State of Rajasthan and Anr. v. M/S. Nav Bharat Construction Co.
SHAH, J. CA. No. 8JJ5 of 2001 @ S.L.P. (C) No. 7192 of 2001. G
Leave granted.
Learned Senior Counsel Mr. Ashwani Kumar appearing for the appellant
contended that the judgment and decree passed by the High Court confirming H
352 SUPREME COURT REPORTS (2001] SUPP. 5 S.C.R.
A the award made by the arbitrator is on the face of it illegal because :
(a) Arbitrator has failed to consider counter-claim.
(b) second reference to arbitrator was not maintainable under Order
2 Rule 2 CPC, and
(c) the arbitrator has awarded interest despite the contrary condition
in the agreement.
As against this, Mr. G.L. Sanghi learned senior counsel for the respond
ent as well as the respondent who is appearing in person submitted that in the
written statement, counter-claim or set off was neither pleaded nor proved by
the appellant before the arbitrator. He also contended that in case of claims
raised by the respondent after preparation of final bill, there is no question of
application of Order 2 Rule 2 CPC as rightly held by the arbitrator and the
Courts below. For the contention based on clause 23 of the Agreement, it is
D submitted that the appellant never contended before the arbitrator that clause
23 provides for non-payment of interest in such cases. It is pointed out that
neither befcre the arbitrator nor before the courts below, it was contended that
arbitrator had no authority to grant interest in view of clause 23. Only conten
tion which was raised with regard to grant of interest pendente lite for which
E reliance was placed on various decisions of this Court.
We would state that the respondent who is appearing in person has in the
alternative referred to the decision rendered by this Court in State qf U.P. v.
Harish Chandra & Co., [1999] l SCC 63 and submitted that similar clause is
interpreted by this Court and it is held that there is no such prohibition on
granting interest. He further pointed out that if such plea was raised, he would
have produced the necessary documentary evidence or the letters written by the
concerned officers and proved that interest was payable for wrongfully with
holding the amount due and payable.
G In our view, it has been rightly pointed out that in the written statement,
appellants have not claimed any set off or title counter claim for the alleged
amount due and payable by the contractor on the alleged ground that Account
ant General's Office has raised objection for payment of labour charges at
accelerated rate. In our view as no such set off or claim nor any counter claim
was filed by the appellant, arbitrator has rightly not considered the same which
' ,
STATE v. NA V BHARAT CONSTRUCTION CO. [SHAH, J.] 353
was sought to be raised after lapse of 4 years of reference. Further the High A
Court has noted that the learned Additional Advocate General was unable to
point out any legal basis to support the contention that arbitrator was required
to go into the counter-claim in the circumstances of the present case.
There is also no substance in the contention raised by Mr. Ashwani
Kumar, learned senior counsel for the appellant that the second reference was
barred by Order 2 Rule 2 CPC. As such the contention was not raised before
the High Court. In any case, the dispute with regard to the subsequent claims
arose after the first reference, that is, after the final bill was prepared and this
aspect is rightly dealt with by the Additional District Judge.
. c
Lastly, in the present case, the award passed by the arbitrator is reasoned
one. The contention raised by the learned counsel for the appellant that under
Clause 23 of the Agreement between the parties, contractor was not entitled
to recover any interest on delayed payment was neither raised before the
arbitrator, the District Court or before the High Court. This question depends D
upon the evidence which may be led by the parties as well as interpretation of
clause 23 by the parties and the arbitrator. The parties have understood that
there is no bar on granting interest on delayed payments. It appears that no such
contention was raised on behalf on behalf of the State of Rajasthan. In this view
of the matter, it cannot be held that arbitrator has committed any error apparent E
on the face of the record or has misconducted himself in passing the impugned
award. It is settled law that scope for setting aside the award is limited to the
grounds available under the Arbitration Act which have been well defined by
long line of decided cases. In this view of the manner, it is not necessary for
us to consider the contention of the contractor that similar clause is interpreted
by this Court in Harsish Chandra and Company's case (supra) and it is held
that there is no bar on granting iilterest. In our view as the contention was not
raised before the arbitrator or at any stage thereafter, it is not necessary for us
to deal with or <lecide the same in this appeal.
However, considering the dispute involved and overall circumstances of G
the case. we modify the award qua the rate of interest and reduce the same at
the rate of 6% per annum. The arbitrator in paragraph 2 l.8.1. of the award has
granted interest on the principal amount of claims no 1 to 8 from l.7.1990 to
30.4.1998 and 10 to 18 from 29.4.1991 to 30.4.1998 at the rate of 18% and
the District Court has awarded interest at the rate of 15% from the date of H
A decree. That part of the award and decree is modified and it is held that
respondent-claimant is entitled to recover the said amount with interest at the
rate of 6% only. The appeal is disposed of accordingly. Parties to bear their
own cost of litigation all throughout.
B S.L.P. (C) No. 6172 of 2001
In view of the aforesaid order, the S.L.P. filed by the contractor for
enhancement of interest rate from 15% to 18% would not survive and is
dismissed.
N.J. Appeal disp?sed of.