Lata Construction and Ors. v. Dr. Rameshchandra Ramniklal Shah and Anr.
S. SAGHIR AHMAD, J. This appeal is directed against the judgment
and order dated 22nd November, 1995 passed by the National Consumer
Disputes Redressal Commission, New Delhi (for short, 'the National
E Commission').
The respondents had approached the Commission with the complaint
that the appellants who were developers and had promised, under a written
agreement dated 27. l.1987, to provid~ a flat to them, had failed to do so and,
therefore, they were guilty of "deficiency in service." It was indicated in the
F complaint that the respondents who were, at that time, in Libya and wanted
to settle in India, had entered into an agreement. dated 27. l .1987 with M/s.
Lata Construction, the appellant No. I, which stipulated that the appellants
would develop, construct and hand over possession of flat No. AG-2 on the
ground floor with. an area of 670 sq. ft. situated in a building named
"Madhusudan", on Plot No. 138, T.P.S. 11 and C.T.S. No. 1166 and 1166(1) in
G Vile Par'te, Bombay 400057. It was indicated that the appellants had earlier
entered into a developme~t agreement on 9.12.1985 with the owners in respect
of the said property to develop, construct and to sell flats in the proposed
building which was to be constructed on ownership basis. On 27th of January,
1987, the respondents had paid a sum of Rs. 3,38,000 to the appellants in cash
H but without any receipt and a sum of Rs. 32,000 by cheque against receipt.
' ..... •
I.
~
I
/
LATA CONSTRUCTION v. DR. R.R. SHAH [S. SAGHIR AHMAD, J.] 417
The respondents also paid to the appellants on various dates, as and when A
demanded by them, a further sum of Rs. 2,00,000 against receipt. In June, 1988
when the respondents returned from Libya, they requested the appellants to
deliver, on payment of balance amount of sale consideration, possession of
the flat to them as the construction of the building was complete but the
appellants refused to accept the payment and deliver possession on the plea
that the building was still under construction particularly as the electricity, B
plumbing, tiling and fencing work was in progress. The appellants, however,
assured the respondents that as and when the building would be completed
in all respects, they would accept the balance amount of sale consideration
and deliver possession to them. In April, 1990, when the respondents again
came back from Libya on a short visit to India and visited the building, they C
found that the flat was locked and outside the main door of the flat, a name
plate of"Indira Joshi" had been put up. The respondents returned from Libya
in January, 1991 and when they demanded the possession of the flat, the
appellants expressed their inability to give possession of the flat to the
respondents in compliance of the agreement dated 27. l.1987. The appellants, D
however, entered into a fresh agreement with the respondents on 23.2.1991
agreeing to pay to the respondents a sum of Rs. 9,51,000 in lieu of the flat
in three instalments on or before 30.5.1991 as under:-
l. Rs. 3,00,000
2. Rs. 3.00.000
3. Rs. 3,51,000
on or before 20.3.1991
on or before 20.4.1991
on or before 30.5.1991
The respondents had entered into a fresh agreement with the appellants ·
without prejudice to their rights under the earlier agreement dated 27. l .1987.
Since the appellants did not honour the commitments under both the F
agreements, the respondents approached the National Commission which,
decreed the claim of the respondents for a sum of Rs. 9 ,51,000 together with
interest at the rate of 18% per annum with effect from 23 .2.1991 till the date
of payment. Another sum of Rs. 1,00,000 was allowed as compensation for
pain and suffering undergone by the respondents. The Commission also
allowed a sum of Rs. l 0,000 to the respondents as costs of the proceedings. G
Learned counsel appearing on behalf of the appellants has contended
that the claim instituted by the respondents before the Commission was
beyond time inasmuch as it was filed beyond the period of two years prescribed
under Section 24-A of the Consumer Protection Act, 1986 (for short, 'the
Act'). It is contended that since the respondents had entered into a fresh H
A agreement with the appellants under which the entire amount of Rs. 9,51,000
·had to be paid on or before 30th of May, 1991, the respondents, if the amount
was not paid, could have instituted the claim petition before the Commission
within the period ofHmitation starting from 31.5.1991, and since the claim was
filed in July, 1993, it was clearly beyond time. This plea has been negatived
B by the Commission on the ground that since the right under the agreement
of 1987 had not been given up by the respondents, there was a continuing
cause of action running against the appellants and the claim was, therefore,
not beyond time.
A perusal of the agreement dated 23rd of February, 1991 would show
C that it was specifically stipulated therein that the rights under the agreement
dated 27th of January, 1987 would remain unaffected. It was for this reason
that in the claim petition filed before the Commission, it was clearly mentioned
that their rights under the agreement dated 27th of January, 1987 as also those
under the agreement dated 23rd of February, 1991 may be enforced. It was
also specifically mentioned in the second agreement that the first agreement
D of 1987 would be treated as terminated only on full payment of the stipulated
amount of Rs. 9,51,000 to the respondents. Sine~ the rights under the agreement
of 1987 had not been given up and the appellants were constantly under an
obligation to provide a flat to the respondents ar{d deliver possession thereof
to them, the Commission rightly treated "cause of action" to be a "continuing
E. cause of action" and came to the right conclusion that the claim was not
beyond time.
Moreover, under the terms of the agreement dated 23rd of February,
1991, it was stipulated that if the entire amount of Rs; 9,51,000 was not paid
by 30th May, 1991, the whole of the amount would become payable at once
F and it would be open to the respondents to claim payment of full amount
together with interest after giving seven days' notice to the appellants. It was
further stipulated that in case of default, the amount already paid by the
appellants shall stand forfeited. Since the whole of the amount had not been
paid to the respondents who could recover the whole of the amount together
with interest from the appellant on giving seven days' notice, the rights under
G the old agreement did not come to an end and they could legally claim specific
performance of that agreement for a flat being provided to them. Their claim
was, therefore, not barred by time.
It was next contended that the agreement dated 27 .1.1987 having been
substituted by a fresh agreement dated 23 .2.1991, under which the respondents
H themselves had agreed to receive Rs. 9,51,000 as compensation for the flat not
LATA CONSTRUCTION v. DR. R.R. SHAH [S. SAGHIRAHMAD, J.] 419
having been provided to them under the earlier agreement, they could only A
approach the civil court for recovery of that amount but could not legally
institute the claim petition before the Commission for compensation on the
ground of "deficiency in service."
This plea has been rejected by the National Commission by placing
reliance upon the decision of this Court in Lucknow Development Authority B
v. MM Gupta, [1994] l SCC 243.
We have already held above _that the rights under the earlier agreement
of 1987 were kept alive even after the second agreement. The rights under the
first agreement had not been given up and there was no substitution of the C
earlier agreement in its entirety by the new agreement.
We may, at this stage, refer to the provisions of Section 62 of the Indian
Contract Act which provides as under :
"If the parties to a contract agree to substitute a new contract for it, D
or to rescind or alter it, the original contract need not be performed."
This provision contains the principle of "Novation" of contract.
One of the essential requirements of 'Novation'; as contemplated by
Section 62, is that there should be complete substitution of a new contract E
in place of the old. It is in that situation that the original contract need not
be performed. Substitution of a new contract in place of the old contract
which would have the effect of rescinding or completely altering the terms of
the original contract, has to be by agreement between the parties. A substituted
contract should rescind or alter or extinguish the previous contract. But if the
terms of the two contracts are inconsistent and they cannot stand together, F
the subsequent contract cannot be said to be in substitution of the earlier
contract.
In the instant case, the rights-under the original contract were not given
up as it was specifically provided in the subsequent contract that the rights G
under the old contract shall stand extinguished only on payment of the entire
amount of Rs. 9,51,000. Since the amount was not paid by the appellants as
stipulated by the subsequent contract, the rights under the original contract
were still available to the respondents and they could legally claim enforcement
of those rights. Obviously, under the original contract, the appellants were
under an obligation to provide a flat to the respondents. This right would H
420 SUPREME COURT REPORTS [1999) SUPP. 1 S.C.R.
A come to an end only when the appellants had, in pursuance of the subsequent
contract, paid the entire amount of Rs. 9 ,51,000 to the respondents. Since they
had not done so, the respondents could legally invoke the provisions of the
earlier contract and claim before the Commission that there was "deficiency
in service" on the part of the appellants.
B We may also point out that the appellants had filed only a written
statement before the Commission but had not produced any evidence in
support of their pleas. Even an affidavit in support of what they had stated
in the written statement was not filed before the Commission. Their case, thus
was not supported by any evidence and the Commission, in the facts and
C circumstances of the case, was justified in decreeing the claim of the
respondents.
Learned counsel for the parties have stated before us that in terms of
the judgment passed by the Commission, the entire amount due from the
appellants has already been paid to the respondents including interest at the
D rate of 18 per cent per annum on the principal amount ofRs.9,51,000. That
being so, we are not prepared to entertain the plea of the appellants that the
decree passed by the Commission in respect of Rs.1 lakh as compensation
on account of the pain and suffering undergone by the respondents may be
reversed.
E We find no merit in the appeal and the same is accordingly dismissed
with no order as to costs.
R.C.K. Appeal dismissed.
-· \.