Union of India v. Pradeep Vinod Construction Company
Cited by 8 judgments in this corpus
- ANKHIM HOLDINGS PVT. LTD. & ANR. v. ZAVERI CONSTRUCTION PVT. LTD. · 2026 INSC 137
- BAKHTAWAR AHMAD RATHER Vs AIRPORT AUTHORITY OF INDIA · 2025 SCC OnLine Del 6570
- Hindustan Construction Company Ltd vs Bihar Rajya Pul Nirman Nigam Limited · 2025 INSC 1365
- CENTRAL ORGANISATION FOR RAILWAY ELECTRIFICATION v. M/S ECI SPIC SMO MCML (JV) A JOINT VENTURE COMPANY · 2024 INSC 857
- SBI GENERAL INSURANCE CO. LTD. v. KRISH SPINNING · 2024 INSC 532
- M/S. SHREE VISHNU CONSTRUCTIONS v. THE ENGINEER IN CHIEF MILITARY ENGINEERING SERVICE & ORS. · 2023 INSC 508
- ELLORA PAPER MILLS LIMITED v. THE STATE OF MADHYA PRADESH · 2022 INSC 11
- G H CENTRAL ORGANISATION FOR RAILWAY ELECTRIFICATION v. M/S ECI-SPIC-SMO-MCML (JV)JOINT VENTURE COMPANY · 2019 INSC 1394
These judgments mention this one. Whether each followed, distinguished or doubted it is not recorded here — read them before relying on any of it.
R. BANUMATHI, J.
1. These appeals arise out of the impugned judgments dated
15.05.2015 and 02.02.2015 passed by High Court of Delhi in Arbitration
Petition No.168 of 2015 and Arbitration Petition No.531 of 2014 in and
by which the High Court appointed an independent arbi trator for
adjudication of disputes between the parties, inste ad of directing
appointment of arbitrator as per Clause 64 of General Con ditions of
Contract (GCC) which stipulates that Railways’ Officers should be
appointed as Arbitrator.
2. Brief facts which led to filing of these appeals ar e as under:-
Facts in CA No.6400/2016 :-
On 14.07.2010, Northern Railways awarded the contract for
misc. civil engineering works such as construction of duty huts at
L-xings, water supply arrangements, provision of station name boards
etc. in connection with Rewari-Rohtak New Line to the respo ndent.
The total cost of the work at accepted rate came to Rs.5,30,31,369.30.
The work was finally completed on 31.03.2012. Accordi ng to the
appellant, final payments were made by the appellant to the respondent
vide bill bearing Vr.No.00356/104/C/TKJ dated 06.05.2014. On the
67
same day i.e. on 06.05.2014, parties also entered into a supplementary
agreement which recorded full accord and satisfaction as on 06.05.2014.
In the meanwhile, on 05.05.2014, respondent sent a letter to the
appellant alleging that under the compulsion of circumstances, it had to
sign the so-called final bill without protest as de sired by the
administration, otherwise heavy financial loss would have been caused
to respondent and it may not be in a position to tender and execut e
further works. The respondent averred that a sum of over Rs.1.50
crores still remains to be paid to the respondent and call ing upon the
appellant to make the payment within 90 days. The respondent vide
its letter dated 05.05.2014 invoked arbitration clause as contained under
Clause 64 of General Conditions of Contract.
3. The appellant issued a reply dated 25.07.2014 rejecting the
arbitration claim of the respondent, taking the stand that the respondent
had signed the final bill and also signed the supplementary ag reement
which clearly stipulates that it was agreed between the parti es that the
respondent has accepted the said sums mentioned therein in full and
final satisfaction of all dues and claims under the principal agreement.
4. The respondent thereafter filed Arbitration Petition No.168 of
2015 under Section 11 of the Arbitration and Conciliation Ac t, 1996
before the High Court for appointment of an arbitra tor. Upon
consideration of contention of the parties, the learned Single Judge held
that the question whether the discharge certificate and suppl ementary
agreement were signed by the respondent under duress, would require
evidence to be led and is therefore, required to be examined by the
arbitrator. So far as the appointment of arbitrator is concerned, the High
Court held that since the Railways failed to appoint an arbitrator despite
invocation of the arbitration clause by the respondent on 05.05.201 4,
the Railways forfeited its right under the arbitration cl ause and the
learned Judge appointed Mr. Ram Prakash(Retd.), District and Sessions
Judge as the sole arbitrator instead of directing the a ppointment of
arbitrator as per Clause 64 of the General Conditions of Cont ract.
Facts in CA No.6420/2016 :-
5. An agreement dated 17.01.2012 was entered into between the
Northern Railways and the respondent for construction of two lane road
over bridge in lieu of L-xing near Muradnagar Railway Station at a cost
of Rs.4,21,69,176.25/-. The work was completed on 0 3.08.2013.
According to the Railways, the respondent received ful l and final
UNION OF INDIA v. PRADEEP VINOD
CONSTRUCTION COMPANY [R. BANUMATHI, J.]
payment vide final bill bearing Vr.No.280 dated 29.01.2014 and als o
signed a supplementary agreement dated 01.03.2014 acknowledging full
and final settlement of all claims. It was also pro vided in this
supplementary agreement that the principal agreement shall stand finally
discharged and the arbitration clause contained therein shall cease to
exist. The respondent vide letter dated 15.01.2014 raised two clai ms
and requested for appointment of arbitrator. The Railways informed the
respondent that the claims of the respondent are no t referable to
arbitration as the same are covered under “excepted m atter”. The
respondent-contractor on 28.08.2014 also sent a “No Claim” letter t o
the Railway stating that it has no claim towards the R ailways and
requested for release of security deposit made by it.
6. The respondent thereafter filed Arbitration Petition No.531/
2014 under Section 11 of the Arbitration and Conciliation Ac t, 1996
seeking appointment of an arbitrator. The High Court held that though
the appellant claims that the disputes raised by the r espondent are in
the nature of “excepted matters” but that the issue can be examined
by the arbitrator. With those findings, the court appointed Mr. H.K.
Chaturvedi, advocate as Sole Arbitrator and directed that arbitration shall
take place under the aegis of the Delhi International Arbitration Centre.
7. Mr. Bharat Singh, learned counsel appearing for the appellant-
Union of India-Railways submitted that the request for appointment of
arbitrator was made before the Amendment Act, 2015 (w.e.f
23.10.2015) and hence, the proceedings will have to be proceeded in
accordance with the pre-amended provision of the Act, 1996. It was
submitted that the High Court erred in appointing an i ndependent
arbitrator instead of directing the General Manager , Railway
administration to appoint an arbitrator as per the terms and conditions
of Clause 64 of GCC which stipulates that “excepted matte rs” cannot
be referred to arbitration.
8. Per contra, Mr. Shantanu Kumar and Ms. Geetanjali Mohan,
learned counsel for the respondent(s) submitted that once the appellant
has failed to appoint an arbitrator under the terms of the agreement
before the petition under Section 11(6) of the Arbitration Act, 1996 being
filed before the Court, the authority forfeits its right o f appointing an
arbitrator and it is for the Chief Justice/Designate Judg e to appoint an
independent arbitrator under Section 11(6) of the Act. It wa s further
submitted that Section 11(6) empowers the court to deviate from the
terms of the agreement, if required, by appointing an independent
69
arbitrator. Insofar as the contention that the respondent(s) have already
received the final bill and issued “No Claim” letter to the Railway, the
learned counsel for the respondent(s) submitted tha t “No Claim”
certificate was issued under compulsion and it is nothing but due to
undue influence by the authorities and it is open to the arb itrator to
adjudicate by examining the bills which is furnished for payment and in
such circumstances, it cannot be said to be an “excepted mat ter”.
9. We have heard the learned counsel appearing for the parties.
We have carefully considered the contentions of both the parties and
perused the impugned judgment and materials on record.
10. The respondent(s) are registered contractors wi th the
Railways and they are claiming certain payments on account of the
work entrusted to them. The request of the respond ent(s) for
appointment of arbitrator invoking Clause 64 of the c ontract was
declined by the Railways stating that their claims have been settled and
the respondent(s) have issued “No Claim” certificate and executed
supplementary agreement recording “accord and satisfaction” and hence,
the matter is not referable to arbitration. Admittedly, th e request for
referring the dispute was made much prior to the Amendment Act, 2015
which came into force w.e.f. 23.10.2015. Since the request for
appointment of arbitrator was made much prior to the Amendment Act,
2015 (w.e.f. 23.10.2015), the provision of the Amended Act, 2015 shall
not apply to the arbitral proceedings in terms of Section 21 of the Act
unless the parties otherwise agree. As rightly pointed out by the learned
counsel for the appellant, the request by the respondent(s)-contrac tors
is to be examined in accordance with the Principal Act , 1996 without
taking resort to the Amendment Act, 2015.
11. Insofar as the applicability of the provisions of the Principal
Unamended Act, 1996, after referring to SP Singla Pvt. Ltd. v. State
of Himachal Pradesh and another (2019) 2 SCC 488 , in Union of
India v. Parmar Construction Company 2019 (5) SCALE 453 , it
was held as under:-
“26. We are also of the view that the Amendment Act, 2015
which came into force, i.e. on 23rd October, 2015, shall not apply
to the arbitral proceedings which has commenced in accordance
with the provisions of Section 21 of the Principal Act, 1996 before
the coming into force of Amendment Act, 2015, unless the parties
otherwise agree.
UNION OF INDIA v. PRADEEP VINOD
CONSTRUCTION COMPANY [R. BANUMATHI, J.]
27. In the instant case, the request was made and received by
the Appellants in the concerned appeal much before the
Amendment Act, 2015 came into force. Whether the application
was pending for appointment of an arbitrator or in the case of
rejection because of no claim as in the instant cas e for
appointment of an arbitrator including change/substitution o f
arbitrator, would not be of any legal effect for invo king the
provisions of Amendment Act, 2015, in terms of Section 21 of
the principal Act, 1996. In our considered view, the applications/
requests made by the Respondent contractors deserves to be
examined in accordance with the principal Act, 1996 without
taking resort to the Amendment Act, 2015 which came into force
from 23rd October, 2015.”
12. In order to appreciate the contention of the partie s, it is
necessary to refer to Clause 64 of the General Conditions of C ontract
(GCC) which reads as under:-
“64. (1) Demand for Arbitration:
64. (1) (i) In the event of any dispute or difference betwee n the
parties hereto as to the construction or operation of this contract,
or the respective rights and liabilities of the parties on any matter
in question, dispute or difference on any account or as to the
withholding by the Railway of any certificate to which the
contractor may claim to be entitled to, or if the Railway fails to
make a decision within 120 days, then and in any such case, but
except in any of the “excepted matters” referred to in C lause
63 of these Conditions, the contractor, after 120 days but within
180 days of his presenting his final claim on disputed matters shall
demand in writing that the dispute or difference be referr ed to
arbitration.
64. (1) (ii) The demand for arbitration shall specify the ma tters
which are in question, or subject of the dispute or difference as
also the amount of claim item-wise. Only such dispute (s) or
difference(s) in respect of which the demand has been mad e,
together with counter claims or set off, given by the Railw ay,
shall be referred to arbitration and other matters shall not be
included in the reference.
……….
71
64. (3) Appointment of Arbitrator:
64. (3) (a)(i) In cases where the total value of all c laims in
question added together does not exceed Rs. 25,00,000 (Rupees
twenty five lakh only), the Arbitral Tribunal shall consist of a Sole
Arbitrator who shall be a Gazetted Officer of Railway not below
JA Grade, nominated by the General Manager. The sol e
arbitrator shall be appointed within 60 days from the day w hen
a written and valid demand for arbitration is received by G M.
{Authority: Railway Board’s letter No. 2012/CE-I/CT/ARB./24,
Dated 22.10./05.11.2013}
64. (3) (a)(ii) In cases not covered by the Clause 64(3)(a) (i ),
the Arbitral Tribunal shall consist of a Panel of three Ga zetted
Railway Officers not below JA Grade or 2 Railway Gazet ted
Officers not below JA Grade and a retired Railway Off icer,
retired not below the rank of SAG Officer, as the arbitrato rs.
For this purpose, the Railway will send a panel of more than 3
names of Gazetted Railway Officers of one or more departments
of the Railway which may also include the name(s) of retir ed
Railway Officer(s) empanelled to work as Railway Arbitrator to
the contractor within 60 days from the day when a written and
valid demand for arbitration is received by the GM. Contractor
will be asked to suggest to General Manager at least 2 na mes
out of the panel for appointment as contractor’s nominee within
30 days from the date of dispatch of the request by Railway.
The General Manager shall appoint at least one out of them as
the contractor’s nominee and will, also simultaneously appoint the
balance number of arbitrators either from the panel or from
outside the panel, duly indicating the ‘presiding arbitrator’ from
amongst the 3 arbitrators so appointed. GM shall complete this
exercise of appointing the Arbitral Tribunal within 30 days from
the receipt of the names of contractor’s nominees. While
nominating the arbitrators, it will be necessary to ensure that one
of them is from the Accounts Department. An officer of Selection
Grade of the Accounts Department shall be considered of equal
status to the officers in SA grade of other departments of the
Railway for the purpose of appointment of arbitrator.
64. (7) Subject to the provisions of the aforesaid Arbitration and
Conciliation Act, 1996 and the Rules thereunder and any
UNION OF INDIA v. PRADEEP VINOD
CONSTRUCTION COMPANY [R. BANUMATHI, J.]
statutory modifications thereof shall apply to the arbi tration
proceedings under this Clause.”
13. It is seen from the above that under Clause 64(1) of GC C,
if there is any dispute or differences between the parties or the
respective rights and liabilities of the parties on any matter in question
or any other ancillary dispute arising from the terms of the contrac t or
if the railway administration fails to make a decision wi thin the time
stipulated thereon, then in any such case, but except i n any of the
“excepted matters”, the General Manager may nominate the of ficer
by designation as referred to under Clause 64(3)(a) (i) and a(ii)
respectively with further procedure being prescribe d for the sole
arbitrator or the Arbitral Tribunal to adjudicate the dispute/differences
arising under the terms of the contract between the part ies.
14. In Union of India and another v. M.P. Gupta (2004) 10
SCC 504 , Union of India and another v. V.S. Engineering (P) Ltd.
(2006) 13 SCC 240 , Union of India v. Singh Builders Syndicate
(2009) 4 SCC 523 and in a catena of judgments, the court held tha t
whenever the agreement specifically provides for appointment of named
arbitrators, the appointment of arbitrator should be in terms of the
contract. After referring to M.P. Gupta , in V.S. Engineering , it was
held as under:-
“3. The learned Additional Solicitor General appearing for the
appellant Union of India has pointed out that as per clauses 63
and 64 of the General Conditions of Contract, this Court in no
uncertain terms has held that the Arbitral Tribunal ha s to be
constituted as per the General Conditions of Contract, the High
Court should not interfere under Section 11 of the Act and the
High Court should accept the Arbitral Tribunal appointed by the
General Manager, Railways. In this connection, the learned ASG
invited our attention to a decision of this Court directly bearing
on the subject in Union of India v. M.P. Gupta (2004) 10 SCC
504 wherein a similar question with regard to appointment of the
Arbitral Tribunal for the Railways with reference to cl ause 64
of the General Conditions of Contract came up before this Court
and this Court held that where two gazetted railway officers are
appointed as the Arbitral Tribunal, the High Court should not
appoint a retired Judge of the High Court as a sole arb itrator
and the appointment of sole arbitrator was set asid e. The
73
conditions of clauses 63 and 64 of the General Conditions of
Contract are almost analogous to the one we have in our hand.
In that case also relying on clause 64 of the contract a thre e-
Judge Bench presided over by the Chief Justice of India observed
as follows: (SCC p. 505, para 4)
“4. In view of the express provision contained therein that two
gazetted railway officers shall be appointed as arbitrators, Justice
P.K. Bahri could not be appointed by the High Court as the sole
arbitrator. On this short ground alone, the judgment and order
under challenge to the extent it appoints Justice P.K. Bahri as
sole arbitrator is set aside. Within 30 days from t oday, the
appellants herein shall appoint two gazetted railway offic ers as
arbitrators. The two newly appointed arbitrators shall enter int o
reference within a period of another one month and thereafter
the arbitrators shall make their award within a period of three
months.””
The court, however observed in para (6) that in the case of public
institutions which are slow in responding to the request made by the
contractor for appointment of an arbitrator, the power of the High Court
to appoint an arbitrator under Section 11 is not taken away. The failure
of the authorities in appointing an arbitrator and when the c ontractor
approached the court for appointment of an arbitrator under Sec tion
11 of the Act, it will then be in the discretion of the Chi ef Justice/
designated Judge to appoint a railway officer as per t he contract or a
High Court Judge.
15. Considering the various matters of railway contracts and
setting aside the appointment of independent arbitrators, after referring
to M.P. Gupta and V.S. Engineering and other judgments, in Parmar
Construction Company , this Court set aside the appointment of the
independent arbitrator and directed the General Man ager of the
Railways to appoint arbitrator in terms of Clause 64(3) of the agreement.
In paras (44) and (45), this Court held as under:-
“44. To conclude, in our considered view, the High Court was
not justified in appointing an independent arbitrator wit hout
resorting to the procedure for appointment of an arbitrator which
has been prescribed under Clause 64(3) of the contract under
the inbuilt mechanism as agreed by the parties.
UNION OF INDIA v. PRADEEP VINOD
CONSTRUCTION COMPANY [R. BANUMATHI, J.]
45. Consequently, the orders passed by the High Cou rt are
quashed and set aside. The Appellants are directed to appoint
the arbitrator in terms of Clause 64(3) of the agreement w ithin
a period of one month from today under intimation to each of
the Respondents/contractors and since sufficient time has b een
consumed, at the first stage itself, in the appointme nt of an
arbitrator and majority of the Respondents being th e petty
contractors, the statement of claim be furnished by each of t he
Respondents within four weeks thereafter and the arbitrator may
decide the claim after affording opportunity of hearing to the
parties expeditiously without being influenced/inhibited by the
observations made independently in accordance with law.”
The ratio of the above decision squarely applies to the case i n
hand. When the agreement specifically provides for appointment of
named arbitrators, the appointment should be in terms of the agreement.
The High Court, in our view, was not right in appointing an independent
arbitrator ignoring Clause 64 of the General Conditions of C ontract.
16. Insofar as the plea of the appellant that there was settlement
of final bill/issuance of “No Claim” letter, the lear ned counsel for the
appellant has drawn our attention on Clause 43(2) – Signing of the
“No Claim” Certificate and submitted that as per Clause 43(2), the
contractor signs a “No Claim” certificate in favour of t he railway in
the prescribed format after the work is finally measure d up and the
contractor shall be debarred from disputing the correctness of the items
covered under the “No Claim” certificate or demanding a clearance to
arbitration in respect thereof. On behalf of the respondent, it has been
seriously disputed that issuance of “No Claim” certificat e as to the
supplementary agreement recording accord and satisfac tion as on
06.05.2014 (CA No.6400/2016) and issuance of “No Claim” certificate
on 28.08.2014 (CA No.6420/2016) that they were issu ed under
compulsion and due to undue influence by the railway authorities. We
are not inclined to go into the merits of the contention of th e parties.
It is for the arbitrator to consider the claim of the respond ent(s) and
the stand of the appellant-railways. This contention raised by the parties
are left open to be raised before the arbitrator.
17. In the result, the impugned judgments dated 15.05.2015 and
02.02.2015 of the High Court of Delhi in Arbitration Petition No .168
of 2015 and Arbitration Petition No.531 of 2014 are set aside and these
75
appeals are allowed. The appellant is directed to appoint the arbitrator
in terms of Clause 64(3) of the agreement within a period of one month
from today under intimation to the respondent(s)-contractors. As soon
as the communication of the appointment of arbitrator is made to the
respondent(s), the statement of claim be filed by the respondent(s) within
six weeks thereafter and the reply of the appellant to be fi led within
four weeks thereafter. The arbitrator shall proceed wit h the matter in
accordance with law and decide the claim after affording suf ficient
opportunity of hearing to both parties expeditiously preferably within a
period of four months.
Ankit Gyan Appeals allowed.
UNION OF INDIA v. PRADEEP VINOD
CONSTRUCTION COMPANY [R. BANUMATHI, J.]