Steel Authority of India Ltd. v. Gupta Brother Steel Tubes Ltd.
Cited by 4 judgments in this corpus
- TATA MOTORS LIMITED v. THE BRIHAN MUMBAI ELECTRIC SUPPLY & TRANSPORT UNDERTAKING (BEST) AND OTHERS · 2023 INSC 574
- Airports Authority Of India vs Hotel Leelaventure Ltd. · 2016 SCC OnLine Del 3882
- Ms.G vs Isg Novasoft Technologies Ltd · 2014 SCC OnLine Mad 6568
- Oil And Natural Gas Corporation Limited vs Oil Country Tubular Limited · 2011 SCC Online Bom 426
These judgments mention this one. Whether each followed, distinguished or doubted it is not recorded here — read them before relying on any of it.
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 261
BROTHER STEEL TUBES LTD .
.,__ \ R.M. LODHA, J. 1. Steel Authority of India Ltd. (SAIL) has - A
preferred this appeal by special- leave aggrieved by the
judgment of High Court of Punjab and Haryana passed on May
15, 2001 whereby the learned Single Judge dismissed Revision
Petition preferred by the present appellant against the judgment
dated September 1, 1999 passed by District Judge, B
Chandigarh affirming· the judgment and order dated May 9,
1994 passed by the Court of Sub-Judge, 1st Class, Chandigarh
4 dismissing the objections preferred by the present appellant
under Sections 30/33 of the Indian Arbitration Act, 1940 and
the award dated September 7, 1993 given by the sole arbitrator c
was made rule of the Court.
2. Brief narration of facts is necessary before we embark
upon the contentions raised on behalf of the appellant. On April
--..,- 18, 1988, SAIL formulated a scheme entitled "Full Requirement D
Supply Scheme" (for short, 'the Scheme'). The said scheme is
said to have been designed for meeting the full requirements
of HR Coils/Skolps to the customers. Those who wanted to
avail the said material as per the scheme were required to
register the requirements with SAIL. The scheme further
stipulated that those who wanted material over and above what E
was likely to be available from indigenous sources and were
~ ~, willing to accept imported HR Coils were required to register
the requirements separately. The scheme was in operation in
respect of two quarters, namely, (i) July to September, 1988
and (ii) October to December, 1988. F
3. The case of the respondent is that pursuant to the terms
of said scheme, they submitted an application for 1500 metric
tones of imported material for the first quarter(July to
September, 1988). It is also their case that they furnished the G
--r financial cover in terms of the said scheme.
4. On September 15, 1988, SAIL informed their inability
to arrange for the import against the indent for reasons beyond
its control. H
A 5. The respondent, thereafter, indented for supply of 1500
~ -metric tonnes of imported material for the second quarter . . '·
(October to December, 1988). The indent was accepted by .
SAi~. The respondent furnished securities in terms of bank
guarantee in lieu of irrevocable letter of credit and took physical
B delivery of the goods on March 7, 1989 and made payment for
the same on February 15, 1989.
6. It appears that dispute/differences arose between the
parties and.the respondent lodged its claim to the appointing
c authority on March 11, 1989. Initially, one Shri K. Janardhana
was appointed as Arbitrator but he resigned later on and in his
place Shri K.P. Bhaumik was appointed arbitrator.
7. It may be noticed here that an application was made
by the respondent before the arbitrator on September 12, 1991
D for quantification of claims under the heads 'A', 'AA' and 'AAA' y-
and thereby they made a total claim of Rs. 1, 75,41,359/-
alongwith interest @ 21 per cent against SAIL before the
arbitrator.
E 8. The claimant - respondent in support of its claim
produced oral as well as documentary evidence. In opposition,
SAIL also produced oral as well as documentary evidence ;__
before the arbitrator .
. 9. The arbitrator seems to have .had fifty sittings and after
hearing the parties and taking into consideration the
documentary as well as oral evidence passed an award on
September 7, 1993. The award runs into almost 290 foolscap
pages.
G 10. The objections to the award were filed by SAIL before
Sub-Judge, 1st Class, Chandigarh raising diverse grounds, inter 't-
alia; that the arbitrator was biased in favour of the claimant; that
he committed a jurisdictional error in adjudication of claims for
the period from July to September, 1988 and granting claim in
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 263
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
;,._ 4 this regard when there was no pre-existing dispute; that the A
-i arbitrator entertained claim in respect of future disputes i.e.
~ disputes not existing at the time of reference; that he went into
constitutional questions such as discrimination, etc. which he
had no jurisdiction to decide; that he ignored the terms of
contract and returned the findings contrary to the express terms B
thereof; that the arbitrator failed to call for material documents
and gave the award which is perverse and based on no
""' evidence and that he committed jurisdictional error by ignoring
the express term of the contract, particularly Clause 7 .2 and the
provisions of the Contract Act. c
- 11. The Sub-Judge, 1st Class, Chandigarh, after hearing
... the parties overruled the objections raised by SAIL and made
the award rule of the Court on May 9, 1994. The Sub-Judge,
. --"T 1st Class, Chandigarh directed that claimant shall be entitled D to interest @ 12% per annum from the date of the judgment
until realization.
12. SAIL challenged the judgment and order dated May
9, 1994 passed by the Sub-Judge, 1st Class, Chandigarh by
filing an appeal before the District Judge, Chandigarh who by E
its decision dated September 1, 1999 dismissed the appeal.
' ,, -· 13. SAIL preferred revision petition before the High Court
of Punjab & Haryana against the aforesaid decisions. It is
pertinent to notice here that before the High Court on behalf of F SAIL, two contentions were raised, namely, (i) that the arbitrator
had committed error of jurisdiction when he entered a time
barred claim and (ii) that the Arbitrator had awarded damages
to the claimant under category 'A', 'AA' and 'C' by exercising
his power beyond Clause 7.2 of the agreement. It was thus G
-f submitted that the arbitrator committed misconduct by going
beyond the terms of the contract (7.2) and violating the
provisions of the Contract Act.
14. The High Court was not persuaded by the two
A submissions made on behalf of the SAIL and dismissed Civil ~
Revision Petition on May 15, 2001 ..
15. It is appropriate at this stage to reproduce the
arbitration clause in the agreement and Clause 7.2. which is
B material for deciding this appeal.
"ARBITRATION CLAUSE:
(i) In the event of any question, dispute or difference arising
under the conditions referred to above or any special
c conditions or Contract or in connection with this Contract
(except as to any matters, the decision of which is
specifically provided for in the conditions referred to above
or the special conditions) the same shall be referred to the
Sole Arbitration of the Chief Executive (by whatever name
0 he may be designated at the relevant time) of the Central
,,,_
Marketing Organisation, Steel Authority of India Ltd. (CMO/
SAIL) for short) or his nominee. It will be no objection that
the Arbitrator is a company's (CMO/SAIL) employee and/
or that he had to deal with the matters to which the
E Contract relates or that in the course of his duties as a
company's employees, he has expressed views on all or
any of the matters in dispute or difference. The award of ;_
the Arbitrator shall be find and binding on the parties to
this contract.
F (ii)· in the event of the Arbitrator dying, neglecting or
refusing to act or resigning or being unable to act for any
reason or his award being set aside by the court for any
reason, it shall be lawful for the Chief Executive of the
Central Marketing Organisation, Steel. Authority of India
G Ltd. to adopt/nominate another arbitrator in place of the
outgoing arbitrator in the manner aforesaid.
(iii) It is further a term of his contract that no person other
than the Chief Executive of the Central Marketing
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 265
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
- ~ Organisation, Steel Authority of India Ltd. or his nominee A
as aforesaid, shall act as Arbitrator and that, if for any
reason that is not possible, the Chief Executive of the
Central Marketing Organisation, Steel Authority of India
Ltd. shall have the right to nominate/appoint another person
as second Arbitrator and if the second Arbitrator also fails B
to arbitrate for any reason, what so ever the matter is not
to be referred to Arbitration to all.
~
(iv) The arbitrator may from time to time, with the consent
of all the parties to the contract enlarge the time for making c the award.
(v) Upon every and any such reference, the assessment
of costs incidental to the reference and award respectively
shall be in the discretion of the Arbitrator. _..,, D
(vi) Subject as aforesaid, the Arbitration Act, 1940 and the
Rules thereunder and any statutory modifications thereof,
for the time being proceedings under this clause.
·(vii) If the value of the claim in a reference exceeds Rs.1 E lakh, the Arbitrator shall give reasoned award.
(viii) The value of Arbitration shall be the place where the
contract was concluded or at Calcutta, being the
headquarters of the Central Marketing Organization, as it
may be fixed by the Arbitrator at his discretion and the F
place so fixed by the Arbitrator shall be final and binding
upon the parties to the contract.
(ix) In this clause, the expression, the Chief Executive of
the Central Marketing Organisation, Steel Authority of India G
Ltd. means the Chief Executive of the Central Marketing
Organization (by whatever name he may be designated at
the relevant time) for the time being and includes, if there
be no Chief Executive, or the Chief Executive is on leave
or he i~ absent from duty or is not available for any reason H
A whatsoever, the officer looking after the duties of the Chief . -"'--
Executive of the Central Marketing Organisation whether
in addition to his other "functions or otherwise".
Clause 7.2
B "SAIL shall supply materials as described in the offer/work
order(s)/Delivery order(s) issued by SAIL from time to time.
SAIL, however, shall have a· period of one month after ,._
expiry of the indicated quarter/quarters as grace period for
the purpose of supply or supplies. In the event of SAIL's
failure(s) to deliver the indicated quantities even after the
expiry of the grace period, SAIL shall pay to the (-
customer(s) compensation @0.25% (quarter per cent) per
month or part thereof on the value of the materials of the
supplies delayed -beyond the quarter/quarters plus the '(-
D grace period(s) subject to a maximum of 3% (three per 'l
cent ) of the value of the delayed supplies. The value for
this purpose shall be worked out on the same basis as
mentioned in note (iii) to para 3.1 regarding caiculation of
Initial Financial Cover. The aforesaid compensation shall
E be paid within th:-c2 1,-jonths from the date of completion
of order. In case an order is not executed within 12 months
from the expiry date of the grace period, the order would ~ ...
be treated as closed after payment of applicable
compensation, if and as due. Delay(s) caused in effecting
F supplies on account of or all of the force majuere
conditions and/or on account of the failure/non-observance '
of the required formalities by the customer(s) shall be
accepted the SAIL shall not bear any liability for such
period(s)."
G 16. With regard to the question relating to Clause 7.2 of
General Terms and Conditions of the Contract, the arbitrator
considered the matter thus:
"19.14 I .have given my .careful consideration to the
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 267
BROTHER STEEL TUf?ES LTD. [R. M. LODHA, J.]
arguments of the counsels for the parties. I find that the A
--- ~ compensation was to be paid by the Respondent within a
period of three months from the date of completion of the
transaction. In case the order is not executed within 12
months from the expiry of the grace period, the same was
treated as closed after payment of compensation as due. B
It is proved on record that no supply was made for July-
September 1988 quarter against the duly registered indent
'~ demand placed by the claimant and within 15 days of the
beginning of the quarter itself i.e. 15. 7.1988; the
Respondent intimated that the material will not be supplied c
to the claimant. The case, therefore, cannot fall within the
ambit of the relevant terms contained in the compensation
Clause reproduced above whereby, in case the order is
not executed within 12 months .after the expiry of the grace
_..,. period the same was to be treated as closed and that too D after payment of applicable compensation. Neither, it is a
case of delayed supply (for July September 1988
quarter's booked).
19.15 In the instant case e-ven otherwise, in this Clause is
to be brought into play the cut off date would be 30th E
October, 1989 (i.e. July-September 1988 + one month
-
.i. grace period (October 1988) + 12 months i.e. upto 30th
October, 1989 i.e. to say that after 30th October, 1989 in
the event of non-supply, the order was to be treated as
closed, but that too after the payment of applicable F
compensation i.e. 3%, as limited under Clause 7.2. In the
instant case what has happened that on 15th July, 1988
itself the Respondent regretted inability to supply the
material (vide C-5, C-7 and C-9) despite confirmed and
duly registered demand (C-3) by the claimant. No G
reference of any compensation Clause (7.2) was made
nor any cheque for the amount of compensation at the
given rate was sent nor the account of claimant was
. credited with the amount as per Clause 7.2. ObviouslyJhe
case is a case of deliberate act of non-supply as 'reasons'
beyond control as intimated in C-5, C-7 and C-9 have not
been proved by the Respondent, inspite of rigorous cross
examination by the claimant's advocate and more than the~
ample time and opportunity, at the disposal of the
Respondent. What has been contemplated in the
compensation Clause is where the force majuere Clause
is not invoked, there is complete lull or silence on the part
of the parties and a period of 12 months expires after the
expiry of grace period. In the instant case even the said
date would have been 30. 10.1989 and even then the
Respondent should/must have paid the compensation as
stipulated if they wanted to bring the case within the ambit
of Clause 7 .2, only thereafter the liability of Respondent
would have extinguished.
19.16. There is thus, substance in the contention of the
claimant that the compensation Clause as discussed
hereinabove cannot be made applicable in the fact and
circumstances duly proved on record. The alternate
argument of the Claimant regarding unconscionability of
the contract/partlcillar term thereof vis-a-vis the present
Clause 7.2 and relying on AIR 1986 SC 1571 need not
be gone into. Under issue No.15, I have attempted to set
out various clauses of document C-2, including the present
Clause and giving a finding that the Scheme C-2 is in
favour of the Respondent,-but since the findings under the
present issues are that the Clause, even otherwise, is not
applicable in the case of non-supply of material for July
September, 1988 quarter I leave the matter to rest without
going into the question of unconscionability."
17. The Sub-Judge, 1st Class, Chandigarh while dealing
with the objections of the appellant with regard to Clause 7 .2 ·
considered the matter thus:
"Sf If the above observations of the arbitrator are read
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 269
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
"'- ~ A carefully it would become clear that he never out stepped
the confines of the contract, he has remained inside the
parameters of the contract and has construed the clause
7.2 thereof. If he has committed any error in the
construction of the contract, that is an error within his i
jurisdiction. Therefore, the authority of law in Associated B
Engineering Co. vs. Government of Andhra Pradesh
:J. (ibid) is of no help to the objector. In that case the error
had arisen not by mis-reading or mis-construing or by mis-
understanding the contract but by acting contrary of what
was agreed. In that case the arbitrator had traveled outside · c
the permissible territory not by construction of the contract
but by merely looking at the same. It was held by Hon'ble
Supreme Court that if the arbitrator remained inside the
·- ')-
parameters of the contract and has construed the
provisions of the contract, his award be interfered with : D
unless he has given reasons for the award disclosing an
error apparent on the fact of it. In the present case the
arbitrator has reached the conclusion by interacting the
contract. The conclusion cannot be termed as conscious
disregard of the law or the provisions of the contract. The E
findings of the arbitrator that clause 7.2 of the scheme is
I
.. ~
not applicable on the facts and circumstances of the case
is not perverse but based on reasoning. Similarly there is
no error apparent on the face of record which would vitiate
the award. In Sudarsan Trading Co. vs. Government of F
Kera/a And Anr., AIR 1989 SC 890 (ibid) it was held that 1
if on a view taken of a contract, the decision of the
arbitrator on certain amounts awarded is a possible view
though perhaps not the only correct view, the award cannot
be examined by the court and that the court has no G .. ""( jurisdiction to substitute its own evaluation of the
I
conclusions of law or fact to come to the conclusion that
the arbitrator had acted contrary to the bargain between
the parties. It was further held that by purporting to construe
the contract the court cannot take upon itself the burden H
f.
A of saying that this was contrary to the contract. Therefore,
there is no substance in the contention of the objector that
the arbitrator has exceeded his jurisdiction by traveling .
outside the bounds of the contract and by ignoring clause
7.2 of the terms and conditions.
8
52. The next objection of the objector is that the arbitrator
not only ignored the provisions of Clause 7.2 of the contract ).
but he also ignored the provisions of Section 74 of the
Contract Act wherein it has been specified that if' a sum
c named in the contract is the amount to be paid in case of
breach, or if the contract conditions any other stipulation
by way of penalty, the party complaining of the Qreach is
only entitled to receive from the party who has broken the
contract a reasonable compensation not exceeding the --('~
D amount so named. Learned counsel argued that the
arbitrator knowingly went against this provision of law. He
further argued that in Sir Chuni Lal V. Mehta & Sons vs.
Century Spinning and Manufacturing Co. AIR 1962 SC
1314, ,the Apex Court has held that where the parties have
E deliberately specified the amount of liquidated damages,
there can be no presumption that they at the same time
intends to allow the party who had suffered by the breach
to say good bye to the sums specified and claim instead
a sum of money which was not ascertained at the date of
breach. Learned counsel further argued that the arbitrator
proceeded contrary to the settled principle of law that
damages for breach of contract by seller by failure to
deliver goods are confined to the difference between the
contract price of the goods and the market price of the
goods if the same are available in the market. Learned
counsel pointed out that in the present case the claimant r
has specifically admitted that the goods were available in
the market. It was, therefore, the duty of the claimant to
purchase the said goods from the market and the SAIL
could have only been made liable for the difference if any
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 271
j
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
~--+ between the contractual price and market price. A
53. To my mind, in view of my above finding, there is no
substance in the contention of the objector that the
arbitrator ignored the provisions of Section 74 of the
Contract Act. Once the arbitrator held that clause 7 .2 of ~ the Contract was not applicable on the facts and
--
circumstances, there can be no question of any liquidated
damages. Resultantly it cannot be said that provisions of
Section 74 of the Contract Act have been ignored. The
authority of law in Chuni Lal V. Mehta (ibid) would have c been applicable only if it was held that clause 7.2 of the
,, Contract was applicable. In Hindustan Tea Co. vs. Mis K.
Shashikant & Co. AIR 1987 SC 81, it was held that where
a reasoned award is challenged on the ground that the
,,. 't- arbitrator acted contrary to the provisions of Section 70 of
the Contract Act, it would be not ground for settling aside D
the award. On the same analogy, even if the contention of
the objector is accepted, the present award cannot be set
aside merely on the ground that the arbitrator acted
contrary to the provisions of Section 7 4 of the Contract Act. E In the similar way the contention that the provisions of Sale
.. _.., of Goods Act were not followed is also devoid of any merit
__.._ because the arbitrator gave due weight to the respective
contention of the parties and reached the conclusion which
cannot be termed as absurd."
18. When the matter came to the District Judge in appeal,
he after taking into consideration the findings recorded by the
arbitrator and the Sub-Judge, 1st Class, Chandigarh, recorded
his findings:
..-~1 "18. On careful reading of these observations of the
arbitrator, it would be clear that he never outstepped the
parameters of the contract. He remained inside the
Laxman Rekha of the contract and construed clause 7.2
thereof in a reasonable manner. If he has committed any H
272 SUPREME COURT REPORTS (2009] 14 (ADDL.) S.C.R.
error in the construction of the contract, it was error within
his jurisdiction. Therefore, the authority reported as AIR
1992 SC 232 Associated Engineering Co. vs.
Government of Andhra Pradesh does not help the
Appellant. In that case, the error had arisen not by mis
reading or misconstruing or misunderstanding the contract,
but by acting contrary to what was agreed. In that case,
the arbitrator had traveled outside the permissible territory
not by construction of the contract but by merely looking
at the same. So ft was held by Hon'ble Supreme Court that
if the arbitrator remained inside the parameters of the
, contract, and has construed the provisions of the contr.act,
his award cannot be interfered with, unless he has given
reasons for the award disclosing an error apparent on the
face of it. In the present case, the arbitrator does not
appear to have showed any conscious disregard of the law
or the provisions of the contract. So the findings of the
arbitrator that the provisions of clause 7 .2 of the scheme
are not applicable to lhe facts and circumstances of the
present case, cannot be said to be perverse. These are
manifestly based on sound reasoning which cannot be said
to be perverse. Surely there is no error apparent on the
face of the record.
19. In AIR 1989 SC 890 Sudarsan Trading Co vs.
Government of Kera/a, it inter-alia ruled that if on a view
taken of a contract, the decision of the arbitrator on certain
amounts awarded is a possible view though perhaps not
the bnly correct view, then the award cannot be examined
by the Court, and the Court has got no jurisdiction to
substitute its oWn evaluation of the conclusion of law or fact
to come to the conclusion that the arbitrator had acted
contrary to the bargain between the parties. It was further
ruled ibid that by purporting to construe the contract, the
Court cannot take upon itself the burden of saying that this
was contrary to the contract. So the learned trial Court was
t
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 273
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
.... _. justified in holding that the arbitrator had not exceeded his A
jurisdiction, nor he had traveled outside the bounds of the
contract while interpreting clause 7.2 of the scheme.
20. Surely the quantum of damages is closely inter-related
with the interpretation of clause 7.2 of the scheme. But as B
demonstrated above, the arbitrator concluded, and not
perversely or unreasonably, that clause 7.2 of the scheme
~ was not applicable to the facts of the case in hand.
Therefore, it proceeded to examine the question of
damages in paras 52 and 53 of the impugned judgment. c
21. The contention of the learned counsel for the appellant
is that not only has the arbitrator ignored the provisions of
clause 7 .2 of the contract, but he had also ignored the
,,. 't' provisions of section 7 4 of the Contract Act wherein it has
D been stipulated that if a sum named in the contract is the
amount to be paid in case of breach, or if the contract
conditions or any other stipulation by way of penalty, the
party complaining of the breach is only entitled to receive
from the party who has broken the contract, a reasonable
compensation not exceeding the amount so named. It is E
,...,.
"'
submitted by the Id. Counsel for the appellant that the
arbitrator intentionally and knowingly went against the
provisions of Section 7 4 of the Contract Act. Ld. Counsel
for the appellant has also relied on AIR 1962 SC 1314 Sir
Chuni Lal V. Mehta & Sons vs. Century Spinning and F
Manufacturing co. where it was inter-alia held that where
the parties had deliberately specified the amount of
liquidated damages, there can be no presumption that
they at the same time intended to allow the party who had
suffered by the breach to say good-bye to the .sums G
,.,.'i specified and claim instead a sum of money which was
not ascertained at the date of breach. He has further
contended that the arbitrator proceeded contrary to the
settled principle of law that damages for breach of contract·
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 275
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
----I' .,, •
"Thus, a reading of the above clause which has been A
·1· relied upon by the learned counsel for the petitioner, makes
it abundantly clear that this clause has only covered one
exigency regarding the delivery or non-delivery or late
delivery of the goods. This clause gives power to the
Arbitrator to award compensation starting from 0.25% to B
the upper limit of 2.01 %. This clause never debars the
'"' Arbitrator from entertaining the contract and consequential
losses which had been suffered by the respondent on
account of non-delivery or late delivery of the goods. If on
account of the act of the petitioner, the respondent-firm had c ... suffered huge losses to itself for the benefit of its customers, _, certainly it has a right to recover the same. Be that as it
... may, I am not to.look at the merits of the case but I have
,. ~ to examine whether the Arbitrator had exceeded beyond
the realm of arbitration clause or clauses of the contract.
If he had not, the civil court will not impose its impression/ D
judgment or opinion over the opinion of the arbitrator, but
I had already held thatthe Arbitrator is the master of facts
as well as of law. Even his erroneous interpretation of the
contract so long as he acts within the contract, is not E supposed to be interfered by the civil court much less by ,,..-
"' the High Court, in the exercise of its revisional jurisdiction."
20. Mr. Jagdeep, Dhankar, learned senior Counsel for tile
appellant urged that the stipulation in Clause 7 .2 is in
consonance with Section 74 of the Indian Contract Act 1872 F
and in that clause compensation is provided in respect of
supplies made beyond specified period; that the said clause
provides for maximum cap of liquidated damages by way of
compensation "to a maximum of three per cent of the value of
-(~ the delayed supplies" and that Clause 7.2 is a complete answer G
to any breach of the contract for whatsoever reason and,
therefore, under no situation the quantum of damages can
exceed the stipulation in the liquidated damages clause. The
learned senior Counsel would, thus, urge that the arbitrator
exceeded his jurisdiction m disregarding well settled principle H
276 SUPREME COURT REPORTS (2009) 14 (ADDL.) S.C.R.
A that where the contract incorporates liquidated damages I.,,.'\
clause, for breach of contract under no circumstances the
quantum of damages be awarded in excess of the cap "
provided therein. He strongly relied upon two Constitution Bench
decisions of this Court in the case of Sir Chunilal V. Mehta &
B Sons Ltd. vs. Century Spinning and Manufacturing Co., Ltd. 1
and Fateh Chand vs. Balkishan Dass2. He also relied upon
decisions of this Court in Oil & Natural Gas Corporation Ltd.
vs. Saw Pipes LtcP. and Tarapore & Co~ vs. State of M.P.4•
21. In Chuni/al V. Mehta & Sons, the Constitution Bench
considered Section 7 4 of the Contract Act and held that right
to claim liquidated damages is enforceable under Section 7 4 ....
of the Contract Act and where such a right is f9und to exist, no ' question of ascertaining damages really arises. It was held that ,,
where parties have deliberately specified the amount of -f .....
D liquidated damages there can be no pre:sumption that they, at
the same time, intended to allow the party who has suffered by
the breach to give a go-by to the sum specified and claim
instead a sum of money which was not ascertained or
ascertainable at the date of the breach. While construing
E Clause 14 therein, the Court held that by providing for
compensation in express terms, the right to claim damages
under the general law is necessarily excluded.
)<. .....
22. Section 74 of the Indian Contract Act fell for
F consideration before the Constitution Bench again in the case
of Fateh Chand. The Constitution Bench held thus:
"8 ..................................................................
The Section is clearly an attempt to eliminate the sometime
~\
1. AIR 1962 SC 1314.
2. AIR 1963 SC 1405.
3. , (2003) 5 sec 705.
H 4. (1994) 3-SCC 521
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 277
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
elaborate refinements made under the English common A
law in distinguishing between stipulations providing for
payment of liquidated damages and stipulations in the
nature of penalty. Under the common law a genuine pre-
estimate of damages by .mutual agreement is regarded as
a stipulation naming liquidated damages and binding B
between the parties: a stipulation in a contract in terrorem
).. is a penalty and the Court refuses to enforce it, awarding
to the aggrieved party only reasonable compensation. The
Indian Legislature has sought to cut across the web of rules
and presumptions . under the English common law, by c
enacting a uniform principle applicable to all stipulations
naming amounts to be paid in case of breach, and
stipulations by way of penalty.
-
9 .......................................................................... D
10. Section 74 of the Indian Contract Act deals with the
measure of damages in two classes of cases (1) where the
contract names a sum to be paid in case of breach and
(ii) where the contract contains any other stipulation by way
of penalty. We are in the present case not concerned to E
decide whether a contract containing a covenant of
forfeiture of deposit for due performance of a contract falls
within the first class. The measure of damages in the case
of breach of a stipulation by way of penalty is by Section
74 reasonable compensation not exceeding the penalty F
stipulated for. In assessing damages the Court has, subject
to the limit of the penalty stipulated, jurisdiction to award
such compensation as it deems reasonable having regard
to all the circumstances of the case. Jurisdiction of the
~-{
Court to award compensation in case of breach of contract G
is unqualified except as to the maximum stipulated; but
compensation has. to be reasonable, and that imposes
upon the Court duty to award compensation according to
settled principles. The section undoubtedly says that the
.
A aggrieved party is entitled to receive compensation from •
the party who has broken the contract, whether or not actual
damage or loss is proved to have been caused by the
breach. Thereby it merely dispenses with proof of "actual
loss or damage"; it does not justify the award of
B compensation when in consequence of the breach no
legal injury at all has resulted, because co.mpensation for
breach of contract can be awarded to make good loss or
damage which naturally arose in the usual course of things,
or which the parties knew when they made the contract,
c to be likely to result from the breach.
11. Before turning to the question about the compensation
which may be awarded to the plaintiff, it is necessary to
· ·~onsider whether Section 7 4 applies to stipulations for
D forfeiture of amounts deposited or paid under the contract. .of
It was urged that the section deals in terms with the right
to receive from the party who has broken the contract
reasonable compensation and not the right to forfeit what
has already been received by the party aggrieved. There
E is however, no warrant for the assumption made by some
· ofthe High Courts in India, that Section 74 applies only to
cases where the, aggrieved party is seeking to receive
some amount on breach of contract and not to cases
where upon breach of contract an amount received under
the contract is sought to be forfeited. In our judgment the
expression "the contract contains any other stipulation by
way of penalty" comprehensively applies to every covenant
involving-a penalty whether it is for payment on breach of
contract of money or delivery of property in future, or for
forfeiture of right to money or other property already ,
delivered. Duty not to enforce the penalty_clause but only I
to award reasonable compensation is statutorily imposed '>
upon courts by Section 74. In all cas.es, therefore, where
there is a stipulation in the nature of penalty for forfeiture
of an amount deposited. pursuant to the terms of contract
...
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 279
BROTHER STEEL ~USES LTD. [R. M. LODHA, J.]
which expressly provides for forfeiture, the court has A
jurisdiction to award such sum only as it considers
reasonable, but not exceeding the amount specified in the
contract as liable to forfeiture ...... n
23. In Oil and Natural Gas Corporation Ltd., while dealing 8 with the aspects of liquidated damages, this Court considered
the aforesa'd Constitution Bench decisions in Chuni Lal V.
Mehta & Sons and Fateh Chand and after reference to
relevant parts of Sections 73 and 74 of the Contract Act held
thus: c
"46. From the aforesaid sections, it can be held that when
a contract has been broken, the party who suffers by such
breach is entitled to receive compensation for any loss
which naturally arises in the usual course of things from
such breach. These sections further contemplate that if D
parties knew when they made the contract that a particular
loss is likely to result from such breach, they can agree for
payment of such compensation. In such a case, there may
not be any necessity of leading evidence for proving
damages, unless the court arrives at the conclusion that E
no loss is likely to occur because of such breach. Further,
in case where the court arrives at the conclusion that the
term contemplating damages is by way of penalty, the court
may grant reasonable compensation not exceeding the
amount so named in the contract on proof of damages. F
However, when the terms of the contract are clear and
unambiguous then its meaning is to be gathered only from
the words used therein. In a case where agreement is
executed by experts in the field, it would be difficult to hold
that . the intention of the parties was different from the G
language used therein. In such a case, it is for the party.
who contends that stipulated amount is not reasonable
compensation, to prove the same."
24. In Tarapore & Co., a two Judge Bench of this Court H
considered few decisions of this Court including the decisions
in.the.case of Mis Sudarsan Trading Co. vs. Government of
Kera/a and Anr°., Associated Engineering Co. vs. Govt. of
A.P. 6 and Managing Director, J&K Handicrafts, Jammu vs.
Good Luck Carpets7 and held that where an arbitrator travels
beyond a contract,-the award would be without jurisdiction and
the same would amount to misconduct and such award would
become amenable for being set aside by a Court.
25. In Sudarsan Trading Co., this Court held that an error
by the arbitrator relatable to interpretation of the contract is not
amenable_ to correction by courts.
26. It is not necessary to multiply the references. Suffice it
to say that the legal position that emerges from the decisions
of this Court can be summarised thus:
(i) In a case where an arbitrator travels beyond the contract,
the award would be without jurisdiction and would amount
to legal misconduct and because of which the award would
become amenable for being set aside by a Court
(ii) An error relatable to interpretation of the contract by an
arbitrator is an error within his jurisdiction and such error
is not amenable to correction by Courts as such error is
not an error on the face of the award.
(iii) If a specific question of law is submitted to the arbitrator
and he answers it, the fact that the answer involves an
erroneous decision in point of law does not make the
award bad on its face.
(iv) An award contrary to substantive provision of law or
5. (1989) 2 sec 38.
a. (1991) 4 sec 93.
H 7. (1990) 4 sec 740. -
....
{ -+ .....
-...
~
~
......
-f -~
... ,.
\
}__.,_____
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 281
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
~, ...ari. • against the terms of contract would be patently illegal. A
(v) Where the parties have deliberately ,specified the
amount of compensation in express terms, ~he party who
has suffered by such breach can only cl~im the sum
specified in the contract and not in excess therepf. In other B
words, no award of compensation in case of breach of
contract, if named or specified in the contract, could be
awarded in excess thereof.
(vi) If the conclusion of the arbitrator is based on a possible
c view of the matter, the court should not interfere with the
award.
(vii) It is not permissible to a court to examine the
.I' ."
correctness of the findings of the arbitrator, as if it were
sitting in appeal over his findings. D
27. Having noticed the legal position, we now tum to Clause
7.2 which can be analysed thus:
(i) SAIL shall supply materials as described in the offer/
E work order(s)/delivery order(s) issued from time to time.
~ (ii) SAIL shall have a period of one month as grace period ~
for the purpose of supply or supplies after expiry of the
indicated quarter(s).
(iii) S"'IL shall pay to the customer(s) compensation @ F
0.25 per cent per month or part thereof on the value of the
materials of the supplies in the event of its failure(s) to
deliver the indicated quantity e\(en after the expiry of the
grace period subject to maximum of three per cent of the G __ , value of the delayed supplies.
(iv) The compensation shall be paid within three months
from the date of completion of order.
(v) In case the order is not executed within 12 months from H
A . the expiry of grace period, the order would be treated as ,_ .........
closed after payment of applicable compensation.
(vi) SAIL shall not bear any liability for such period where
delay caused in effect of supplies is on account of failure/.
B non-observance of the required formalities by the
customer.
28. The question that needs to be determined by us is
whether the breaches alleged by the respondent are covered
by the stipulations contained in Clause 7.2. If the answer is in
affirmative, obviously compensation cannot be awarded
beyond what is provided th~rein. On the other hand, if breaches
are not covered by clause 7.2, cap provided therein with regard
. to liquidated damages will not be applicable at all.
29. Insofar as booking of July-September, 1988 quarter
-f ....__
by the respondent is concerned, it is an admitted position that
the appellant (SAIL) declined the supply of materials i.e. 1500MT
of 2mm thickness HR coils on the .ground of 'reasons beyond
control'. The arbitrator in the award observed that SAIL has
E admitted that the demand w:ic validly registered by the claimant;
that material was available in abundance specially from
domestic source and that supplies were made to others ignoring _, .
the claim of the present respondent. The arbitrator held that the '
intimation of the SAi L to the present respondent that the
F material will not be supplied to the claimant cannot fall within
the ambit of Clause 7.2.
30. Although it has been strenuously urged on behalf of the
appellant that stipulations contained in Clause 7 .~ are
comprehensive enough to include all types of breaches, on a
careful consideration thereof, we are unable to accept. the
submission made on behalf of the appellant. Can it be said that
,._,,
SAIL intended to provide for liquidated damages in the contract
even in a situation where they were unable to make supply of
materials for the reasons beyond control or they declined to .
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 283
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
"'-."""' . supply the materials on one ground or the other. The answer A
has to be plainly in the negative. It is well known that intention
of the parties to an instrument has to be gathered from the
terms thereof and that-the contract must be construed having
regard to the terms and conditions as w~ll as nature thereof.
Clause 7.2 that provides for compensation to the respondent B
for failure to supply or delayed supply of the materials by SAIL
was never intended to cover refusal to deliver the materials of
the supplies on the part of the SAIL. Refusal to supply materials
. by SAIL resulting in breach is neither contemplated nor covered
in Clause 7.2. There is no impediment nor we know of any c
obstacle for the parties to a contract to make provision of
liquidated damages for specific breaches only leaving other
types of breaches to be dealt with as unliquidated damages.
We are not aware of any principle that .once the ·provision of
} "'- liquidated damages has been made in the contract, in the D
event of breach by one of the parties, such clause has to be
read covering all types of breaches although parties may not
have intended and provided for compensation in express term~
for all types of breaches. It is not a question of giving restrictive
or wider meaning to clause 7.2 but the question is what is E intended by the parties by making a provision such as this and
""I 'i'- does such clause cover all situations of breaches by SAIL
..
31. A careful consideration of clause 7.2 would show that
it does not prescribe compensation for every type of breach;
F To name a few, breaches such as: (i) supplies of materials not
in conformity with the contract; (ii) defective materials of
supplies; (iii) deficient or short supply; (iv) different materials
of the supplies are apparently not covered by Clause 7.2. We
have indicated these breaches by way of illustration only to
G make a point that the provision in the contract for damages vide ._ i clause 7.2 cannot be said to extend to all situations and all
types of breaches. In substance and in form, the claim of
damages by the respondent for the breaches of contract by
SAIL is essentially distinct from the breaches contemplated by ·
284 SUPREME COURT REPORTS [2009) 14 (ADDL.) S.C.R.
A Clause 7.2. In this back-drop, if the High Court observed that
J Jle,. .. "'
Clause 7.2 is not panacea of all ills, it cannot be said that High
Court fell into an error. Again, the view of the arbitrator that
breach due to refusal on the part of SAIL to supply materials in
July-September, 1982 quarter does not fall within the ambit of
B relevant terms contained in the compensation Clause (7.2), by
'•no stretch of imagination can be said to be an absurd view.
The arbitrator's view about non-applicability of Clause 7 .2 for
refusa! to supply materials in July-September, 1988 quarter and
delayed supply of materials for October-December, 1988
c quarter is founded on diverse grounds elaborately discussed .
in the award. Whether this is or is not a totally correct view is
really immaterial but such view is a possible view that flows
from reasonable construction of Clause 7.2. The view of the
arbitrator being possible view on construction of Claus~_ 7.2,
~ ....
D and having not been found absurd or perverse or unreasonable
by any of the three Courts, namely , Sub-Judge, District Judge
and the High ~ourt, we are afraid, no case for interference is
made out in exercise of our jurisdiction under Article 136 of the
Constitution.
E 32. Once the arbitrator has construed clause 7.2 in a
particular manner, and such construction is not absurd and ~ ;.
appears to be plausible, it is not open to the courts to interfere ..
with the award of the arbitrator. Legal position is no more res
integra that the arbitrator having been made the final arbiter of
resolution of disputes between the parties, the award is not
open to challenge on the ground that arbitrator has reached at
a wrong conclusion. The courts do not interfere with the
conclusion of the arbitrator even with regard to construction of
a contract, if it is a possible view of the matter. The words "no
G award shall be set aside" in Section 30 mandate the courts not )- ...
to set aside the award on the ground other than those specified
in Section 30. In a case such as this, where the arbitrator has
given elaborate reasons that compensation clause 7 .2 is not
attracted for the breaches for which the compensation has been
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 285
BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
.. ,... . claimed by the respondent and such view of the arbitrator is a A
possible view, we are afraid in the circumstances award is not
amenable to correction by the court.
33. The arbitrator having taken the view in respect of
Clause 7.2 that claim of damages by the respondent of the B
breaches committed by the SAIL for refusal to supply materials
in July-September, 1988 quarter and delayed supply of the
materials for October-December, 1988 quarter did not fall within
the ambit of that clause, his further view that Section 7 4 of the
Contract Act has no application as the contract does not c determine damages for the breaches in question cannot be
said to be legally flawed. It is true that Section 74 declares the
law as to liability upon breach of contract where compensation
is by agreement of the parties pre-determined. However, in the
,,. 'r absence of any agreement specifying damages for the D. breaches alleged by the respondent, Section 7 4, in the facts
and circumstances, is not at all attracted. Seen thus, the two
decisions of the Constitution Bench of this Court in Chunilal
V. Mehta & Sons and Fateh Chand have no application to the
fact situation of the present case.
34. The learned senior counsel for the appellant would urge
~
"' that the arbitrator had no jurisdiction whatsoever to entertain the ,
claim preferred on September 12, 1991 by way of an
application indicating quantification of claims. The learned
senior counsel submitted that the claimant preferred the claim F
of about Rs. 64 lacs to the designated authority on November
3, 1989 in terms of Clause 10 of the Scheme. The designated
authority nominated initially one Shri K. Janardhana as an
arbitrator but later on appointed Shri K.P. Bhaumik as Shri K.
Janardhana submitted his resignation. Learned senior counsel G ,._ i submitted that the claim submitted on November 3, 1989,
pertained to the first quarter and for the first time, after the
arbitration proceedings had made substantial headway, the
claimant preferred an application designated as quantification
,
~ .... "-
A of claims thereby trebling the original claim of Rs. 64 lacs to
Rs.175 lacs and introducing the claim in respect of first quarter
" (July-September, 1988). He, thus, strenuously urged that
arbitrator had no jurisdiction to address the fresh claims made
on September 12, 1991.
8 35. We are not. persuaded by the aforenoted submission
of the learned senior counsel for the appellant for more than :"-one reason. For one, the aforesaid argument was not at all
canvassed before the High Court. A perusal of the judgment
c of the High Court would show that only two contentions were
raised there, namely; (i) that arbitrator committed error of
jurisdiction when he entered a time barred claim and (ii) that
the arbitrator awarded damages to the claimant under category
'A'; 'AA' and 'C' by exercising his power beyond Clause 7.2
-;. "':.
D of the agreement. We are afraid the appellant cannot be
permitted to raise a contention before this Court in an appeal
by special leave which was not raised before the High Court.
This contention is not even indirectly or remotely connected with
the plea of limitation that was canvassed before the High Court.
For another, even otherwise, we find no merit in the submission
of the learned senior counsel that fresh claim was made by the
respondent on September 12, 1991. In the claim petition filed ~
-by the respondent, in paragraph 18, it has been stated that in
view of non availability of certain details which are in
.F
possession of the respondent and otherwise, the claimant
reserves its right to add, amend and/or modify the statement ,ii--
of claims. Consequent upon the right already reserved in
paragraph 18 of the claim petition, the respondent quantified
the claims, namely, 'A', 'AA', 'AAA' vide application dated
Septembe~ 12, 1991. We find no merit that by consideration
of the claims as quantified vide application dated September ~- ...
12, 1991, the arbitrator exceeded his jurisdiction. ..
36. The learned senior counsel for the appellant also urged -~
that claim 'A' pertaining to difference in price has come to be
H determined by the arbitrator de-hors contract stipulations. In this
\
,
,.,
STEEL AUTHORITY OF INDIA LTD. v. GUPTA 287
._,, BROTHER STEEL TUBES LTD. [R. M. LODHA! J.]
..... I. regard the learned senior counsel referred to paragraph 20.21 A
and 20.22 of the award·. We are afraid, this contention too,
cannot be permitted to be raised before us since no such
contention was raised before the High Court. There has to be
some sanctity and finality attached to the decision of the
arbitrator and new plea cannot be allowed to be raised in an B
appeal under Article 136 which was not raised before the High
Court.
~
37. The learned senior counsel for the appellant vehemently
contended that the present case throws up the prescribed c jurisdiction issue wherein the ,arbitrator had chosen to function
only outside the confines of the contract and with total disregard
of express stipulations and, therefore, this Court must interfere
in the matter. He relied upon decisions of this Court in the case
> "t of Rajasthan State Mines & Minerals Ltd. Vs. Eastern
~,
Engineering Enterprises & Anr8., Food Corporation of India D
vs. Chandu Construction & Anr8., Steel Authority of India Ltd.
vs. J.C. Budharaja, Government & Mining Contractor10 and
_, Associated Engineering Co. vs. Govt. of Andhra Pradesh &
-,
Anr. 6, State of Jammu & Kashmir and Anr. vs. Dev Dutt t
' Pandit11 • E \
-
~
38. We are afraid none of the decisions cited by the
"" ' learned senior Counsel for the appellant has any application
to the facts of the present case. The courts below have
concurrently held that the arbitrator has gone into the issues of F
facts thoroughly, applied his mind to the pleadings, evidence
before him and the terms of the contract and then passed duly
considered award and no ground for setting aside the award
within the four corners of Section 30 has been made out. We
---1 8. (1991) 9 sec 283.
9 . (2001) 4 sec 697.
• 10. (1999) 8 sec 122. "
11. (1999) 1 sec 339.
288 SUPRE~E COURT REPORTS [200.9] 14 (ADDL.) S.C.R.
A have no justifiable reason to take a different view. As. noticed
above, only two grounds were urged before the High Cot1rt in
·assailing the award, one of which relating to time b(lrred claim
was ultimately notessed before us and the only argument
survived for consideration before us related to clause 7.2 of the
B contract. In what we have already discussed above, the view
of the arbitrator in this regard is a possible view.
39. Consequently, appeal has no merit and must fail. The
same is dismissed with no order as to costs.
C R.P. Appeal dismissed.