the plaintiff that the
defendants agreed under the written contract to pay on multi slab basis.
The plaintiffs have utterly failed to establish the same. A particular officer
E for various reasons may pass a bill on multi slab basis or a contractor may
be able to get one of his bills passed at a rate other than the rate given in
written contract in connivance with the passing authority. But when a
dispute arises and the matter comes to court for adjudication no decree
can be granted to the plaintiffs on that basis and the plaintiffs would be
F required to establish that the defendants in written contract agreed to grant
the rate on multi slab basis. That has not been establish in the case in hand.
Therefore, in our considered opinion the Division Bench of the High Court
wholly erred in law in allowing the plaintiffs' appeal and granting that
decree accepting plaintiffs' claim that the rate has to be paid on. multi slab
basis. In the aforesaid premises the impugned judgment and decree of the
G Division Bench is set aside and that of the learned Single Judge is affirmed.
This appeal is allowed, but in the circumstance-' there will be no order as
to costs.
R.A. Appeal allowed.