Dakshin Haryana Bijli Vitran Nigam Ltd v. M/S Paramount Polymers Pvt. Ltd.
P.K. BALASUBRAMANY AN, J. I. Leave granted.
2. Mis L.L.C. Steels Pvt. Ltd. was a consumer of electricity from the
appellant, a distributing company established in the place of the State Electricity
Board. It allegedly fell into arrears to the tune of Rs. 64,23,6951-towards
consumption charges of electrical energy including interest and other incidental D
charges. Because of the failure to pay the consumption charges, the power
to the undertaking was disconnected on 6.4.1998. Mis L.L.C. Steels Pvt. Ltd.
had also borrowed amounts from the Haryana Financial Corporation and had
mortgaged the undertaking to the Financial Corporation. In exercise of power
under Section 29 of the State Financial Corporations Act, 1951, the undertaking E
was taken over by the Financial Corporation and advertised for sale. In the
advertisement, the undertaking was offered for sale on "as is where is basis".
The first respondent herein bid the undertaking and its bid was accepted.
Possession was given by the Financial Corporation to the first respondent on
22.4.1999.
3. On 27.11.2001, the appellant-Company decided to incorporate a term
in the Terms and Conditions of Supply of electrical energy by providing that
in cases where a consumer had defaulted in paying electrical charges and
there had been a consequent disconnection of supply, no fresh connection
in respect of the premises would be given to a purchaser unless the purchaser
cleared the amount that was left in arrears by the consumer whose undertaking G
had been purchased. It is seen that the first respondent applied for a connection
on 1.1.2002. The appellant-Company took the stand that unless the first
respondent paid the amount outstanding against Mis L.L.C. Steels Pvt. Ltd.,
the prior consumer, no fresh connection could be given to the first respondent.
Since the first respondent was not willing to comply, the application of the H
A first respondent was rejected. The first respondent thereupon filed a suit,
Civil Suit No. 23 of 2002 in the Court of Civil Judge (Senior Division},
Faridabad, seeking to restrain the appellant-Company from interfering with the
use of generators by the first respondent for generating electricity for its use
and for a mandatory injunction directing the appellant-Company to give a
B fresh electric connection to the first respondent without insisting on the
clearing of the dues of the prior owner of the premises. Even while the suit
was pending, the first respondent filed a Writ Petition, Civil Writ Petition No.
5350 of 2002 in the High Court of Punjab and Haryana praying for the issue
of a writ of certiorari to quash the circular dated 27 .11.200 I introducing a
condition for fresh connection only on payment of the dues of the previous
C consumer of electricity in the premises concerned, for a writ of prohibition
restraining the appellant from removing the generators installed by the first
respondent in the premises, for a writ of mandamus directing the appellant to
provide electric connection temporarily to enable the first respondent to run
its factory during the pendency of the Writ Petition and for other incidental
reliefs. The scrutiny of the prayers made in the Writ Petition shows that there
D was no prayer for a writ of mandamus directing the appellant-Company to
provide a permanent electric connection to the first respondent. The appellant
resisted the Writ Petition submitting that the first respondent having already
approached the Civil Court for relief, the Writ Petition was not maintainable.
It was further contended that the Circular dated 27 .11.200 I sought to be
E challenged in the Writ Petition was issued in exercise of power under Section
49 of the Electricity (Supply) Act, 1948 by the competent authority thereunder
and that incorporation of such a condition in the Terms and Conditions of
Supply was statutory in nature and was perfectly valid. It was also pleaded
that the fact that a substantial amount was due to the appellant from Mis
L.L.C. Steels Pvt. Ltd. was brought to the notice of the Financial Corporation
F and a request was made that the amount of Rs. 60,48,504/-should also be
recovered when the sale was effected by it. The sale by the Financial
Corporation was on "as is where is basis" and hence the first respondent was
liable for the dues run up in respect of the premises by the prior consumer.
It was submitted that there was no merit in the Writ Petition and it was liable
G to be dismissed.
4.Almost the whole case of the first respondent in the Writ Petition was
based on the decision of this Court in Mis lsha Marbles v. Bihar State
Electricity Board, [ 1995] I S.C.R. 84 7. In that decision, this Court held that
in the absence of there being a charge over the property and the premises
H comes to be owned or occupied by the auction purchaser and that auction
DAKSHIN HARYANA flULIVITRAN NIGAM LTD 1· PARAMOUNT POLYMERS !'\'T. LTD. IBALASlJBRAMANYAN. J.164 l
purchaser seeks supply of electrical energy by way of a fresh connection, he A
cannot be called upon to clear the past arrears as a condition precedent for
the fresh connection or supply. What mattered was the contract entered into
by the erstwhile consumer with the Electricity Board. The Electricity Board
could not seek the enforcement of the contractual liability of the prior consumer
against the third party, the purchaser. Even the bona fides of the sale may
not be relevant. It was impossible to impose on the purchaser a liability which B
was not incurred by him. The auction purchaser came to purchase the property
after disconnection but it could not be understood as a consumer or occupier
within the meaning of the Electricity Act until a contract was entered into.
Though, it was stated that electricity is public property and law, in its majesty,
benignly protects public property and it behoves everyone to respect public C
property, since the law, as it stood, was inadequate to enforce the liability of
the previous contracting party against the auction purchaser who was a third
party and was in no way connected with the previous owner/occupier, the
liability could not be enforced against the purchaser or the clearing off of the
earlier dues made a condition precedent for grant of a fresh connection. The
answer of the appellant-Company to the argument based on this ratio of /sha D
Marbles (supra) was that on 27.11.200 I, the appellant-Company had
incorporated a specific term in that regard in the Terms and Conditions of
Supply and since there was no infirmity or invalidity attached to such a
condition, the ratio of the decision in Is ha Marbles (supra) would not enable
the first respondent to ignore the condition specifically inserted in exercise E
of statutory power and consequently, no relief could be granted to the first
respondent unless that condition was also fulfilled by the first respondent.
5. The High Court did not go into the question of the validity or
otherwise of the amendment to the Terms and Conditions incorporated as
clause 21 A on 27 .11.200 I. The learned single judge accepted the argument F
on behalf of the first respondent that since there was no charge on the
premises for the electricity charges run up by M/s L.L.C. Steels Pvt. Ltd. and
the purchase by the first respondent was on 22.4.1999, the amendment
promulgated on 27.11.2001 could not be applied in the case of the first
respondent and that the appellant-Company was bound to provide the electric G
connection to the first respondent without insisting on the Terms and
Conditions introduced with effect from 27.11.200 I. The argument that what
was relevant was the date of the application for connection made by the first
respondent herein and the application was made after the amended term was
incorporated, was brushed aside stating that in the absence of any charge or
of contractual liability created against the auction purchaser, the liability H
642 SUPREME COURT REPORTS [2006) SUPP. 7 S.C.R.
A could not be fastened unless it is shown that on the date of transfer, the
auction purchaser was either bound by a statute or by a contract. The judge
also noticed that in another case where a transfer was effected in the year
2003, the appellant had conceded that the decision of the Supreme Court in
/sha Marbles (supra) applied and a different stand could not be taken in the
present case by the appellant. Thus, it was directed that the appellant release
B the power connec.tion to the first respondent expeditiously and not later than
30 days from the date of the judgment. The appellant filed an appeal. The
Division Bench of the High Court even without admitting the appeal and
without appreciating that some questions of importance do arise for decision
in the appeal dismissed the same by referring to the decision in /sha Marbles
C (supra) and stating that the amendment of the Terms and Conditions of
Supply could not be made applicable since the purchase by the first respondent
was prior to the introduction of condition 21 A and as legislation which
affected substantive rights are presumed prospective. The High Court also
relied heavily on the fact that in another case of disconnection and transfer
in the year 2003, the appellant had not taken up the stance it had taken up
D in the present case and had conceded that the decision in lsha Marbles
(supra) applied to that case. It is this dismissal that is challenged in this
appeal.
6. We may observe even at this stage that though the main contention
E raised on behalf of the first respondent was that the condition incorporated
on 27. I 1.2001 was not valid in the light of the ratio of the decision in /sha
Marbles (supra), that question has not been decided by the High Court. The
High Court has proceeded on the basis that there is no charge created on the
undertaking for the consumer's dues and consequently, the incorporation of
a condition on 27. I l.'2001 could not have operation in a case where the sale
F of the undertaking and purchase by the first respondent, were prior to the
date of the amendment. What is the effect of the first respondent applying
for a fresh connection only on I .1.2002 after the amendment was incorporated
was not considered properly. The terms incorporated were also not scrutinized.
The court proceeded on the basis that the relevant date was the date of
G purchase of the undertaking by the first respondent.
7. Even at the outset, learned counsel for the first respondent submitted
that the correctness of the decision in /sha Marbles (supra), which is a three
judge Bench decision, has been doubted by a Bench of two judges in Civil
Appeal Nos. 5312 and 5313 of 2005 and the appeals have been referred to a
H Bench of three judges and these appeals can also be so referred. But on
DAh:SlllN llAR,"ANA BULl\'ITRAN NIGAM Lto. r PARAMOUNT POLY~IERS P\T LTD IBALASUBRAM.o\NYAN. J.I 643
scrutinizing the order of reference, this is what we find recorded:
''Heard.
The basic question is whether electricity dues constitute a charge
on the property so far as the transferor or the transferee of the unit
are concerned.
Considering the importance of the issues involved, it would be
appropriate if the matters are heard by a three judge Bench. The
matters may be placed before Hon'ble The Chief Justice of India for
necessary directions."
On a scrutiny of the decisions of the High Court of Bombay giving rise to
those appeals, we find that the primary question in those appeals would be
the correctness of the view of the High Court that the Electricity Board had
no power to impose a condition that the purchaser of an undertaking will have
the obligation to clear the arrears of charges of the prior consumer. Of course,
incidentally the correctness of some of the observations in lsha Marbles D
(supra) may also be involved. Anyway, that aspect will also have to be borne
in mind while we consider the elaborate submissions made before us in this
appeal.
8. It appears to be appropriate to set down Clause 2 lA inserted in the
Terms and Conditions of Supply of electrical energy by the appellant with E
effect from 27.11.2001, which reads as under:
"21-A (a) When there is transfer of ownership or right of
occupancy of a premises, the registered consumer shall
intimate the transfer of right of occupancy of the premises F
within 15 days to the Assistant Engineer/ Assistant Executive
Engineer concerned. Intimation having been received, the
service shall be disconnected unless application for transfer
is allowed. If the transferee desires to enjoy the service
connection, he shall pay the outstanding dues, if any, to the
Nigam and apply for transfer of the service connection within G
30 days and execute fresh agreement and furnish fresh
security. New Consumer number shall be allotted in such
cases canceling the previous number.
(b) Reconnection or new connection shall not be given to
any premises where there are arrears on any account due to
the Nigam unless these are cleared in advance. If the new
owner/occupier/allottee remits the amount due from the
previous consumer, the N igam shall provide reconnection or
new connection depending upon whether the service remains
disconnected/dismantled as the case may be. The amount
so remitted will be adjusted against the dues from the
previous consumer. If the Nigam get the full or partial dues
from the previous consumer through legal proceedings or
otherwise, the amount remitted by the new owner/occupier
to whom the connection has been effected shall be refunded
to that extent. But the amount already remitted by him/her
shall not bear any interest.
(c) The above proposed provisions of clause 21-A(a) and (b)
shall be applicable to existing consumers also where
defaulting amount exists against premises occupied by such
consumer."
It is seen that the above amendment was also formally notified on 11.2.2002.
As we see it, a transferee of ownership or of right of occupancy of a premises
to which electrical connection had been given, is given the option to enjoy
the service connection already granted by paying the outstanding dues, if
E any, to the appellant and apply for transfer of service connection and obtain
the same by executing a fresh agreement and furnishing a fresh security. Sub
clause (b) provides that reconnection or new connection shall not be given
to any premises where there are arrears on any account to the appellant
unless the arrears are cleared in advance. It has to be noted that reconnection
F is related to the premises and arrears again is related to the premises. The
amount remitted by the transferee towards arrears are to be adjusted against
the dues from the previous consumer. But it is provided that if meanwhile
the appellant is enabled to recover the amount from the transferor or consumer,
the amount remitted by the transferee-consumer is to be r.:funded, but
without interest. Sub-clause (c) provides that provisions contained in sub-
G clauses (a) and (b) of clause 21A shall be applicable to an existing consumer
also where defaulting amount exists against the premises occupied by such
consumer.
9. According to us, the High Court has gone wrong in holding that
this newly inserted clause 21 A of the terms and conditions was not applicable
H to the first respondent. It is true that the sale of the undertaking at the
OAh:.SH II\ HAR YAN.\ Bl'LlVlTRAN NIG!\.M LTD 1'. PARAMOUNT POLYMERS PVT LTD. IBALASUBRAMANYAN. J.I 645
instance of the Financial Corporation to the first respondent was prior to A
27.11.2001 and possession was also given to the first respondent on 22.4.1999,
prior to the insertion of clause 21A. But going by clause 21A(c) it is clear
that even if the view taken by the High Court that the. relevant date is the
date of sale in favour of the first respondent is accepted, even then, the
appellant would be entitled to apply sub-clause (b) of clause 21 A to the first
respondent as an existing consumer, since defaulting amount existed against
the premises occupied by the first respondent. We are also not in a position
to agree with the High Court that the relevant date is the date of sale of the
undertaking by the Financial Corporation to the first respondent. The
insertion of clause 2 lA was circulated by the communication dated 27.11.2001
and it was subsequently followed by the formal notification in terms of C
Section 49 of the Supply Act read with Section 79(j) of that Act. The first
respondent having applied for a fresh connection only on 1.1.2002, the
application would be governed by the terms and conditions including the
term inserted on 27.11.2001, as subsequently formally notified. In the writ
petition filed on 27.2.2002 in that behalf, the court could not have come to
the conclusion that the application made by the first respondent was not D
governed by the amended terms and conditions including clause 2 lA thereof.
It is not as if the first respondent was an ignorant party. Before submitting
its bid to the Financial Corporation the first respondent would certainly have
inspected the premises and could have come to know that power connection
to the premises had been snapped and this information should have put it E
on reasonable enquiry about the reasons for the power disconnection leading
to the information that the previous owner of the undertaking or consumer
was in default. Moreover, the appellant had clearly written to the Financial
Corporation even before the sale was advertised by it, informing it that a sum
of Rs.64,23,695/- was due towards electricity charges to the appellant and
when selling the undertaking, that amount had to be provided for or kept in F
mind. Therefore, any reasonable enquiry by the first respondent as a prudent
buyer would have put it on notice of the subsistence of such a liability. The
sale was also on 'as is where is' basis. On our interpretation of clause 2 IA
of the Terms and Conditions of Supply as inserted with particular reference
to clauses (b) and ( c) thereof, we are of the view that the said clauses clearly G
applied to the first respondent when it made an application on 1.1.2002
seeking a fresh connection for the premises.
I 0. We find that the High Court has also not referred to the Haryana
Government Electrical Undertakings (Dues Recovery) Act, 1970 which came
646 SUPREME COURT REPORTS (2006] SUPP. 7 S.C.R.
A into effect on 27.10.1970. The said Act enabled the Electricity Board, of which
the appellant is the successor, to recover the dues to the Board on account
of consumption of electrical energy and other charges as defined in that Act
to be recovered as an arrear of land revenue notwithstandino anythino
"' "'
contained in any other law or instrument or agreement to the contrary. We
may set down Section 6 of that Act herein:
"6. Recovery of dues, etc., if not paid If the aggregate amount of the
various dues, penalty and costs mentioned in the notice of demand
served under Section 4 is not deposited with the prescribed authority
within sixty days of the date of such service or such extended period
as the prescribed authority may from time to time allow, the debtor
shall be deemed to be in default in respect of such amount and the
same shall be recoverable as an arrear of land revenue, notwithstanding
anything contained in any other law or instrument or agreement to the
contrary.
(2) For the purpose of such recovery, the prescribed authority may
forward to the Collector a certificate under his signature in the
prescribed form stating the amount and details of the demand and the
name and description of the debtor in default and the Collector shall
on receipt of such certificate, proceed to recover from the debtor the
amount of the demand as if it were an arrear of land revenue."
11. The recovery of arrears ofland revenue is provided for in the Punjab
Land Revenue Act, 1887. Chapter 6 thereof deals with recovery. Section 61
provides that the entire estate and the land owner shall be liable for the land
revenue for the time being assessed on the estate. Section 62 provides as
further security that the land revenue payable in respect of a holding shall
F be the first charge upon rents, profits and produce thereof. Section 67 deals
with the modes of recovery of arrears of land revenue. That section
contemplates recovery, inter a/ia, by way of arrest and detention of the
person who is liable to pay the land revenue; by distress and sale of his
movable property and uncut or ungathered crops; by transfer of the holding
G in respect of which the arrears is due; by attachment of the estate or holding
in respect of which the arrears is due; by sale of that estate or holding or by
proceeding against other immovable property of the defaulter. Under Section
72 of the Act, the Collector can takeover the management of the estate or
effect attachment thereof and under Section 7 5 he can sell the estate itself for
recovery with the previous sanction of the Commissioner. Thus, the amount
-
DAl-.:Sl~[(I..' HARY A.~A BULl\'ITRAN \!lG.\M LTD. ,._ PAR.A.~10UNT POLYMERS P\'T_ LTD IBALASliBRAMANYAN. J.J 64 7
due from the prior owner of the undertaking or consumer could be recovered A
by proceeding against the undertaking even in the hands of the transferee
if we go by the relevant provisions of the above two enactments applicable
to recovery of dues by the appellant or its predecessor, the Electricity Board.
If in the context of such provisions. the appellant introduced a term in the
Tenns and Conditions of Supply in the case of a transfer that the transferee
has to discharge the prior amounts due in respect of that undertaking by the B
prior consumer. could it be said that it had no authority to do so or that the
provision is not a reasonable one in the interests of safeguarding the rights
of the appellant?
12. We must notice that the High Court did not consider the effect of C
the above enactments relating to recovery of dues. Counsel for the first
respondent submitted that no such contention was raised in the High Court
and even in this petition for special leave to appeal such a contention is not
raised. But considering that the contention is based on statutes enacted by
the State Legislature and are in force, the arguments cannot be ignored by
merely stating that they were not put forward before the High Court, since D
they have been put forward before us at the time of arguments. At best the
first respondent could plead that it did not get a proper opportunity to meet
this contention in the circumstances of this case.
13. We must observe that the decision in lsha Marbles (supra) is by
itself not an answer to the validity of clause 21A of the terms and conditions E
inserted by notification. Under section 49 of the Supply Act, the licensee
or rather, the Electricity Board, is entitled to set down tenns and conditions
for supply of electrical energy. In the light of the power available to it, also
in the context of Section 79(j) of the Supply Act, it could not be said that the
insertion of clause 21 A into the Tenns and Conditions for supply of electrical F
energy is beyond the power of the appellant. It is also not merely contractual.
This Court in Mis Hyderabad Vanaspati Ltd. v. Andhra Pradesh State
Electricity Board and Ors., [1998] 2 S.C.R. 620 has held that the Terms and
Conditions for Supply of Electricity notified by the Electricity Board under
Section 49 of the Electricity (Supply) Act are statutory and the fact that an
individual agreement is entered into by the Board with each consumer does G
not make the terms and conditions for supply contractual. This Court has
also held that though the Electricity Board is not a commercial entity, it is
entitled to regulate its tariff in such a way that a reasonable profit is left with
it so as to enable it to undertake the activities necessary. If in that process
in respect of recovery of dues in respect of a premises to which supply had H
A been made, a condition is inserted for its recovery from a transferee of the
undertaking, it cannot ex facie be said to be unauthorized or unreasonable.
Of course, still a court may be able to strike it down as being violative of the
fundamental rights enshrined in the Constitution of India. But that is a
different matter. In this case, the High Court has not undertaken that
exercise.
14. The pos1t1on obtaining in lsha Marbles (supra) was akin to the
position that was available in the case on hand in view of the Haryana
Government Electrical Undertakings (Dues Recovery) Act, 1970. There was
no insertion of a clause like clause 21 A as in the present case, in the Terms
C and Conditions of Supply involved in that case. The decision proceeded on
the basis that the contract for supply was only with the previous consumer
and the obligation or liability was enforceable only against that consumer and
since there was no contractual relationship with the subsequent purchaser
and he was not a consumer within the meaning of the Electricity Act, the dues
of the previous consumer could not be recovered from the purchaser. This
D Court had no occasion to consider the effect of clause like clause 21 A in the
Terms and Conditions of Supply. We are therefore of the view that the
decision in lsha Marbles (supra) cannot be applied to strike down the condition
imposed and the first respondent has to make out a case independent,_on the
ratio of lsha Marbles (supra), though it can rely on its ratio if it is helpful,
E for attacking the insertion of such a condition for supply of electrical energy.
This Court was essentially dealing with the construction of Section 24 of the
Electricity Act in arriving at its conclusion. The question of correctness or
otherwise of the decision in Is ha Marbles (supra) therefore does not arise in
this case especially in view of the fact that the High Court has not considered
the question whether clause 21 A of the terms and conditions incorporated is
F invalid for any reason.
15. In the light of what we have stated above we think that the proper
course to adopt is to set aside the judgments of the learned Single Judge and
that of the Division Bench and remit the writ petition filed by the first
respondent to the High Court for a fresh decision in accordance with law.
G The first respondent would be free to amend its writ petition including the
prayers therein and in the case of such an amendment the appellant would
be entitled to file an additional statement in opposition. The writ petition will
be considered afresh by the High Court in the light of what we have stated
above.
-
DAKSHIN HARYANA BUL.l\llTRAN NJGAl\I LTD 1. rARAMOUNT POLYMERS PVT. LTD. IBAL-\'"l'RI{ \I .\'<YAN. J.1649
16. It is seen that after the High Court allowed the writ petition, the A
connection was restored to the first respondent in obedience to the writ, even
though subsequently, this Court stayed the operation of the judgment of the
High Court by its order dated 5.7.2006. It is now brought to our notice that
a fresh connection has been provided to the first respondent in the light of
the direction in the judgment under appeal without collecting the arrears that
were due from M/s L.L.C. Steel Pvt. Ltd. Strictly, in view of the fact that we B
have set aside the judgment of the High Court, the first respondent should
lose the benefit of the fresh connection. But considering that the first
respondent is an industrial undertaking and taking note of the plea that
investments have been made by it to make the unit workable, we think that
it will be appropriate to direct the first respondent to deposit a portion of the C
amount in arrears as a condition for continuance of the supply to it by the
appellant on payment of regular monthly bills as per the terms and conditions
between the parties. We, therefore, direct that if the first respondent pays
to the appellant, without prejudice to its contentions in the writ petition, a
sum of Rs. 25 lakhs (rupees twenty five lakhs) within a period of six weeks
from today, the fresh connection given to the first respondent will not be D
disconnected by the appellant, until the writ petition is disposed of afresh by
the High Court pursuant to this order of remand. In case the High Court
accepts the challenge of the first respondent to clause 21 A as inserted in the
terms and conditions of supply, the appellant will refund the sum of Rs. 25
lakhs with six per cent interest thereon from the date of payment by the first E
respondent till the date of its return by the appellant. In case the writ petition
is dismissed by the High Court, the appellant would be entitled, at the volition
of the first respondent, to adjust the amount of Rs. 25 lakhs towards the dues
claimed from the previous consumer, Mis L.L.C. Steel Pvt. Ltd. and maintain
the fresh connection given to the first respondent on it fulfilling its obligations
in terms of clause 2IA and act on that basis. If the first respondent, does F
not desire to have a power connection based on clause 21 A of the Terms and
Conditions of Supply, the appellant will refund the sum of Rs. 25 lakhs to the
first respondent without interest within two months of the judgment of the
High Court and would disconnect the power connection now given. Of
course, if the first respondent fails to deposit the sum of Rs.25 lakhs within G
the time fixed by us, the appellant would be free to disconnect the power
supply granted to the first respondent pursuant to the judgment of the High
Court which we have set aside herein and take all steps that may be permissible
in law for recovery of the amounts due.
A 17. The appeal is allowed in the above manner. There will be no order
as to costs. The High Court is requested to expeditiously dispose of the writ
petition afresh according to law and in the light of the observations contained
herein.
vs. Appeal allowed.
-